Environmental compliance is current. |
B: 165. Ensure environmental compliance is current |
|
09/30/2021 |
09/30/2021 |
BPA Project management complete. |
C: 119. Manage BPA Project |
|
09/30/2021 |
|
Approximately 150,000 spring Chinook salmon acclimated & released into the Hood River |
D: 176. Acclimate and release BY 19 spring Chinook salmon into the West Fork Hood River. |
|
04/30/2021 |
04/14/2021 |
Collect and incubate approximately 326,000 eggs to provide approximately 218,000 eyed eggs for Parkdale and Round Butte hatcheries. |
E: 176. Incubate BY 20 spring Chinook salmon eggs |
|
11/30/2020 |
11/30/2020 |
Rear BY 20 juvenile spring Chinook salmon at PFH and MFFF. |
F: 176. Rear BY 20 juvenile spring Chinook salmon |
|
06/30/2021 |
06/30/2021 |
Collect and spawn BY 2021 adult spring Chinook salmon |
G: 176. BY 2021 spring Chinook salmon brood stock collection and spawning. |
|
09/30/2021 |
|
Approximately 150,000 Hood River origin spring Chinook marked with an adipose fin clip. |
H: 158. Fin clip BY 2020 Chinook reared at PFH and MFFF. |
|
07/31/2021 |
07/29/2021 |
Approximately 50,000 50-20 winter steelhead smolts acclimated & released into the Hood River. |
I: 176. Acclimate and release BY20 winter steelhead in the Hood River subbasin. |
|
05/15/2021 |
05/05/2021 |
Fish health maintained at PFH and MFFF. |
J: 60. Maintain adult and juvenile fish health at Parkdale Hatchery and Moving Falls Fish Facility. |
|
09/30/2021 |
09/30/2021 |
Fully functional HRPP facilities. |
K: 61. Operate and maintain PFH, MFFF, Dee Hwy office and Oak Springs Hatchery residence |
|
09/30/2021 |
09/30/2021 |
Salmon educational curriculum and public tours completed. |
L: 99. Public outreach and education. |
|
09/30/2021 |
|
2021 annual operating plan. |
M: 174. Produce and update 2021 Annual Operation Plan. |
|
09/30/2021 |
09/30/2021 |
HRPP Coordination |
N: 191. Hood River Production Program Coordination |
|
09/30/2021 |
09/30/2021 |
Twelve monthly reports |
O: 141. Other Reports for BPA |
|
09/30/2021 |
09/30/2021 |
Summary of HRPP fish culture activities during Oct. 1, 2019 through Sept. 30, 2020 |
P: 132. FY 2020 Annual Report. |
|
04/14/2021 |
04/14/2021 |
Council step process and ISRP response completed. |
Q: 196. Complete responses to questions in ISRP 2020-2 regarding Spring Chinook |
|
09/30/2021 |
07/21/2021 |
NPCC Anadromous Fish Habitat and Hatchery Review for Hood River Basin projects and ISRP response loop completed. |
R: 122. Complete NPCC’s Anadromous Fish Review for CTWS sponsored Hood River basin projects. |
|
09/30/2021 |
09/30/2021 |