Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 61265: 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Project Number:
Title:
Lapwai Creek Anadromous Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
61265
Contract Title:
2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
57048: 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
  • 64969: 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract Changes for April-July--No Cost Time Extension

This contract was amended for a no cost time extension (NCTE) to extend the contract from 4/30/2014 to 7/31/2014.  The specific WEs that were changed include U,V Z, and AB.  The NCTE purpose is to allow for the completion of the identified items.  The NCTE is needed in order to complete field implementation of fence, water development and wetland due to not getting environmental compliance requirements completed, and a landowner seeding  fields where projects would be located. The project can commence once the fields are harvested so there is not a crop loss.

CONTRACT AMENDMENT DESCRIPTION:

WE U AND V  
WE U and V are components of a project located at the same site along Mission Creek.  Project installation was delayed due to cultural resources clearance.  Cultural resources clearance was obtained on 4/2/2014, however, the landowner had seeded spring crops at the project site on March 27, 2014.  The landowner is reluctant to install the identified measures until after the crop is harvested (estimated at 6/30/2014) due to a loss of income from damaged crops.   The water development requires the excavation of a pipeline which is within the crop field.  The installation of the fence requires driving through the crop field and along the cropland border in order to auger the fence post holes and install the posts.  The landowner is completing the construction of these WEs with his own equipment.  This landowner has a long history of installing conservation measures for fish habitat restoration and also has planned future work.  In addition, this landowner controls approximately 3 miles of Mission Creek where steelhead spawning and rearing activities are documented.  Allowing the extension as requested by the landowner would promote and preserve the existing cooperative working relationship and encourage future project work.  The planned construction sequence for WE U and V is:
• June 23-26, 2014 deliver materials to project site.  Materials include fencing, pipeline and trough.
• July 7 -10, 2014 install water development.
• July 7-16 install fence.

WE Z
The work for WE AB needs to be completed before this work element can be completed.  The planting scheduled at this site is partially within the excavated area identified under WE AB.    The Idaho Department of Corrections work crew will install the plantings under supervision of NPSWCD staff.  The plant materials are available and located at the NPSWCD office.  The proposed construction schedule for the work:
• April 30 – May 3, 2014 install the vegetation that is outside of the WE AB area of influence.
• June 12-14, 2014 install the vegetation that is within the WE AB area.

WE AB
The work planned for this work element includes removal of a small berm, which requires a plan review by the BPA EC lead.  The results of the plan review will not be completed prior to 4/30/2014 which prohibits completion of the earthwork component of this project.  Planned construction schedule:
• April 22, 2014 submit plan to EC lead for review.
• April 22 – May 31, 2014 plan review (up to 30 days is needed if hydrology and engineering review is needed)
• June 2-5, 2014 organize equipment and ensure materials are on site.
• June 9-11, 2014 complete earthwork


ORIGINAL DESCRIPTION

The Restoring Anadromous Fish Habitat in the Lapwai Creek Watershed, project 2002-070-00, began in 2003.  This multi-year project focuses on restoring and improving fish habitat within the Lapwai Creek watershed.  The limiting factors addressed include low summer flows, wide fluctuation in annual stream flows, connectivity, loss of all or partial floodplain, sedimentation of spawning and rearing habitat, high summer stream temperatures, and lack of in-stream cover.  Past accomplishments have entailed the installation of land improvement projects to address these limiting factors, including 8.24 miles of riparian fencing, 6.21 miles of upland fencing, 499 acres of weed control, two livestock waste systems, 9,000 LF of riparian plantings, 4 stream crossings, 12.1 miles of road improvements, 2 miles of streambank bioengineering restoration, 4.5 acres of wetland enhancement, 15,209 acres of direct seeding, 15 alternative watering systems for livestock, 13 water and sediment control structures,22 LF grassed waterway, the development of 52 habitat conservation plans, 9.27 miles of access restored, 3.1 miles of floodplain reconnected, 82 acres of tree planting, and 200 acres of grass seeding.  

Prior to the initiation of this project, a massive data gap existed on fish, the condition of fish habitat, and limiting factors within the watershed.  Under the FY 2007 contract, we focused primarily on the analysis and compilation of the fish presence and abundance data, and stream habitat data collected annually since 2003.  The data was analyzed and converted into a GIS-compatible format and then combined with other available, watershed-wide data sets developed by the Nez Perce Soil and Water Conservation District, the Nez Perce Tribe Watershed Division (NPT) and the NPT Water Resources Division.  The synergistic effect of these combined data sets came together in the development of the "Strategy for the Ecological Restoration of Lapwai Creek Watershed," a document intended to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek Watershed.  This document provides an accurate assessment of the status and health of the aquatic resources within the watershed, and will allow us to spatially prioritize the implementation of future watershed protection and restoration projects for the Lapwai Creek Watershed. This plan was updated in FY08 to incorporate information identified by the ISRP review.
                                                                                                                                                                          
FY 13 Contract Summary:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract and revised in FY08, was the main reference for prioritizing implementation and developing the FY 13 SOW.  Work during this contract period includes more design and plan development than the previous 3 contract years.  The plan and design will allow for future implementation actions.  The NPSWCD anticipates the installation of projects planned and designed through this contract period in the years 2014-2016.

Under this contract, the NPSWCD plans to install 850 LF of fence, control  6 acres of noxious weeds, improve 700 LF or road, plant 6 acres with native trees and shrubs, install 2 water developments, install one erosion control structure, maintain vegetation at 20 sites (310 acres), develop 4 habitat restoration plans, remove two passage barriers, treat 73 acres of hybrid knotweed, treat 115 acres of orange hawkweed, release biocontrol adults at 5 sites, and install 2,225 acres of direct seeding.  Work completed under this contract assists in meeting the following objectives:

Objective 1 – Reduce stream temperatures
Reduce water temperatures to levels meeting applicable water quality standards for life stage specific needs of anadromous and native resident fish, with an established upward trend in the number of stream miles meeting standards. The benchmark for this objective is to reduce overall days exceeding daily average temperatures at less than 16 degrees Celsius for spawning and rearing for anadromous salmonids and less than 20 degrees Celsius under all circumstances (NPCC 1994). Additional benchmarks for specific project types are discussed under relevant deliverables. Desired out comes include restoring hydrologic functions related to temperature--identifying and rehabilitating wetland and floodplain areas, restoring riparian functions related to temperature--continuing efforts aimed at increasing streamside shading where streamside shading has been reduced by anthropogenic activities.  This objective is consistent with the Clearwater Subbasin Management Plan, pg 35 (NPCC, 2005).

Objective 2 – Improve aquatic habitat diversity and complexity
Improve aquatic habitat diversity and complexity to levels consistent with objectives in the subbasin plan, with particular emphasis on recovery of anadromous stocks. Aquatic habitat condition (including diversity and/or complexity components) is limiting all focal species. Improvement in habitat productivity is considered critical to attainment of goals for both anadromous and resident species. Address priority problems with protection and restoration activities designed to promote development of more complex and diverse habitats through improved watershed condition and function. Desired outcomes include additions of large woody debris, stream channel reconstruction, increased side channels, increased pool quality/quantity, floodplain reconstruction, protecting and restoring wetland, and improved hydrologic functions.  Management criteria includes water temperature of 16°C, adequate sources of woody debris recruitment, width to depth ratios <10, streambank conditions are >90% stable, with on average, less than 10% of banks actively eroding, and overbank flows occur on a 1.5 – 2 year event. Link to Clearwater Subbasin Plan, pg 37 (NPCC, 2005).

Objective 3 – Reduce instream sedimentation
Reduce instream sedimentation to levels meeting applicable water quality standards, with an established upward trend in the number of stream miles meeting standards.  Benchmarks for this activity include streambanks are >90% stable, < 20% cobble embeddedness, and turbidity is low (NOAA, 1996).  Additional benchmarks for specific project types are discussed under relevant deliverables. Desired outcomes include restoring streambank condition, reducing sediment delivery to the stream from hydrologically connected roads and uplands, and reducing sediment inputs by implementing practices that address problems from logging, mining, agricultural and other historic and current sediment producing activities.   This objective is consistent with the Clearwater Subbasin Management Plan, pg 35 (NPCC, 2005).

Status and Trend and Implementation/Effectiveness monitoring under this contract is coordinated with the Nez Perce Tribe.  The Nez Perce Tribe conducts the monitoring and evaluation required to determine population status and trends, as well as the physical and biological response to the habitat/watershed restoration efforts.  The Nez Perce Soil and Water Conservation District (NPSWCD) utilizes the Nez Perce Tribe's monitoring data to prioritize habitat improvement and site specific project areas.
Account Type(s):
Expense
Contract Start Date:
05/01/2013
Contract End Date:
07/31/2014
Current Contract Value:
$261,759
Expenditures:
$261,759

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Description: 2400 biocontrol agents (Aceria malherbae) gall mites were released at this site. Photo shows infestation of field bindweed (Convolvulus arvensis L.) in the fence row. The mite feeds on the leaves during the growing season and migrates to roots in dormant season. The insects were obtained from the Nez Perce Tribe Biocontrol Center. Photo taken by Kayla Dau.

Contract(s):

61265

Dimensions: 1600 x 1200

Description: Photo of field bindweed gall mite. Insect is microscopic and feeds on leaves of field bindweed. Photo courtesy of USDA-Agricultural Research Service Archive, bugwood.org.

Contract(s):

61265

Dimensions: 768 x 512

Description: Photo is of location where thermograph is deployed. Stream temperature data collected at this to document temperature ranges prior to a riparian project planting. This site is one of several proposed for planting in 2017.

Contract(s):

61265

Dimensions: 1600 x 1200

Description: Photo showing Webb Creek in May 2013 at the stream temperature site WC03 location.

Contract(s):

61265

Dimensions: 448 x 336

Description: View of Webb Creek in November 2013 at the WC03 stream temperature deployment site.

Contract(s):

61265

Dimensions: 800 x 600

Description: VIew of orange hawkweed found during July 2013 inventory. Site is forestland and is located in the Mission Creek drainage of the Lapwai Creek watershed.

Contract(s):

61265

Dimensions: 1600 x 1200

Description: View of orange hawkweed found during inventory in July 2013. Site is a grazed meadow and is located in the Mission Creek tributary of Lapwai Creek.

Contract(s):

61265

Dimensions: 448 x 336

Description: View of bank erosion and erosion site 1 along Sweetwater Creek. April 2014.

Contract(s):

61265

Dimensions: 640 x 479

Description: View of streambank erosion along Lapwai Creek at inventory site number 33. February 2014. Photo taken during streambank erosion inventory.

Contract(s):

61265

Dimensions: 1920 x 2560

Description: View of streambank erosion at site 95 along Lapwai Creek. Photo dated April 2014.

Contract(s):

61265

Dimensions: 640 x 479

Description: View of streambank erosion at site 65 along Lapwai Creek. Photo April 2014

Contract(s):

61265

Dimensions: 640 x 479

Description: Potential project site located in LC2 assessment unit.

Contract(s):

61265

Dimensions: 448 x 299

Description: Potential riparian restoration site in LC2 assessment unit.

Contract(s):

61265

Dimensions: 448 x 299


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Requirements Completed A: 165. Environmental Compliance 04/28/2014 04/30/2014
Attach Progress Report in Pisces C: 132. Produce Progress Report for Period 5/1/12-4/30/13 07/15/2013 06/28/2013
Manage 5/1/2013 to 4/30/2014 contract (FY2013 funding) E: 119. Management, Coordination, and Communication 04/30/2014 04/29/2014
Coordinate Lapwai Creek Watershed Activities F: 191. Coordinate Lapwai Creek Watershed Activities 04/30/2014 04/30/2014
Updated GIS database G: 160. Maintain project database 04/15/2014 04/15/2014
Marketing plan implementation H: 99. Implement Lapwai Watershed Marketing Plan 03/31/2014 03/31/2014
Projects selected for installation in future contract years I: 114. Select, Prioritize, and Obtain Permission for 2014 Projects 11/30/2013 11/28/2013
Design package for 6 land improvement projects J: 175. Prepare Engineering and Technical Designs for 2013/2014 Projects 04/17/2014 04/17/2014
Completed RIPP Step 1 on 4 non-tribal Properties K: 115. Complete Habitat Restoration Plans 04/29/2014 04/29/2014
Develop Plan L: 174. Culdesac to Sweetwater Floodplain Restoration Plan 04/30/2014 04/30/2014
Produce Plan M: 115. Lower Lapwai Streambank Stability Plan 04/30/2014 04/28/2014
240 acres of hawkweed inventoried N: 115. Orange Hawkweed Inventory 10/04/2013 09/30/2013
Data Sent to Idaho StreamNet Project Leader O: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader 03/01/2014 03/31/2014
Raw temperature data P: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed 03/31/2014 03/26/2014
104 acres of vegetation maintained at 20 sites Q: 197. Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through 2012 09/20/2013 09/20/2013
2.05 miles Stream Treated for Hybrid Knotweed R: 197. Control Hybrid Knotweed 10/11/2013 10/01/2013
Treat 2.5 acres of hawkweed at 2 sites. S: 197. Craig Mountain Hawkweed Treatment 09/30/2013 08/08/2013
10 Acres of Invasive Plant Management T: 197. Release biocontrol agents for spotted knapweed and field bindweed control 08/31/2013 08/14/2013
Alternative water source installed U: 34. Site 11-128 Water Developments 07/31/2014 07/30/2014
Install approximately 850 linear feet of fence along Mission Creek V: 40. Site 11-128 Livestock Exclusion from Mission Creek 07/31/2014 07/30/2014
3 Acres of Invasive Plant Management W: 197. Weed Control Demonstration Project and Field Trial 09/13/2013 07/13/2013
Bio-logs, wetland and grass plugs planted and stored in holding tanks until 2013/2014 installa X: 47. Preparation of Wetland and riparian plant materials for 2014/2015 planting 04/25/2014 04/23/2014
3341.6 acres seeded with direct seeding systems Y: 48. Reduce Sediment Delivery and Improve Hydrology 12/31/2013 11/07/2013
Plant native tree, shrub and grass in riparian buffer and wetland area Z: 47. South Tom Beall Buffer Project Riparian and Wetland Planting Phase II 07/31/2014 07/29/2014
Perform pre-planting weed control along 0.5 acres of South Tom Beall Creek. AA: 197. South Tom Beall Buffer Project Pre-Planting Weed Control Phase II 04/30/2014 04/30/2014
Restore wetland along South Tom Beall Creek AB: 181. South Tom Beall Buffer Project Wetland Restoration Phase II 07/31/2014 07/30/2014
Weed Control Applied AC: 197. Site 12-161 Pre-planting weed control 04/30/2014 04/22/2014
Develop Plan AD: 174. Tom Beall Channel Restoration Plan - Site 12-1551 04/30/2014 04/30/2014
Develop Plan AE: 174. Webb Ridge Road Wetland Plan - Site 13-1591. 04/10/2014 04/15/2014
Produce Inventory and Assessment AF: 115. Sweetwater Creek inventory and assessment - Site 13-1589. 04/30/2014 04/24/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 7 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 48 Practice No-till and Conservation Tillage Systems
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 114 Identify and Select Projects
  • 4 instances of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 05/01/2013
B 185 Periodic Status Reports for BPA 05/01/2013
C 132 Produce Progress Report for Period 5/1/12-4/30/13 05/01/2013
D 132 Prepare draft progress report for the 5/1/2013 to 4/30/2014 contract period 05/01/2013
E 119 Management, Coordination, and Communication 05/01/2013
F 191 Coordinate Lapwai Creek Watershed Activities 05/01/2013
G 160 Maintain project database 05/01/2013
H 99 Implement Lapwai Watershed Marketing Plan 05/01/2013
I 114 Select, Prioritize, and Obtain Permission for 2014 Projects 05/01/2013
J 175 Prepare Engineering and Technical Designs for 2013/2014 Projects 05/01/2013
K 115 Complete Habitat Restoration Plans 05/01/2013
L 174 Culdesac to Sweetwater Floodplain Restoration Plan 05/01/2013
M 115 Lower Lapwai Streambank Stability Plan 05/01/2013
N 115 Orange Hawkweed Inventory 05/01/2013
O 161 Supply Publicly Available Data to Idaho StreamNet Project Leader 05/01/2013
P 157 Stream Temperature Data Collection in the Lapwai Creek Watershed 09/24/2013
Q 197 Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through 2012 09/24/2013
R 197 Control Hybrid Knotweed 09/26/2013
S 197 Craig Mountain Hawkweed Treatment 09/26/2013
T 197 Release biocontrol agents for spotted knapweed and field bindweed control 09/24/2013
U 34 Site 11-128 Water Developments 04/03/2014
V 40 Site 11-128 Livestock Exclusion from Mission Creek 04/03/2014
W 197 Weed Control Demonstration Project and Field Trial 02/28/2014
X 47 Preparation of Wetland and riparian plant materials for 2014/2015 planting 05/01/2013
Y 48 Reduce Sediment Delivery and Improve Hydrology 09/24/2013
Z 47 South Tom Beall Buffer Project Riparian and Wetland Planting Phase II 02/28/2014
AA 197 South Tom Beall Buffer Project Pre-Planting Weed Control Phase II 02/28/2014
AB 181 South Tom Beall Buffer Project Wetland Restoration Phase II 04/30/2014
AC 197 Site 12-161 Pre-planting weed control 09/26/2013
AD 174 Tom Beall Channel Restoration Plan - Site 12-1551 05/01/2013
AE 174 Webb Ridge Road Wetland Plan - Site 13-1591. 05/01/2013
AF 115 Sweetwater Creek inventory and assessment - Site 13-1589. 05/01/2013