Contract 58390: 199802100 EXP HOOD RIVER FISH HABITAT
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
58390
Contract Title:
199802100 EXP HOOD RIVER FISH HABITAT
Contract Continuation:
Previous: Next:
54380: 1998-021-00 EXP HOOD RIVER FISH HABITAT
  • 62296: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Status:
Closed
Contract Description:
ADMINISTRATIVE SUMMARY
The Confederated Tribes of the Warm Springs Reservation of Oregon
Hood River Production Program
6030 Dee Highway
Parkdale, Oregon 97041
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer: Arthur Mitchell (541) 553-3219
Hood River Production Program Coordinator:  Chris Brun (541) 806-0293
Technical Contact:  Joe McCanna (541) 352-9326

FISCAL YEAR 2013

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, project planning and implementation activities.

OBJECTIVE 2.  Coordinate and implement Hood River Watershed Action Plan.

OBJECTIVE 3.  Add large wood to West Fork Hood River to restore fish habitat complexity.

OBJECTIVE 4. Continue  long term trend pesticide monitoring in the Hood River subbasin.

OBJECTIVE 5. Partner with Columbia Gorge Fruit Growers to plant spray buffer vegetation along selected stream reaches.

OBJECTIVE 6.  Begin development of a water conservation plan for the East Fork Irrigation District

OBJECTIVE 7.  Conduct aquatic habitat surveys in the East Fork Hood River.

OBJECTIVE 8. Acquire logs for instream wood placement projects.

OBJECTIVE 9. Maintain existing riparian exclosure fences.
Account Type(s):
Expense
Contract Start Date:
10/01/2012
Contract End Date:
09/30/2013
Current Contract Value:
$251,226
Expenditures:
$251,226

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All work complies with environmental regulations B: 165. Work with BPA on Environmental Compliance requirements. 10/31/2012 10/31/2012
FY 2012 Annual Progress Report complete C: 132. Prepare and submit annual report for FY12 work 04/30/2013 04/30/2013
Project administration requirements completed D: 119. Manage Project 09/30/2013 09/30/2013
Pesticide trend assessment in Hood River subbasin throughout 2013 spray application season E: 115. Pesticide assessment in Hood River Subbasin. 09/30/2013 09/30/2013
Hood River Watershed Group support F: 114. Provide implementation support 09/30/2013 09/30/2013
Add LWD to Red Hill Cr. and West Fork Hood River G: 29. Implement Red Hill Large Wood Placement 09/30/2013
Riparian fences maintained. H: 186. Maintain riparian fences 09/02/2013 09/02/2013
1,000 riparian shrubs planted along Neal, Odell and Evans Creeks. I: 47. Plant riparian vegetation to reduce orchard spray drift from entering creeks. 09/30/2013 09/30/2013
Complete canal mapping and pipe sizing for East Fork Irrigation District's water conveyance system J: 175. East Fork Irrigation District water conservation plan. 09/30/2013 09/30/2013
East Fork Hood River Stream Survey K: 115. East Fork Aquatic Habitat Survey 09/30/2013 09/30/2013
Obtain 225 mbf of logs. L: 29. Obtain logs for instream placement projects. 09/30/2013 09/30/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2012
B 165 Work with BPA on Environmental Compliance requirements. 10/01/2012
C 132 Prepare and submit annual report for FY12 work 10/01/2012
D 119 Manage Project 10/01/2012
E 115 Pesticide assessment in Hood River Subbasin. 11/21/2012
F 114 Provide implementation support 10/01/2012
G 29 Implement Red Hill Large Wood Placement 04/01/2013
H 186 Maintain riparian fences 10/01/2012
I 47 Plant riparian vegetation to reduce orchard spray drift from entering creeks. 10/01/2012
J 175 East Fork Irrigation District water conservation plan. 10/01/2012
K 115 East Fork Aquatic Habitat Survey 11/21/2012
L 29 Obtain logs for instream placement projects. 12/26/2012