| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| EC documents obtained for this contract | B: 165. Provide EC documentation to BPA | 10/31/2011 | 08/10/2011 | |
| Project managed. Draft contracting package including the SOW, LIB, & PI submitted to COTR. | C: 119. Manage and administer project | 06/30/2011 | 06/30/2011 | |
| Install PIT tag arrays | D: 70. Install permanent in-stream PIT tag arrays (3 total in upper Yakima Basin) in preselected locations | 08/01/2011 | 08/01/2011 | |
| PIT tag O. mykiss in upper Yakima Basin tributaries and mainstem areas | E: 158. PIT tag Juvenile O. Mykiss in select locations | 10/14/2011 | 10/14/2011 | |
| PIT tag recapture data | F: 159. Upload PIT tag data to PTAGIS database | 10/14/2011 | 10/14/2011 | |
| O. mykiss abundance and bio-sampling | G: 157. O. Mykiss abundance and bio sampling | 10/14/2011 | 10/14/2011 | |
| Generate VSP metrics considering life history expression | H: 162. Generate abundance of life history types in pre selected locations | 10/14/2011 | 10/14/2011 | |
| Analyze Genetic samples to disaggregate MPG into population | I: 162. Analyze Genetic samples to disaggregate MPG into population | 08/01/2011 | 06/01/2011 | |
| Generate Prespawn population estimates (run escapement) | J: 162. Generate pre-spawning steelhead population estimates | 08/01/2011 | 08/01/2011 | |
| Produce Annual Report | K: 132. Submit Progress Report for the contract period | 10/14/2011 | 10/14/2011 | |
| Present resident/anadromous interactions study progress/ findings at the YBS&M conference | L: 161. Present resident/anadromous interactions study at YBS&M conference | 07/01/2011 | 06/16/2011 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 10/15/2010 | ||||||
| B | 165 | Provide EC documentation to BPA | 10/15/2010 | ||||||
| C | 119 | Manage and administer project | 10/15/2010 | ||||||
| D | 70 | Install permanent in-stream PIT tag arrays (3 total in upper Yakima Basin) in preselected locations | 07/18/2011 | ||||||
| E | 158 | PIT tag Juvenile O. Mykiss in select locations | 04/18/2011 | ||||||
| F | 159 | Upload PIT tag data to PTAGIS database | 10/15/2010 | ||||||
| G | 157 | O. Mykiss abundance and bio sampling | 04/18/2011 | ||||||
| H | 162 | Generate abundance of life history types in pre selected locations | 10/15/2010 | ||||||
| I | 162 | Analyze Genetic samples to disaggregate MPG into population | 10/15/2010 | ||||||
| J | 162 | Generate pre-spawning steelhead population estimates | 10/15/2010 | ||||||
| K | 132 | Submit Progress Report for the contract period | 10/15/2010 | ||||||
| L | 161 | Present resident/anadromous interactions study at YBS&M conference | 10/15/2010 |