Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 38941: 198805307 EXP PARKDALE BERM DESIGN/CONSTRUCT
Project Number:
Title:
Hood River Production Operations and Maintenance (O&M)-Warm Springs
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
38941
Contract Title:
198805307 EXP PARKDALE BERM DESIGN/CONSTRUCT
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Tenneson Engineering Corporation proposes to undertake the required engineering and construction management services to obtain completion of the proposed flood protection dike work on the Jack Sanders property and adjacent Red Hill Road near Parkdale, Oregon, just south of BPA's Parkdale Fish Facility.  Time is of the essence in carrying ahead with this project to conduct the actual construction during the fall of 2008 (now spring of 2009).

The work will be divided into two phases.  Phase One will consist of the required design and related permitting work to get the project under a construction subcontract.  Phase Two will be the construction management of the selected subcontractor working under Tenneson Engineering Corporation to build the dike, together with as-builts and a final engineering report.

BPA may hire an independent inspector under a separate contract and Tenneson will coordinate with the inspector as needed.
Account Type(s):
Expense
Contract Start Date:
08/08/2008
Contract End Date:
07/15/2009
Current Contract Value:
$83,162
Expenditures:
$83,162

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project goes as planned B: 119. Manage Project 07/15/2009 07/15/2009
All permits in place before construction of berm C: 165. Work with BPA on Environmental Compliance needs 09/15/2008 11/30/2008
Final designs, specs, and cost estimate complete D: 175. Phase 1: Prepare final designs & specifications for Parkdale Berm 12/31/2008 03/31/2008
Engineer's final report submitted E: 100. Phase 2: Manage construction of Parkdale Berm 07/10/2009 07/15/2009
Berm constructed to specifications F: 61. Phase 2: Construct berm to protect Parkdale Fish Facility 06/30/2009 05/27/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 119 Manage Project 02/09/2007
C 165 Work with BPA on Environmental Compliance needs 02/09/2007
D 175 Phase 1: Prepare final designs & specifications for Parkdale Berm 02/09/2007
E 100 Phase 2: Manage construction of Parkdale Berm 02/09/2007
F 61 Phase 2: Construct berm to protect Parkdale Fish Facility 08/20/2008
G 132 Final designs, specs, & engineer's final report will substitute for annual report 02/09/2007