Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 47101: 200845500 EXP STURGEON MANAGEMENT
Project Number:
Title:
Sturgeon Management
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Columbia Upper Middle 100.00%
Contract Number:
47101
Contract Title:
200845500 EXP STURGEON MANAGEMENT
Contract Continuation:
Previous: Next:
41810: 200845500 EXP YN MOA STURGEON MANAGEMENT
  • 52389: 2008-455-00 EXP STURGEON MANAGEMENT
Contract Status:
Closed
Contract Description:
The goal of the White Sturgeon Management project, at some point in the future, is to release juvenile sturgeon to restore existing stocks and to re-introduce sturgeon to areas where natural production is limited in the Mid-Columbia River.  The fish will be reared on the Yakama Reservation at the Prosser and Marion Drain Hatcheries.  The project will operate by cost sharing between BPA and the Yakama Nation.  

The first phase of the project (including this contract period, April 1, 2010 - March 31, 2011) will include the development and refinement of sturgeon culture techniques using captive brood in preparation for wild stock.  The Yakama Nation is holding nearly 100 broodstock from various projects throughout the Columbia River Basin.  The YN project does not propose building new hatchery facilities or releasing hatchery-reared sturgeon during Phase I.  Phase I identifies hatchery evaluation and development work to be completed concurrent with the CRITFC comprehensive strategic and hatchery master planning which will clarify appropriate applications and objectives for hatchery sturgeon in the lower mid-Columbia River (downstream from Priest Rapids).   YN Phase I involves a short term contract with the Bonneville Power Administration and does not include the development of significant new facilities.  YN Phase II might include significant new facilities contingent on the outcome of the strategic and master planning process.  Work will be completed by Yakama Tribal fishery program staff in coordination with fishery co-managers from other treaty tribes and the states.  Hatchery activities will occur primarily at established Tribal Facilities at Prosser and Marion Drain Hatcheries, and may involve limited temporary modifications.
Account Type(s):
Expense
Contract Start Date:
04/01/2010
Contract End Date:
03/31/2011
Current Contract Value:
$129,768
Expenditures:
$129,768

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Hannah Dondy-Kaplan Bonneville Power Administration No Env. Compliance Lead hadondy-kaplan@bpa.gov (503) 230-4071
Loverne George Yakama Confederated Tribes No Administrative Contact geol@yakamafish-nsn.gov (509) 865-5121x6364
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Donella Miller Yakama Confederated Tribes Yes Contract Manager mild@yakamafish-nsn.gov (509) 945-0132
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
David Roberts Bonneville Power Administration Yes COR daroberts@bpa.gov (503) 230-4511
Bob Rose Yakama Confederated Tribes No Supervisor rosb@yakamafish-nsn.gov (509) 388-3871
Thomas Scribner Yakama Confederated Tribes Yes Interested Party scrt@yakamafish-nsn.gov (503) 331-9850
Nancy Weintraub Bonneville Power Administration No Interested Party nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Produce environmental clearances for the project. A: 165. Obtain environmental clearances for project 06/01/2010 05/31/2010
Rear Captive Brood B: 63. Rear Captive Brood 03/31/2011 03/31/2011
Collect Field Data C: 157. Collect Field Data 03/31/2011 03/31/2011
Feasibility of White Sturgeon Culture for use in Restoration/ Mitigation to Mid-Columbia River D: 176. White Sturgeon Restoration/ Mitigation to Mid-Columbia River 03/31/2011 03/31/2011
Funding Package - Submit draft to COTR E: 119. Manage and Administer project 01/03/2011 01/03/2011
Workshop Participation F: 189. Workshop Participation 03/31/2011 03/31/2011
Draft Strategic Plan Review & Comment G: 174. Draft Strategic Plan Review & Comment 03/31/2011 03/31/2011
Annual Report for the period April 2009 to March 2010 I: 132. Begin Preparing Progress Report for the period April 2009 to March 2010 12/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sturgeon, White (A. transmontanus) - Lower Columbia River
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 63 Rear Fish
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain environmental clearances for project 04/01/2010
B 63 Rear Captive Brood 04/17/2009
C 157 Collect Field Data 03/01/2010
D 176 White Sturgeon Restoration/ Mitigation to Mid-Columbia River 04/17/2009
E 119 Manage and Administer project 04/01/2010
F 189 Workshop Participation 04/01/2010
G 174 Draft Strategic Plan Review & Comment 04/01/2010
H 185 Periodic Status Reports for BPA 04/01/2010
I 132 Begin Preparing Progress Report for the period April 2009 to March 2010 04/01/2010