| 53025: 2010-001-00 EXP TYEE RANCH FLOODPLAIN ENHANCEMENT AND COMPLEXITY |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Obtain required permits prior to 2013 construction of project. | A: 165. Complete EC Permitting Process | 01/14/2014 | 01/14/2014 | |
| Fulfill all administrative tasks with quality products and in a timely manner. | B: 119. Lead coordination efforts for project implementation | 01/14/2014 | 01/14/2014 | |
| Stakeholder Coordination | C: 191. Lead Coordination for Watershed Restoration | 01/14/2014 | 01/14/2014 | |
| Installation of riparian vegetation | D: 47. Riparian Planting | 05/31/2013 | 05/31/2013 | |
| Installation of riparian vegetation | E: 47. Floodplain Planting | 06/30/2013 | 06/15/2013 | |
| Monitoring plan | F: 174. Prepare Monitoring Plan for Post Planting Mortality | 01/14/2014 | 01/14/2014 | |
| Fence Installation | G: 40. Livestock Exclusion Fence Installation | 08/31/2013 | 08/31/2013 | |
| Water Facility | H: 34. Watering Facility Construction | 07/15/2013 | 07/15/2013 | |
| Attach Progress Report in Pisces | J: 132. Submit Progress Report for the period Jan 2013 to Dec 2013 | 01/14/2014 | 01/14/2014 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
| Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Complete EC Permitting Process | 01/15/2013 | ||||||
| B | 119 | Lead coordination efforts for project implementation | 01/15/2013 | ||||||
| C | 191 | Lead Coordination for Watershed Restoration | 01/15/2013 | ||||||
| D | 47 | Riparian Planting | 06/01/2012 | ||||||
| E | 47 | Floodplain Planting | 06/28/2011 | ||||||
| F | 174 | Prepare Monitoring Plan for Post Planting Mortality | 06/28/2011 | ||||||
| G | 40 | Livestock Exclusion Fence Installation | 06/28/2011 | ||||||
| H | 34 | Watering Facility Construction | 06/28/2011 | ||||||
| I | 185 | Periodic Status Reports for BPA | 01/15/2013 | ||||||
| J | 132 | Submit Progress Report for the period Jan 2013 to Dec 2013 | 01/15/2013 |