Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 43868: 2003-011-00 EXP TRASK COLUMBIA R/ESTUARY HABITAT
Project Number:
Title:
Columbia River Estuary Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 50.00%
Lower Columbia Columbia Lower 50.00%
Contract Number:
43868
Contract Title:
2003-011-00 EXP TRASK COLUMBIA R/ESTUARY HABITAT
Contract Continuation:
Previous: Next:
40221: 2003-011-00 EXP COLUMBIA R/ESTUARY HABITAT (TRASK & ASSOC.)
Contract Status:
Closed
Contract Description:
The contractor will provide technical support/planning services and review in support of the Action Agency efforts directly addressing habitat BiOp requirements that the Action Agencies are responsible for satisfying.  The contractor will work under the direction of the Action Agencies in close coordination with the Estuary Partnership and other interested regional parties.
Account Type(s):
Expense
Contract Start Date:
09/01/2009
Contract End Date:
09/30/2010
Current Contract Value:
$179,000
Expenditures:
$179,000

* Expenditures data includes accruals and are based on data through 28-Feb-2025.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
30 km
20 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Sandra Coveny PC Trask and Associates No Contract Manager sandra@pctrask.com (503) 517-0706
Marchelle Foster Bonneville Power Administration Yes COR mmfoster@bpa.gov (503) 230-3446
Corie Peters PC Trask and Associates No Administrative Contact corie@pctrask.com (971) 271-8492
Phil Trask PC Trask and Associates Yes Supervisor phil@pctrask.com (503) 240-3973
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing 5 of 5 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A78515185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$2,0001.12%01/01/201009/30/2010
B78516132Produce Progress (Annual) ReportAnnual Reports for BPAContractor will draft and submit a FY09 annual report detailing progress implementing the pile structure program and development of the Action Agency restoration project approval process and methodology. The report will document milestones accomplished as well as outstanding issues in program development. This report will be submitted the BPA Project Manager by the attaching the report as an attachment to Pisces.$2,0001.12%07/01/201009/30/2010
C78517122Provide Technical Review and RecommendationTechnical Support and GuidanceThe Pile Structure Program as envisioned in RPA 38 establishes a new pile structure program. Significant effort has been expended by the Estuary Partnership and the Action Agencies to guide the new program toward project implementation. In the next fiscal year, the Estuary Partnership will move to test program hypothesis by monitoring site conditions and performing environmental compliance activities. It is likely that actual implementation of pile structure removal or enhancement will occur. The contractor will provide technical support guidance to the Estuary Partnership and the Action Agencies to ensure successful and timely implementation.$5,5003.07%09/01/200909/30/2010
D78518114Identify and Select ProjectsStrategic Habitat IdentificationThe goal of this work element is to help move estuary habitat project selection from opportunistic to strategic by utilizing emerging scientific tools currently available. In 2008, a demonstration project using the ecosystem classification system, salmonid genetic information, and a project assessment of Reach F, provided a new basis for identifying projects in the estuary. A steering committee and temporary expert panel was formed to help guide the development of priority project types and geographic areas. This project builds upon the 2008 project by expanding the project to apply similar concepts to two additional reaches in the estuary. This includes the development of GIS products that depicts potential projects in terms of habitat capacity (restoration of hydrologically connected sites) and habitat opportunity (opening sites to salmonid use where dikes or levees have cut them off). This will be accomplished using available estuary tools including Lidar, t-sheets, Ortho layers, historical photos, field visits, and communications with local entities engaged in project development. Draft products will be developed in coordination with the Estuary Partnership, the Lower Columbia Fish Recovery Board, Washington Department of Fish & Wildlife, Oregon Department of Fish & Wildlife, CREST, Columbia Land Trust, Cowlitz Tribe, watershed councils, and conservation districts. Special attention will be directed to project development efforts initiated by the Estuary Partnership and the Columbia Land Trust. This project also provides technical support to Bonneville Power Administration for implementation of the pile structure program, development of the ecosystem classification system, and regional monitoring.$166,50093.02%09/01/200909/30/2010
E78519119Manage and Administer ProjectsManage and Administer ProjectsPerform tasks as needed to assist Bonneville Power Administration in accrual process.$3,0001.68%09/01/200909/30/2010
      
$179,000
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
FY09 Annual Progress Report B: 132. Annual Reports for BPA 09/30/2010 09/30/2010
Technical Support and Policy Guidance C: 122. Technical Support and Guidance 09/30/2010 09/30/2010
Refine and Implement Estuary Habitat Priorities D: 114. Strategic Habitat Identification 09/30/2010 09/30/2010
Manage and Administer Contract E: 119. Manage and Administer Projects 09/30/2010 09/30/2010

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 122 Provide Technical Review and Recommendation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 132 Annual Reports for BPA 02/09/2007
C 122 Technical Support and Guidance 02/09/2007
D 114 Strategic Habitat Identification 02/09/2007
E 119 Manage and Administer Projects 02/09/2007