Province | Subbasin | % |
---|---|---|
Columbia Plateau | Umatilla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Julie Burke | Umatilla Confederated Tribes (CTUIR) | Yes | Administrative Contact | julieburke@ctuir.org | (541) 429-7292 |
Israel Duran | Bonneville Power Administration | Yes | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
Gary James | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | garyjames@ctuir.org | (541) 429-7285 |
Peter Lofy | Bonneville Power Administration | Yes | Interested Party | ptlofy@bpa.gov | (503) 230-4193 |
Amber MacLachlan | Bonneville Power Administration | Yes | Contracting Officer | almcmahon@bpa.gov | (503) 230-3983 |
Travis Olsen | Umatilla Confederated Tribes (CTUIR) | Yes | Contract Manager | travisolsen@ctuir.org | (541) 429-7542 |
Barbara Shields | Bonneville Power Administration | Yes | COR | bashields@bpa.gov | (503) 230-4748 |
Gene Shippentower | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | geneshippentower@ctuir.org | (541) 429-7287 |
Dorothy Welch | Bonneville Power Administration | Yes | F&W Approver | dwwelch@bpa.gov | (503) 230-5479 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | A: 119. Manage and administer project | 11/30/2015 | ||
Environmental Compliance complete | B: 165. Environmental Compliance complete on time | 12/31/2015 | 12/31/2015 | |
Parentage based tagging samples collected, cataloged and shipped to Hagerman Genetics Lab | C: 189. Parentage based tagging coordination | 11/30/2015 | 09/30/2015 | |
Inter and intra- agency coordination | D: 189. Coordinate field and laboratory activities | 12/16/2015 | 12/31/2015 | |
Sr: Ca ratio variability in Iskúulktpe Creek - fall 2014 otolith collection | E: 157. Otolith Sampling from Iskúulktpe Creek O.mykiss | 11/01/2015 | 09/10/2015 | |
Radio tag summer steelhead captured in Iskúulktpe weir | F: 157. Collect radio tag data on adult steelhead caputured at Iskúulktpe Weir | 06/01/2015 | 06/01/2015 | |
Microchemistry of water | G: 157. Collect water samples for Sr:Ca variability | 11/30/2015 | 10/29/2015 | |
Population genetics | H: 157. Genetic Identification for Iskúulktpe Creek steelhead | 06/30/2015 | 06/30/2015 | |
Genetic analysis | I: 162. Pedigree report- Determine hatchery contribution to natural production | 11/30/2015 | ||
Microchemistry analysis | J: 162. Use microchemistry to describe contribution of hatchery fish to Nat Production | 11/30/2015 | ||
Spatial distribution | K: 162. Spatial distribution of summer steelhead in Iskúulktpe Creek | 10/01/2015 | ||
Experimental units for testing a trans-generational mark | L: 158. Sampling Iskúulktpe Summer Steelhead | 05/31/2015 | 05/31/2015 | |
Deflection Board Weir Installed | M: 70. Site preparation and assembly of deflection board weir in Iskúulktpe Creek tributary | 10/15/2015 | 12/31/2015 | |
Progress Report has been published | N: 132. Submit Progress Report for the period Jan 1, 2014 to Dec 31, 2014 | 12/01/2015 | ||
Annual Report for Project 2002-030-00 for period of January 1, 2012- December 31, 2012 | O: 132. Submit Progress Report for the period Jan 1, 2012 to Dec 31, 2012. | 12/31/2015 | ||
Annual Report for Project 2002-030-00 for period of January 1, 2013- December 31, 2013 | P: 132. Submit Progress Report for the period Jan 1, 2013 to Dec 31, 2013 | 12/15/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Manage and administer project | 01/01/2015 | ||||||
B | 165 | Environmental Compliance complete on time | 01/01/2015 | ||||||
C | 189 | Parentage based tagging coordination | 01/01/2015 | ||||||
D | 189 | Coordinate field and laboratory activities | 01/01/2015 | ||||||
E | 157 | Otolith Sampling from Iskúulktpe Creek O.mykiss | 01/01/2015 | ||||||
F | 157 | Collect radio tag data on adult steelhead caputured at Iskúulktpe Weir | 01/01/2015 | ||||||
G | 157 | Collect water samples for Sr:Ca variability | 01/01/2015 | ||||||
H | 157 | Genetic Identification for Iskúulktpe Creek steelhead | 01/01/2015 | ||||||
I | 162 | Pedigree report- Determine hatchery contribution to natural production | 01/01/2015 | ||||||
J | 162 | Use microchemistry to describe contribution of hatchery fish to Nat Production | 01/01/2015 | ||||||
K | 162 | Spatial distribution of summer steelhead in Iskúulktpe Creek | 01/01/2015 | ||||||
L | 158 | Sampling Iskúulktpe Summer Steelhead | 01/01/2015 | ||||||
M | 70 | Site preparation and assembly of deflection board weir in Iskúulktpe Creek tributary | 01/01/2015 | ||||||
N | 132 | Submit Progress Report for the period Jan 1, 2014 to Dec 31, 2014 | 01/01/2015 | ||||||
O | 132 | Submit Progress Report for the period Jan 1, 2012 to Dec 31, 2012. | 01/01/2015 | ||||||
P | 132 | Submit Progress Report for the period Jan 1, 2013 to Dec 31, 2013 | 01/01/2015 | ||||||
Q | 185 | Periodic Status Reports for BPA | 01/01/2015 |