Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 42333: 1996-083-00 EXP BIOP CTUIR GRAND RONDE SUBBASIN RESTORATION 09
Project Number:
Title:
CTUIR Grand Ronde Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
42333
Contract Title:
1996-083-00 EXP BIOP CTUIR GRAND RONDE SUBBASIN RESTORATION 09
Contract Continuation:
Previous: Next:
37002: 1996-083-00 EXP CTUIR GRANDE RONDE SUBBASIN RESTORATION
  • 47504: 1996-083-00 EXP BIOP CTUIR GRAND RONDE SUBBASIN RESTORATION 10
Contract Status:
Closed
Contract Description:
The Confederated Tribes of the Umatilla Indian Reservation (CTUIR) propose ongoing fish habitat protection, restoration and enhancement, maintenance, and monitoring activities under the CTUIR Grande Ronde Subbasin Restoration Project (199608300) to achieve the vision, goals, and objectives established in the Grande Ronde Subbasin Plan (NPCC, 2004) and the Northwest Power and Conservation Council (NPCC) Fish and Wildlife Program (NPPC 2000).  The Project plans, designs, implements, maintains, and monitors habitat protection, enhancement and restoration projects in the Subbasin with a primary goal of protecting high quality habitat and restoring/enhancing degraded habitats to support the recovery of focal species, including Threatened Snake River spring-summer Chinook salmon and summer steelhead.  

In FY 2010, the Project will focus on implementing the Ladd Marsh, Upper Grande Ronde Tailings, McCoy Creek, and Meadow Creek (Habberstad) projects.  Ladd Marsh is being implemented in cooperation with ODFW with the Grande Ronde Project in cooperation with the Wallowa-Whtiman National Forest.  Project development and planning for 2010-2012 project activities will be ongoing with initial site survey and conceptual project planning on several potential project areas in the Upper Grande Ronde and Catherine Creek watersheds.  In addition to these activities, project staff will conduct additional revegetation activities at the McCoy Meadows Restoration Project Area, as well as conduct annual project maintenance and monitoring/evaluation.

A budget of $589,500 is requested to perform watershed restoration-related tasks associated with several project areas.  Funds provided under this contract are utilized to conduct pre-project planning, administration, project maintenance, monitoring and evaluation, as well as developing cost-share proposals to support restoration project implementation from various sources.
Account Type(s):
Expense
Contract Start Date:
05/01/2009
Contract End Date:
04/30/2010
Current Contract Value:
$503,483
Expenditures:
$503,483

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Allen Childs Umatilla Confederated Tribes (CTUIR) Yes Contract Manager allenchilds@ctuir.org (541) 429-7940
Jason Grant Umatilla Confederated Tribes (CTUIR) Yes Interested Party jasongrant@ctuir.org (541) 729-7730
Tracy Hauser Bonneville Power Administration Yes COR tlhauser@bpa.gov (503) 230-4296
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Rosemary Mazaika Bonneville Power Administration Yes F&W Approver rxmazaika@bpa.gov (503) 230-5869
Leslie Naylor Umatilla Confederated Tribes (CTUIR) No Interested Party lesnaylor@ctuir.org (541) 429-7942
Paul Rabb Umatilla Confederated Tribes (CTUIR) No Administrative Contact paulrabb@ctuir.org (541) 429-7165
Donald Rose Bonneville Power Administration No Env. Compliance Lead dlrose@bpa.gov (503) 230-3796
Jim Webster Umatilla Confederated Tribes (CTUIR) No Supervisor jameswebster@ctuir.org (541) 429-7240


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Receipt of environmental compliance clearance from BPA. A: 165. Produce Environmental Compliance Documentation 04/30/2010 04/30/2010
Conduct ongoing project development and coordination activities B: 114. CTUIR Grande Ronde Subbasin Restoration Coordination 04/30/2010 04/30/2010
Complete BiOp project solicitation C: 114. Solicit, review and select BiOp expense & capital projects - FY2010-2012 04/30/2010 04/30/2010
Implement Meadow Creek (Habberstad) Project D: 29. Implement large wood additions on Meadow Creek (Habberstad) Project 08/21/2009 07/31/2009
Assist in the administration of the initial phase of the Ladd Creek Restoration Project E: 119. Assist ODFW with Ladd Creek Restoration Project (Ladd Marsh Wildlife Area) 03/31/2010 03/31/2010
Implement McCoy Meadows Enhancement Project F: 119. Manage and administer McCoy Meadows Enhancement Project 04/30/2010
Assist in the administration of the initial phase of the UGRR Tailings Project G: 119. Assist USFS LaGrande Ranger District with UGRR Tailings Project 03/31/2010 03/31/2010
Conduct planting on Meadow Creek Project H: 47. Plant Vegetation on Meadow Creek Project 04/30/2010 03/19/2010
Conduct vegetation maintenance I: 22. Maintain vegetation 04/30/2010 04/30/2010
Conduct project maintenance J: 186. Maintain instream structures, fences, and off-channel water developments 11/27/2009 11/27/2009
Complete data collection K: 157. Monitoring & Evaluation CTUIR GR Subbasin Restoration Project 03/31/2010 03/31/2010
Complete data analysis and interpretation L: 162. Analyze and Interpret M&E Data 03/31/2010 03/31/2010
Complete outreach and education activities M: 99. Public Outreach and Education 04/30/2010 03/30/2010
Conduct ongoing project administration and management N: 119. Manage and Administer CTUIR GR Subbasin Restoration Project 04/30/2010 04/30/2010
Progress Report O: 132. Initiate development of FY2009 Annual Report 04/30/2010
Prepare Hydrologic and Hydraulic Assessment of South Fork Willow Creek Q: 115. Conduct South Fork Willowa Hydrologic Analysis to evaluate 2006 End Creek Restoration Project 04/30/2010 04/30/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental Compliance Documentation 02/09/2007
B 114 CTUIR Grande Ronde Subbasin Restoration Coordination 02/09/2007
C 114 Solicit, review and select BiOp expense & capital projects - FY2010-2012 02/09/2007
D 29 Implement large wood additions on Meadow Creek (Habberstad) Project 07/22/2009
E 119 Assist ODFW with Ladd Creek Restoration Project (Ladd Marsh Wildlife Area) 02/09/2007
F 119 Manage and administer McCoy Meadows Enhancement Project 02/09/2007
G 119 Assist USFS LaGrande Ranger District with UGRR Tailings Project 02/09/2007
H 47 Plant Vegetation on Meadow Creek Project 02/09/2007
I 22 Maintain vegetation 04/30/2009
J 186 Maintain instream structures, fences, and off-channel water developments 03/17/2009
K 157 Monitoring & Evaluation CTUIR GR Subbasin Restoration Project 03/17/2009
L 162 Analyze and Interpret M&E Data 02/09/2007
M 99 Public Outreach and Education 02/09/2007
N 119 Manage and Administer CTUIR GR Subbasin Restoration Project 02/09/2007
O 132 Initiate development of FY2009 Annual Report 02/09/2007
P 185 Periodic Status Reports for BPA 02/09/2007
Q 115 Conduct South Fork Willowa Hydrologic Analysis to evaluate 2006 End Creek Restoration Project 04/02/2010