Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 62904: 2008-608-00 EXP IDAHO ACCORD WATER TRANSACTIONS
Project Number:
Title:
Idaho MOA/Fish Accord Water Transactions
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
62904
Contract Title:
2008-608-00 EXP IDAHO ACCORD WATER TRANSACTIONS
Contract Continuation:
Previous: Next:
54579: 2008-608-00 EXP IDAHO ACCORD WATER TRANSACTIONS
  • 69884: 2008-608-00 EXP IDAHO ACCORD WATER TRANSACTIONS
Contract Status:
Closed
Contract Description:
Idaho MOA/Fish Accord Water Transactions Contract

The MOA Idaho Water Transactions Program will complement the Columbia Basin Water Transactions Program (CBWTP) and will utilize the transaction tracking and procedural aspects of CBWTP to enhance the effectiveness of implementation.  The basis of the funding is the MOA signed between the Action Agencies and the state of Idaho for Idaho-specific projects addressed in the Biological Opinion issued in 2008.
Account Type(s):
Expense
Contract Start Date:
10/01/2013
Contract End Date:
09/30/2015
Current Contract Value:
$220,769
Expenditures:
$220,769

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Morgan Case Idaho Department of Water Resources (IDWR) Yes Contract Manager morgan.case@idwr.idaho.gov (208) 762-2803
Mike Edmondson Idaho Governor's Office of Species Conservation Yes Administrative Contact mike.edmondson@osc.idaho.gov (208) 334-2189
Christopher Furey Bonneville Power Administration Yes COR chfurey@bpa.gov (503) 230-3371
Helen Harrington Idaho Department of Water Resources (IDWR) No Supervisor helen.harrington@idwr.idaho.gov (208) 287-4848
Amy Hines Idaho Governor's Office of Species Conservation Yes Administrative Contact amy.hines@osc.idaho.gov (208) 332-1557
Rankin Holmes National Fish and Wildlife Foundation No Technical Contact Rankin.Holmes@watercourseinc.com (406) 239-5587
Amy Mai Bonneville Power Administration Yes Env. Compliance Lead aemai@bpa.gov (503) 230-7349
Kacy Markowitz National Fish and Wildlife Foundation No Technical Contact kacy.markowitz@nfwf.org (503) 417-8700x6010
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Scott McCaulou National Fish and Wildlife Foundation No Technical Contact scott.mccaulou@nfwf.org (503) 417-8700
Andrew Purkey National Fish and Wildlife Foundation No Technical Contact andrew.purkey@nfwf.org (503) 417-8700x6009
Ryan VanderMeulen National Fish and Wildlife Foundation No Technical Contact ryan.vandermeulen@nfwf.org (503) 417-8700
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All administrative tasks fulfilled with timely quality products B: 119. Manage and Adminster Projects 09/30/2015 09/30/2015
Prioritized transactions C: 114. Identify and Select Water Transactions for Development 09/30/2015 09/30/2015
Flow and Habitat Data for Water Transactions D: 157. Collect/Generate/Validate Field Data for Water Transactions 09/30/2015 09/30/2015
Water transaction checklists and associated documentation for proposed transactions. E: 154. Develop and Negotiate Water Right Transactions 09/30/2015 09/30/2015
Strategic Plan/Model development for a high priority stream F: 174. Strategic Plan Development 09/30/2015 09/30/2015
Updated SHIPUSS document G: 191. Local Watershed Coordination 09/30/2015 09/30/2015
Environmental Compliance Documentation H: 165. Environmental Compliance for Collecting Field Monitoring Data 09/30/2015 09/30/2015
Attach Progress Report in Pisces I: 132. Submit Annual Report for the FY13 period (Oct 1 2012) to (Sept 30 2013) 01/15/2014 01/15/2014
Attach Progress Report in Pisces J: 132. Submit Progress Report for the FY14 period (Oct 1 2013) to (Sept 30 2014) 03/15/2015 03/15/2015
Water instream. K: 164. 102c-08 Lemhi Permanent Cerise/TNC 09/30/2015
Water Instream. L: 164. 72k-14 Lower Lemhi 2014-2015 09/30/2015 09/30/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2013
B 119 Manage and Adminster Projects 10/01/2013
C 114 Identify and Select Water Transactions for Development 10/01/2013
D 157 Collect/Generate/Validate Field Data for Water Transactions 10/01/2013
E 154 Develop and Negotiate Water Right Transactions 10/01/2013
F 174 Strategic Plan Development 10/01/2013
G 191 Local Watershed Coordination 10/01/2013
H 165 Environmental Compliance for Collecting Field Monitoring Data 10/01/2013
I 132 Submit Annual Report for the FY13 period (Oct 1 2012) to (Sept 30 2013) 10/01/2013
J 132 Submit Progress Report for the FY14 period (Oct 1 2013) to (Sept 30 2014) 10/01/2013
K 164 102c-08 Lemhi Permanent Cerise/TNC 10/01/2013
L 164 72k-14 Lower Lemhi 2014-2015 09/04/2014