Contract 66453: 1988-053-08 EXP HRPP ODFW HATCHERY O&M - ROUND BUTTE
Project Number:
Title:
Hood River Production Operations and Maintenance (O&M) and Powerdale
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
66453
Contract Title:
1988-053-08 EXP HRPP ODFW HATCHERY O&M - ROUND BUTTE
Contract Continuation:
Previous: Next:
62683: 1988-053-08 EXP HRPP ODFW HATCHERY O&M - ROUND BUTTE
  • 69700: 1988-053-08 EXP HRPP ODFW HATCHERY O&M - ROUND BUTTE
Contract Status:
Closed
Contract Description:
October 1 to September 30
Project 1988-053-08 (formerly -06)
Hood River Production Program - Hatchery O&M
(Round Butte Hatchery - Pelton Ladder Extended Rearing Facilities)

Program Objectives:  ODFW, working in cooperation with PGE and the CTWSRO, at the PGE/CTWRO-owned Round Butte Hatchery and Pelton Ladder trap and rearing cell facilities, will rear up to 75,000, age 1 plus, Hood River and Deschutes River spring Chinook smolts and transfer to the Hood River Basin for release.  One complete hatchery cycle (from trapping of broodstock to release of smolts from that broodstock) is about 18 months long.  ODFW is responsible for all rearing while PGE does required maintenance at both Round Butte Hatchery and Pelton Ladder.
Work Plan Objectives:
The plan objectives are to initiate and complete the annual extended rearing activities in Pelton Ladder, identify and complete all O&M activities, continue routine hatchery operations (broodstock selection, spawning, incubation, rearing and disease control of spring Chinook fingerlings), initiate necessary facility upgrades and continue routine ancillary actions.  Work items are presented below.

Deliverables
- Status reports need to be sent, either via e-mail or hard copy, whenever problems are encountered during the contract period (i.e.disease outbreaks or unexpected mortalities associated with hatchery fish).

- A brief summary report is due at the end of the contract period reporting the number of fish transferred to Pelton Ladder cells, the number of fish transferred to the Hood River, and the number of fish released into the Deschutes River.  Data from this report will be used by ODFW in the annual report for the HRPP M&E project.
Account Type(s):
Expense
Contract Start Date:
10/01/2014
Contract End Date:
09/30/2015
Current Contract Value:
$126,666
Expenditures:
$126,666

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project continues to maintain current permits B: 165. NEPA and ESA compliance for project work 09/30/2015 09/30/2015
Project administration requirements completed C: 119. Manage and Administer Project 09/30/2015 09/30/2015
Submit yearly updated maintenance plan to BPA D: 174. Produce hatchery maintenance plan 03/31/2015 03/31/2015
Transfer of about 75,000 smolts to CTWS E: 176. Fish Management for brood year 2013 09/30/2015 02/25/2015
Progress toward about 75,000 hatchery fish F: 176. Fish Management for brood year 2014 09/30/2015 09/30/2015
Progress toward 75,000 smolts G: 176. Fish Management for brood year 2015 09/30/2015 09/30/2015
Complete transport of smolts to Hood River Basin H: 66. Transport Fish 03/31/2015 02/25/2015
Fish health monitoring/ sampling/ treatment I: 60. Maintain Fish Health 09/30/2015 09/30/2015
Fully functional fish hatchery to produce quality fish J: 61. Facilities O&M 09/30/2015 09/30/2015
~83,000 smolts fin clipped and coded wire tagged K: 158. Fin clip all BY2014 smolts 08/15/2015 08/15/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 60 Maintain Fish Health
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 158 Mark/Tag Animals
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 176 Produce Hatchery Fish

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2014
B 165 NEPA and ESA compliance for project work 10/01/2014
C 119 Manage and Administer Project 10/01/2014
D 174 Produce hatchery maintenance plan 10/01/2014
E 176 Fish Management for brood year 2013 10/01/2014
F 176 Fish Management for brood year 2014 10/01/2014
G 176 Fish Management for brood year 2015 10/01/2014
H 66 Transport Fish 10/01/2014
I 60 Maintain Fish Health 10/01/2014
J 61 Facilities O&M 10/01/2014
K 158 Fin clip all BY2014 smolts 10/01/2014
L 132 Reporting data transferred to Project 1988-053-04 10/01/2014