Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
Previous: | Next: |
---|---|
56065 REL 18: 2007-246-00 EXP PNNL RESTORATION OF BULL TROUT PASS |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Martin Allen | Bonneville Power Administration | Yes | COR | mballen@bpa.gov | (503) 230-5115 |
Amber Allman | Pacific Northwest National Laboratory | No | Contract Manager | amber.allman@pnnl.gov | (509) 375-2039 |
Brian Bellgraph | Pacific Northwest National Laboratory | Yes | Supervisor | brian.bellgraph@pnnl.gov | (509) 371-7185 |
Desmond Gelman | Bonneville Power Administration | No | CO Assistant | dxgelman@bpa.gov | (503) 230-4960 |
Kristen Jule | Bonneville Power Administration | Yes | F&W Approver | krjule@bpa.gov | (503) 230-3588 |
Joe Maroney | Kalispel Tribe | Yes | Interested Party | jmaroney@knrd.org | (509) 447-7272 |
Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
Jennifer Snyder | Bonneville Power Administration | Yes | Env. Compliance Lead | jasnyder@bpa.gov | (503) 230-4187 |
Janie Vickerman | Pacific Northwest National Laboratory | Yes | Administrative Contact | janie.vickerman@pnnl.gov | (509) 371-7260 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Ensure environmental compliance requirements are complete | B: 165. Complete environmental compliance requirements | 04/30/2018 | 04/30/2018 | |
3 new sites and new antenna at fish trap | C: 70. Install new telemetry equipment | 06/30/2017 | 06/30/2017 | |
Functioning radio monitoring stations throughout study period | D: 157. Maintain and download radio receiving stations | 04/30/2018 | 04/30/2018 | |
Develop a profile of each fish tracked | E: 162. Data reduction and analysis | 02/28/2018 | 02/28/2018 | |
Completed Annual Report | F: 132. Submit Progress Report for the period 1 Jan 2017 through 31 Dec 2017 | 04/30/2018 | ||
All administrative tasks fulfilled with timely quality products | G: 119. Manage Project | 04/30/2018 | 04/30/2018 | |
Testing and calibration of all monitoring stations, or remove stations | H: 70. Test all stations prior to next monitoring season, if applicable. Otherwise, uninstall equipment. | 04/30/2018 | 04/24/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 05/01/2017 | ||||||
B | 165 | Complete environmental compliance requirements | 05/01/2017 | ||||||
C | 70 | Install new telemetry equipment | 05/01/2017 | ||||||
D | 157 | Maintain and download radio receiving stations | 05/01/2017 | ||||||
E | 162 | Data reduction and analysis | 05/01/2017 | ||||||
F | 132 | Submit Progress Report for the period 1 Jan 2017 through 31 Dec 2017 | 05/01/2017 | ||||||
G | 119 | Manage Project | 05/01/2017 | ||||||
H | 70 | Test all stations prior to next monitoring season, if applicable. Otherwise, uninstall equipment. | 05/01/2017 |