Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Audrey Ahmann | Walla Walla County Conservation District (SWCD) | Yes | Contract Manager | audrey.ahmann@wwccd.net | (509) 522-6340x107 |
Sarah Branum | Bonneville Power Administration | Yes | COR | stbranum@bpa.gov | (503) 230-5115 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Rick Jones | Walla Walla County Conservation District (SWCD) | Yes | Supervisor | rick.jones@wwccd.net | (509) 522-6340x110 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Rachel Rounds | Bonneville Power Administration | Yes | Interested Party | rarounds@bpa.gov | (503) 230-3967 |
Jennifer Stolz | Bonneville Power Administration | No | Env. Compliance Lead | jpstolz@bpa.gov | (503) 230-3233 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
BPA contract requirements complete | B: 119. Manage Gose Street passage project | 01/31/2009 | 12/31/2008 | |
Attach Progress Report in Pisces | C: 132. Submit Progress Report for the period 8/1/08 to 7/31/09 | 12/31/2008 | 12/31/2008 | |
Project completed according to PE stamped design | D: 184. Complete Gose Street fish passage structures | 11/15/2008 | 11/15/2008 | |
Documentation and assistance to support BPA's Environmental Compliance Group | E: 165. Ensure project environmental compliance is current | 11/15/2008 | 11/15/2008 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
B | 119 | Manage Gose Street passage project | 02/09/2007 | ||||||
C | 132 | Submit Progress Report for the period 8/1/08 to 7/31/09 | 02/09/2007 | ||||||
D | 184 | Complete Gose Street fish passage structures | 07/14/2008 | ||||||
E | 165 | Ensure project environmental compliance is current | 02/09/2007 |