Contract 44709: 198710002 EXP UMATILLA ANAD FISH HABITAT- ODFW
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Oregon Department of Fish and Wildlife (ODFW)
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
44709
Contract Title:
198710002 EXP UMATILLA ANAD FISH HABITAT- ODFW
Contract Continuation:
Previous: Next:
39122: 1987-100-02 EXP UMATILLA ANAD. FISH HABITAT
  • 50161: 1987-100-02 EXP UMATILLA ANAD FISH HABITAT- ODFW
Contract Status:
Closed
Contract Description:
The Umatilla River Subbasin Fish Habitat Improvement Program (UFHIP) is responsible for the protection, enhancement, and rehabilitation of stream ecosystems on private lands within the Umatilla River Subbasin.  Project activities are implemented under long-term agreements with landowners.  Past activities include the construction of grazing control fences and off-channel watering facilities, fish passage barrier remediation, channel rehabilitation, native plant enhancement and management of noxious weeds.

Proposed activities for FY 2010 include the removal of an unneeded diversion dam (Joliff property), stream channel rehabilitation, removal of exotic vegetation, and planting of native vegetation.  The UFHIP also proposes to maintain 275 acres of riparian and stream habitat within the Umatilla River Subbasin.  Specifically, 14 miles of fence, 11 off-channel watering facilities, and 117 acres of native vegetation will be maintained to meet program objectives.  Two surface flow monitoring systems and 11 temperature probes will be operated and maintained throughout the contract period.  The project will also monitor the status and trends of water temperature, stream flows and fish habitat in the Birch and Meacham Creek watersheds.
Account Type(s):
Expense
Contract Start Date:
10/01/2009
Contract End Date:
09/30/2010
Current Contract Value:
$243,629
Expenditures:
$243,629

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Umatilla River Subbasin Fish Habitat Improvement Program B: 119. Umatilla River Subbasin Fish Habitat Improvement Program 09/30/2010 09/24/2010
Environmental Compliance for FY 2010 C: 165. Environmental Compliance for FY 2010 09/30/2010 09/24/2010
Watershed and Habitat Restoration Outreach and Education D: 99. Watershed and Habitat Restoration Outreach and Education 09/30/2010 09/24/2010
Identify and Select Projects in the Umatilla River Subbasin E: 114. Identify and Select Projects in the Umatilla River Subbasin 09/30/2010 09/24/2010
Lease Riparian Area on Birch Creek F: 92. Lease Riparian Area on Birch Creek 09/30/2010 09/24/2010
Lease Riparian Area on Twomile Creek G: 92. Lease Riparian Area on Twomile Creek 09/30/2010 09/24/2010
East Birch Creek Dam Removal and Joliff Property Restoration H: 175. East Birch Creek Dam Removal and Joliff Property Restoration Bid Package 06/30/2010 09/24/2010
Remove Joliff Dam on East Birch Creek I: 85. Remove Joliff Dam on East Birch Creek 09/30/2010 09/24/2010
Rehabilitate Stream Channel Around Removed East Birch Creek Joliff Dam J: 30. Rehabilitate Stream Channel Around Removed East Birch Creek Dam 09/30/2010 09/24/2010
Add Cross-vanes and J-hooks Around Removed East Birch Creek Joliff Dam K: 29. Add Cross-vanes and J-hooks Around Removed East Birch Creek Dam 09/30/2010 09/24/2010
Maintain Fence L: 186. Maintain Fence 09/30/2010 09/24/2010
Maintain Instream Structures M: 186. Maintain Instream Structures 09/30/2010 09/24/2010
Control Noxious Weeds in Riparian Buffer on Birch and East Birch Creeks N: 22. Control Noxious Weeds in Riparian Buffer on Birch and East Birch Creeks 09/30/2010 09/24/2010
Irrigate Willows Planted in Riparian Buffer on Kinzua Property O: 22. Irrigate Willows Planted in Riparian Buffer on Kinzua Property 09/30/2010 09/24/2010
Maintain Trees Planted in the Riparian Buffer on East Birch Creek P: 22. Maintain Trees Planted in the Riparian Buffer on East Birch Creek 09/30/2010 09/24/2010
Plant Cottonwoods on Rupp (Houser) Property Q: 47. Plant Cottonwoods on Rupp (Houser) Property 09/30/2010 09/24/2010
Plant Cottonwoods on Kinzua Property R: 47. Plant Cottonwoods on Kinzua Property 09/30/2010 09/24/2010
Operate and Maintain Flow Gauging Stations S: 157. Operate and Maintain Flow Gauging Stations 09/30/2010 09/24/2010
Effectiveness Monitoring T: 157. Effectiveness Monitoring 09/30/2010 09/24/2010
2009 Annual Progress Report U: 132. 2009 Annual Progress Report 05/15/2010 05/18/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 2 instances of WE 92 Lease Land
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 119 Umatilla River Subbasin Fish Habitat Improvement Program 02/09/2007
C 165 Environmental Compliance for FY 2010 02/09/2007
D 99 Watershed and Habitat Restoration Outreach and Education 02/09/2007
E 114 Identify and Select Projects in the Umatilla River Subbasin 02/09/2007
F 92 Lease Riparian Area on Birch Creek 10/01/2009
G 92 Lease Riparian Area on Twomile Creek 10/01/2009
H 175 East Birch Creek Dam Removal and Joliff Property Restoration Bid Package 02/09/2007
I 85 Remove Joliff Dam on East Birch Creek 05/27/2010
J 30 Rehabilitate Stream Channel Around Removed East Birch Creek Dam 05/27/2010
K 29 Add Cross-vanes and J-hooks Around Removed East Birch Creek Dam 05/27/2010
L 186 Maintain Fence 10/01/2009
M 186 Maintain Instream Structures 10/01/2009
N 22 Control Noxious Weeds in Riparian Buffer on Birch and East Birch Creeks 02/01/2010
O 22 Irrigate Willows Planted in Riparian Buffer on Kinzua Property 09/30/2009
P 22 Maintain Trees Planted in the Riparian Buffer on East Birch Creek 10/01/2009
Q 47 Plant Cottonwoods on Rupp (Houser) Property 10/01/2009
R 47 Plant Cottonwoods on Kinzua Property 10/01/2009
S 157 Operate and Maintain Flow Gauging Stations 10/01/2009
T 157 Effectiveness Monitoring 10/01/2009
U 132 2009 Annual Progress Report 02/09/2007