Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 102: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Project Number:
Title:
Walla Walla River Basin Fish Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
73982 REL 102
Contract Title:
1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
73982 REL 61: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
  • 73982 REL 134: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
The CTUIR Walla Walla River Basin Fish Habitat Enhancement Project, initiated in 1996, is an ongoing effort to monitor, protect, enhance, and restore the natural form and function of rivers, floodplains, and native fish habitat. Restoration project location and selection criteria is derived from various managerial guidance documents and based upon identification and addressing factors limiting salmonid production including the Middle Columbia River Steelhead Recovery Plan (NMFS 2009), Bull Trout Recovery Plan (USFWS 2015), Walla Walla Subbasin Plan (NPCC 2004), Umatilla River Vision (Jones et al. 2008), Lower Walla Walla River Geomorphic Assessment and Action Plan (CTUIR 2014), and the Lower Mill Creek Final Habitat and Passage Assessment and Strategic Action Plan (CTUIR 2017). The Project is responsible for improving physical habitat conditions for ESA-Listed salmonid species.  

Major tasks to be completed by the project in this funding cycle include:  

1) North Fork Touchet RM 1.3-2.0: Implement restoration actions along a 3/4 mile reach of the river focusing on habitat complexity, floodplain reconnection, and post-construction riparian restoration.      

2) North Fork Touchet River RM 2.0 - 3.3: Finalize design initiated in 2019 to restore 1 mile of the North Fork Touchet River. Plan for implementation in 2021.    
        
3) Walla Walla River Nursery Bridge Project: Complete Phase 2 Final & Phase 3 30% designs, Imp & Mon. Plans, Staking, Oversight, As-Built, and Implementation Plan. Continue with planning, design and coordination for habitat and passage improvements at Nursery Bridge. This project will plan for construction in 2021.

4) Walla Walla River Forks Confluence: Complete final designs and secure easements for priority reach established for ESA-Listed salmonid species. Project involves reactivating floodplain, improving passage and complexity, and restoring river into historic channel. Project will plan for construction in 2021.

5) Mill Creek: Complete implementation of fishway improvements at the City of Walla Walla Mill Creek Dam to bring the fishway into full compliance with federal and state fish passage requirements.

6) Upper Walla Walla Basin Prioritization: Complete inventory and assessment for the upper Walla Walla Basin used to identify and prioritize future projects.

7) Enhance riparian vegetative components at restoration project sites: Plant new vegetation and maintain previously planted areas.
Account Type(s):
Expense
Contract Start Date:
04/01/2020
Contract End Date:
03/31/2021
Current Contract Value:
$1,374,201
Expenditures:
$1,374,201

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Morgan Clay Umatilla Confederated Tribes (CTUIR) Yes Interested Party morganclay@ctuir.org (541) 429-7549
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Ethan Green Umatilla Confederated Tribes (CTUIR) Yes Contract Manager ethangreen@ctuir.org (541) 429-7555
Gary James Umatilla Confederated Tribes (CTUIR) No Interested Party garyjames@ctuir.org (541) 429-7285
Travis Kessler Bonneville Power Administration No Interested Party tdkessler@bpa.gov (503) 230-5468
Michael Lambert Umatilla Confederated Tribes (CTUIR) Yes Supervisor mikelambert@ctuir.org (541) 429-7240
Andre L'Heureux Bonneville Power Administration No Interested Party allheureux@bpa.gov (503) 230-4482
Claire McClory Bonneville Power Administration Yes Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
Gerald Middel Umatilla Confederated Tribes (CTUIR) Yes Technical Contact geraldmiddel@ctuir.org (541) 969-9925
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Michelle Thompson Umatilla Confederated Tribes (CTUIR) No Administrative Contact michellethompson@ctuir.org (541) 429-7227
Jesse Wilson Bonneville Power Administration Yes Interested Party jcwilson@bpa.gov (503) 230-4506
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project administration activities managed effectively A: 119. Conduct all project management activities 03/31/2021 03/31/2021
Environmental compliance B: 165. Produce environmental compliance for on the ground work 03/31/2021 03/31/2021
Projects identified and prioritize; short and long term C: 114. Identify and select habitat projects that benefit salmonids 03/31/2021 03/31/2021
Provide technical support through interagency coordination and public forum D: 122. Provide technical support on related resource topics 03/31/2021 03/31/2021
Maintained Vegetation E: 198. Maintain Vegetation at Past Projects 03/31/2021 03/31/2021
Photo point monitoring F: 186. Implementation Monitoring and Adaptive Management of Past Project Sites 03/31/2021 03/31/2021
Produce Upper Walla Walla River Assessment and Action Plan G: 115. Develop Upper Walla Walla River Assessment & Action Plan 03/31/2021
Biological resource reports submitted to BPA H: 115. Nursery Bridge NEPA Support 02/05/2021 02/02/2021
Produce final design package I: 175. Nursery Bridge Reach Phase 2 - Produce Final Designs 03/31/2021
30% design for reach downstream of Nursery Bridge J: 175. Nursery Bridge Reach Phase 3 - Produce 30% Designs 03/31/2021
Produce final design K: 175. Walla Walla River Forks Confluence - Produce Final Designs 03/31/2021
Construction Management Complete L: 100. North Fork Touchet RM 1.3-2.0 - Construction Management 03/31/2021 12/31/2020
Restoration of the North Fork Touchet River RM 3 M: 29. North Fork Touchet RM 1.3-2.0 - Increase Complexity 12/31/2020 09/30/2020
Reconnect floodplain N: 180. North Fork Touchet RM 1.3-2.0 - Remove Berm and Excavate Floodplain 09/30/2020 09/30/2020
Completed channel construction O: 30. North Fork Touchet RM 1.3-2.0 - Create Side Channel 09/30/2020 09/30/2020
Vegetation Planted P: 47. North Fork Touchet RM 1.3-2.0 - Riparian Planting 12/31/2020 11/13/2020
Produce Final Designs Q: 175. North Fork Touchet RM 2.0-3.3 - Floodplain and Habitat Restoration 03/31/2021 03/15/2021
Mill Creek Diversion Dam Fishway Modifications Complete S: 184. Mill Creek Intake Dam Fishway Improvement 03/31/2021
Complete NWPCC proposal and review process T: 141. ISRP review and Council process 03/31/2021
Completed Annual Report U: 132. Annual Progress Report (1/1/19) to (3/31/20) 07/01/2020 06/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Conduct all project management activities
B 165 Produce environmental compliance for on the ground work
C 114 Identify and select habitat projects that benefit salmonids
D 122 Provide technical support on related resource topics
E 198 Maintain Vegetation at Past Projects
F 186 Implementation Monitoring and Adaptive Management of Past Project Sites
G 115 Develop Upper Walla Walla River Assessment & Action Plan 03/13/2020
H 115 Nursery Bridge NEPA Support
I 175 Nursery Bridge Reach Phase 2 - Produce Final Designs
J 175 Nursery Bridge Reach Phase 3 - Produce 30% Designs 09/09/2020
K 175 Walla Walla River Forks Confluence - Produce Final Designs 09/09/2020
L 100 North Fork Touchet RM 1.3-2.0 - Construction Management
M 29 North Fork Touchet RM 1.3-2.0 - Increase Complexity 08/12/2020
N 180 North Fork Touchet RM 1.3-2.0 - Remove Berm and Excavate Floodplain 08/12/2020
O 30 North Fork Touchet RM 1.3-2.0 - Create Side Channel 08/12/2020
P 47 North Fork Touchet RM 1.3-2.0 - Riparian Planting 08/12/2020
Q 175 North Fork Touchet RM 2.0-3.3 - Floodplain and Habitat Restoration 09/09/2020
R 175 Yellowhawk Creek Provenance Dam Fish Passage Rectification 09/09/2020
S 184 Mill Creek Intake Dam Fishway Improvement
T 141 ISRP review and Council process
U 132 Annual Progress Report (1/1/19) to (3/31/20)
V 185 Periodic Status Reports for BPA