Province | Subbasin | % |
---|---|---|
Blue Mountain | Imnaha | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Briana Anderson | Fish Passage Center | No | Interested Party | banderson@fpc.org | (503) 230-4099 |
Mickey Carter | Bonneville Power Administration | No | Interested Party | macarter@bpa.gov | (503) 230-5885 |
James Harbeck | Nez Perce Tribe | Yes | Interested Party | jimh@nezperce.org | (541) 432-2501 |
Arleen Henry | Nez Perce Tribe | No | Administrative Contact | arleenh@nezperce.org | (208) 621-3833 |
Jay Hesse | Nez Perce Tribe | No | Supervisor | jayh@nezperce.org | (208) 621-3552 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Brian Michaels | Nez Perce Tribe | Yes | Contract Manager | brianm@nezperce.org | (541) 432-2507 |
David Roberts | Bonneville Power Administration | Yes | COR | daroberts@bpa.gov | (503) 230-4511 |
Jennifer Stolz | Bonneville Power Administration | Yes | Env. Compliance Lead | jpstolz@bpa.gov | (503) 230-3233 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Ensure Environmental Compliance Requirements Have Been Met | A: 165. Ensure Environmental Compliance Requirements Have Been Met | 01/01/2009 | 01/01/2009 | |
Install and remove screw traps | B: 70. Install and remove screw traps | 07/31/2009 | 06/10/2009 | |
Operate Juvenile Screw Trap | C: 157. Operate Juvenile Screw Trap | 07/31/2009 | 06/10/2009 | |
PIT Tag Natural Origin Steelhead | D: 158. PIT Tag Natural Origin Steelhead | 07/31/2009 | 06/10/2009 | |
Collect PIT Tag Data | E: 157. Collect PIT Tag Data | 12/31/2009 | 12/31/2009 | |
Analyze PIT Tag Data | F: 162. Analyze PIT Tag Data | 12/31/2009 | 12/31/2009 | |
Analyze Length and Weight Data | G: 162. Analyze Length and Weight Data | 12/31/2009 | 12/31/2009 | |
Upload/Download PIT Tag Data to/from the PTAGIS Database | H: 159. Upload/Download PIT Tag Data to/from the PTAGIS Database | 12/31/2009 | 12/31/2009 | |
Download River Flow and Temperature Data | I: 159. Download River Flow and Temperature Data | 12/31/2009 | 12/31/2009 | |
Disseminate Summary Reports | J: 161. Disseminate Summary Reports | 12/31/2009 | 12/31/2009 | |
Local and Regional Smolt Monitoring Project Planning | K: 122. Local and Regional Smolt Monitoring Project Planning | 12/31/2009 | 12/31/2009 | |
Attend Smolt Monitoring and Fish Production Coordination Meetings | L: 189. Attend Smolt Monitoring and Fish Production Coordination Meetings | 12/31/2009 | 12/31/2009 | |
Public Outreach for Fisheries Education | M: 99. Public Outreach For Fisheries Education | 12/31/2009 | 06/26/2009 | |
Attach 2008 Progress Report in Pisces | N: 132. Submit Progress Report for the period Jan 2008 to Dec 2008 | 10/31/2009 | ||
Quarterly Reports | O: 141. Quarterly Reports | 12/31/2009 | 12/31/2009 | |
Manage and Administer Project | P: 119. Manage and Administer Project | 12/31/2009 | 12/31/2009 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Ensure Environmental Compliance Requirements Have Been Met | 02/09/2007 | ||||||
B | 70 | Install and remove screw traps | 02/09/2007 | ||||||
C | 157 | Operate Juvenile Screw Trap | 02/09/2007 | ||||||
D | 158 | PIT Tag Natural Origin Steelhead | 02/09/2007 | ||||||
E | 157 | Collect PIT Tag Data | 02/09/2007 | ||||||
F | 162 | Analyze PIT Tag Data | 02/09/2007 | ||||||
G | 162 | Analyze Length and Weight Data | 02/09/2007 | ||||||
H | 159 | Upload/Download PIT Tag Data to/from the PTAGIS Database | 02/09/2007 | ||||||
I | 159 | Download River Flow and Temperature Data | 02/09/2007 | ||||||
J | 161 | Disseminate Summary Reports | 02/09/2007 | ||||||
K | 122 | Local and Regional Smolt Monitoring Project Planning | 02/09/2007 | ||||||
L | 189 | Attend Smolt Monitoring and Fish Production Coordination Meetings | 02/09/2007 | ||||||
M | 99 | Public Outreach For Fisheries Education | 02/09/2007 | ||||||
N | 132 | Submit Progress Report for the period Jan 2008 to Dec 2008 | 02/09/2007 | ||||||
O | 141 | Quarterly Reports | 02/09/2007 | ||||||
P | 119 | Manage and Administer Project | 02/09/2007 | ||||||
Q | 185 | Periodic Status Reports for BPA | 02/09/2007 |