Project 2007-325-00 - Wenatchee River Complexity Fisheries Enhancement
Project Number:
2007-325-00
Title:
Wenatchee River Complexity Fisheries Enhancement
Summary:
The Chelan County Natural Resource Department (CCNRD) Wenatchee Complexity contract (200732500) will construct several fish habitat complexity projects to benefit Upper Columbia spring Chinook, steelhead and bull trout. The life cycle of the projects will span several performance periods. The first performance period is from September 27, 2007 through September 26, 2008. During this performance period, the following will be accomplished:
1. Survey, design, permitting, pre-monitoring and construction for CMZ 11.
2. Survey, and beginning permitting for CMZ N4 and CMZ 6.

The Work Elements for this performance period will include:
WE 165: Produce Environmental Compliance Documents
WE 119: Manage and Administer Projects
WE 189: Regional Coordination
WE 185: Produce PISCES Status Reports
WE 175: Produce Design and/or Specifications for CMZ N4
WE 175: Produce Design and/or Specifications for CMZ 6
WE 175: Produce Design and/or Specifications for CMZ 11
WE 157: Pre-construction Level I effectiveness monitoring for CMZ 11
WE 30: Construct designed project for CMZ 11
WE 47: Vegetate disturbed sites at CMZ 11
WE 132: Produce Annual Progress Report for 09/27/2007 to 09/26/2008

Work Elements for the 09/27/2008 to 09/26/2009 will include:
WE 165: Produce Environmental Compliance Documents
WE 119: Manage and Administer Projects
WE 189: Regional Coordination
WE 185: Produce PISCES Status Reports
WE 175: Produce Design and/or Specifications for CMZ N4
WE 175: Produce Design and/or Specifications for CMZ 6
WE 157: Pre-construction Level I effectiveness monitoring for CMZ N4
WE 157: Pre-construction Level I effectiveness monitoring for CMZ 6
WE 157: Post-construction Level I effectiveness monitoring for CMZ 11
WE 30(?): Construct designed project for CMZ N4; work element may change depending upon design input from DOT and USDA Forest Service
WE 30(?): Construct designed project for CMZ 6; work element may change depending upon design input from DOT
WE 47: Vegetate disturbed sites at CMZ N4
WE 47: Vegetate disturbed sites at CMZ 6
WE 132: Produce Annual Progress Report for 09/27/2008 to 09/26/2009

Work Elements for the 09/27/2009 to 09/26/2010 will include:
WE 165: Produce Environmental Compliance Documents
WE 119: Manage and Administer Projects
WE 189: Regional Coordination
WE 185: Produce PISCES Status Reports
WE 157: Post-construction Level I effectiveness monitoring for CMZ N4
WE 157: Post-construction Level I effectiveness monitoring for CMZ 6
WE 47: Vegetate disturbed sites at CMZ N4
WE 47: Vegetate disturbed sites at CMZ 6
WE 132: Produce Annual Progress Report for 09/27/2009 to 09/26/2010
Proposer:
None
Proponent Orgs:
Chelan County (Govt - Local)
Starting FY:
2007
Ending FY:
2014
BPA PM:
Stage:
Area:
Province Subbasin %
Columbia Cascade Wenatchee 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Columbia River Spring ESU
Steelhead - Upper Columbia River DPS
Trout, Bull
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
None
BiOp Association:
FCRPS 2008 – view list of FCRPS 2008 BiOp Actions

Tributary Habitat Implementation 2007 to 2009,
Tributary Habitat Implementation 2007 to 2009,
Tributary Habitat Implementation 2007 to 2009

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2011 $2,016 100%
2010 $37,600 4%
2009
2008
2007

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
36533 SOW Chelan County 200732500 EXP UPA CHELAN CO - WENATCHEE COMPLEXITY PROGR. History $1,440,461 9/27/2007 - 6/1/2010
46466 SOW Chelan County 2007-325-00 EXP UPA WENATCHEE COMPLEXITY History $852,527 3/1/2010 - 11/30/2011



Annual Progress Reports
Expected (since FY2004):4
Completed:3
On time:3
Status Reports
Completed:18
On time:8
Avg Days Late:31

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
36533 46466 2007-325-00 EXP UPA WENATCHEE COMPLEXITY Chelan County 09/27/2007 11/30/2011 History 18 51 0 0 1 52 98.08% 0
Project Totals 18 51 0 0 1 52 98.08% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 2007-325-00-NPCC-20090924
Project: 2007-325-00 - Wenatchee River Complexity Fisheries Enhancement
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: ISRP fundable in part:as per ISRP comments, funding is provided for securing land owner agreements and implementation plans. Funding for implementation is contingent for favorable ISRP and Council review of implementation plans.

Independent Scientific Review Panel Assessment

Assessment Number: 2007-325-00-ISRP-20060831
Project: 2007-325-00 - Wenatchee River Complexity Fisheries Enhancement
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria - In Part
Final Round ISRP Comment:
Reconnecting potential floodplain habitats is definitely worthwhile, but this proposal does not provide enough information to enable a technical evaluation of the merits of each project individually. In some of the site descriptions there was insufficient information on how the berms/levees/roads would be breached or otherwise removed to reconnect the river with potential floodplain habitats, or what habitat conditions (e.g., acres of wetland ponds, riparian terraces, side channels, etc.) would be created after access is restored. Without this information, it was difficult to assess the potential benefits of each site scientifically.

Therefore, the ISRP recommends partial funding for this project until the plans for each site are more fully developed and landowner agreements are finalized. Given the high total cost of the reconnecting the five floodplain sites, each location should be treated as an individual project and justified more completely. It is highly likely that these floodplain reconnection projects could have real benefits to fish and wildlife in the Wenatchee subbasin, but each area deserves a more complete description, a landowner agreement, and a reasonable monitoring plan. We suggest that funding be provided for securing agreements and developing thorough engineering plans, with implementation contingent on preparation of more complete proposals for each site.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 2007-325-00-INLIEU-20090521
Project Number: 2007-325-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: No Problems Exist
Cost Share Rating: None
Comment: Channel realignment, LWD etc on private lands.

Capital Assessment

Assessment Number: 2007-325-00-CAPITAL-20090618
Project Number: 2007-325-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: None

Name Role Organization
Carolyn Pearson (Inactive) Interested Party EcoA.I.M., Inc.
Alan Schmidt (Inactive) Supervisor Chelan County
Douglas Corkran (Inactive) Env. Compliance Lead Bonneville Power Administration
Mike Kaputa Administrative Contact Chelan County
Joseph Connor Project Manager Bonneville Power Administration
Peter Lofy Supervisor Bonneville Power Administration
Kathryn (CC) Bangs (Inactive) Administrative Contact Chelan County
Jennifer Hadersberger (Inactive) Technical Contact Chelan County
Mike Kane (Inactive) Technical Contact Chelan County
Matt (Chelan Cnty) Shales (Inactive) Project Lead Chelan County