Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete environmental compliance process | A: 165. Environmental compliance documentation | 09/30/2016 | 09/26/2016 | |
Complete data collection | B: 157. Collect stream flow measurements on twelve Grande Ronde Basin gauging stations | 09/30/2016 | 09/26/2016 | |
Complete provisional and final flow records | C: 162. Generate provisional and final flow records | 09/30/2016 | 09/26/2016 | |
Complete station maintenance as needed | D: 148. Repair/maintain/replace stream flow gauging station | 09/30/2016 | 09/26/2016 | |
All administrative tasks fulfilled with timely quality products | E: 119. Project administration | 09/30/2016 | 09/26/2016 | |
2015 Water Year RME Report | F: 132. 2015 Water Year Report - 10/1/15 - 9/30/16 | 09/30/2016 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental compliance documentation | 10/01/2015 | ||||||
B | 157 | Collect stream flow measurements on twelve Grande Ronde Basin gauging stations | 10/01/2015 | ||||||
C | 162 | Generate provisional and final flow records | 10/01/2015 | ||||||
D | 148 | Repair/maintain/replace stream flow gauging station | 10/01/2015 | ||||||
E | 119 | Project administration | 10/01/2015 | ||||||
F | 132 | 2015 Water Year Report - 10/1/15 - 9/30/16 | 10/01/2015 | ||||||
G | 185 | Quarterly Status Reports | 10/01/2015 |