Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Sep-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Idaho scientific collection, transportation, and federal permits | B: 165. Obtain necessary permits and set up contract for genetic analysis | 04/30/2015 | 03/27/2015 | |
Electrofishing collection of bull trout below Albeni Falls Dam | C: 157. Electrofishing to collect bull trout below Albeni Falls Dam | 04/30/2015 | 04/30/2015 | |
Implanting of radio tags | D: 158. Implant combination radio acoustic or radio transmitter into bull trout | 04/30/2015 | 04/30/2015 | |
Bull trout transported above Albeni Falls Dam when water temperature approaches 18 C | E: 28. Transport bull trout above Albeni Falls Dam | 04/30/2015 | 04/30/2015 | |
Genetic Analysis | F: 157. Rapid response genetic analysis of bull trout biopsy samples | 04/30/2015 | 04/30/2015 | |
Tracking of radio tagged fish with aircraft, vehicle, and boat. | G: 157. Mobile tracking surveys by fixed wing aircraft, boat, and vehicle | 04/30/2015 | 04/30/2015 | |
Temporary upstream trap installed and operated at Albeni Falls Dam, Idaho | H: 184. Temporary upstream trap installed at Albeni Falls Dam, Idaho | 04/30/2015 | 03/01/2015 | |
Analyzed data for annual technical report. | I: 162. Analysis of bull trout radiotelemetry data | 04/30/2015 | 04/30/2015 | |
Annual maintenance of monitoring equipment | J: 70. Annual overhaul and recalibration of ground receiver stations | 04/30/2015 | 04/30/2015 | |
Electrofishing and angling data entry | K: 157. Compile electronic spreadsheet database of electrofishing data | 04/30/2015 | 02/05/2015 | |
Downloading stationary ground radio receiver | L: 157. Download stationary ground radio receiving stations | 04/29/2015 | 04/26/2015 | |
Data analysis of tracking data | M: 162. Data reduction and analysis | 04/15/2015 | 04/15/2015 | |
Project coordination among stakeholders | N: 189. Project coordination among all stakeholders | 04/30/2015 | 04/30/2015 | |
All administrative tasks fulfilled with timely quality products | O: 119. Manage Project | 04/30/2015 | 04/30/2015 | |
Attach Progress Report in Pisces | P: 132. Submit Annual Report for the period (5/1/2013) to (4/30/2014) | 04/30/2015 | 04/30/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 05/01/2014 | ||||||
B | 165 | Obtain necessary permits and set up contract for genetic analysis | 05/01/2014 | ||||||
C | 157 | Electrofishing to collect bull trout below Albeni Falls Dam | 05/01/2014 | ||||||
D | 158 | Implant combination radio acoustic or radio transmitter into bull trout | 05/01/2014 | ||||||
E | 28 | Transport bull trout above Albeni Falls Dam | 05/01/2014 | ||||||
F | 157 | Rapid response genetic analysis of bull trout biopsy samples | 05/01/2014 | ||||||
G | 157 | Mobile tracking surveys by fixed wing aircraft, boat, and vehicle | 05/01/2014 | ||||||
H | 184 | Temporary upstream trap installed at Albeni Falls Dam, Idaho | 05/08/2014 | ||||||
I | 162 | Analysis of bull trout radiotelemetry data | 05/01/2014 | ||||||
J | 70 | Annual overhaul and recalibration of ground receiver stations | 05/01/2014 | ||||||
K | 157 | Compile electronic spreadsheet database of electrofishing data | 05/01/2014 | ||||||
L | 157 | Download stationary ground radio receiving stations | 05/01/2014 | ||||||
M | 162 | Data reduction and analysis | 05/01/2014 | ||||||
N | 189 | Project coordination among all stakeholders | 05/01/2014 | ||||||
O | 119 | Manage Project | 05/01/2014 | ||||||
P | 132 | Submit Annual Report for the period (5/1/2013) to (4/30/2014) | 05/01/2014 |