73982 REL 11: 2000-031-00 EXP ENHANCE HABITAT N. FORK JOHN DAY RIVER |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Produce Project Deliverables | 01/31/2019 | 01/31/2019 | |
Identify, Prioritize and Select Habitat Project Areas | B: 114. Identify, Prioritize and Select Habitat Project Areas | 11/30/2018 | 11/30/2018 | |
Produce Environmental Compliance Documentation | C: 165. Produce Environmental Compliance Documentation | 01/31/2019 | 01/31/2019 | |
Provide Local Community-Based Outreach and Education | D: 99. Provide Outreach and Education | 01/31/2019 | 01/31/2019 | |
Investigate for Livestock Trespass | E: 26. Investigate for Livestock Trespass | 01/31/2019 | 01/31/2019 | |
Maintain Fences | F: 186. Maintain Fences | 01/31/2019 | 01/31/2019 | |
Maintain Water Developments | G: 186. Maintain Water Developments | 01/31/2019 | 01/31/2019 | |
Noxious Weed Control | H: 198. Noxious Weed Control | 01/31/2019 | 01/31/2019 | |
Desolation Creek Upper Reach 6 Implementation - Floodplain Enhancement | I: 29. Desolation Creek Upper Reach 6 Implementation - Floodplain Enhancement | 12/31/2018 | 12/31/2018 | |
Desolation Creek Upper Reach 6 Implementation - Side Channel Reconnect | J: 30. Desolation Creek Upper Reach 6 Implementation - Side Channel Reconnect | 12/31/2018 | 12/31/2018 | |
Desolation Creek Upper Reach 6 Implementation - Road Decommission | K: 33. Desolation Creek Upper Reach 6 Implementation - Road Decommission | 12/31/2018 | 12/31/2018 | |
Collect Water Temperature and Photo point Data | L: 157. Collect Water Temperature and Photopoint Data | 01/31/2019 | 01/31/2019 | |
Desolation Creek Meadow Storage Feasibility | M: 115. Desolation Creek Meadow Storage Feasibility | 01/31/2019 | 01/31/2019 | |
Hideway Creek Design | N: 175. Hideway Creek Design | 01/31/2019 | ||
Completed Annual Report | P: 132. Submit Progress Report for the Period (February 1, 2016) to (January 31, 2017) | 01/31/2019 | 01/31/2019 | |
Complete 30% Design and Wetland Assessment | Q: 175. CCR-40645 Bull Run Creek Design | 01/31/2019 | 01/31/2019 | |
Complete 30% Conceptual Design Development | R: 175. CCR-40645 Desolation Creek Reach 3 Design | 01/31/2019 | 01/31/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Lamprey, Western Brook (L. richardsoni) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Trout, Rainbow (Oncorhynchus mykiss) |
|
Trout, Interior Redband (O. mykiss gairdnerii) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Produce Project Deliverables | 02/01/2018 | ||||||
B | 114 | Identify, Prioritize and Select Habitat Project Areas | 02/01/2018 | ||||||
C | 165 | Produce Environmental Compliance Documentation | 02/01/2018 | ||||||
D | 99 | Provide Outreach and Education | 02/01/2018 | ||||||
E | 26 | Investigate for Livestock Trespass | 02/01/2018 | ||||||
F | 186 | Maintain Fences | 02/01/2018 | ||||||
G | 186 | Maintain Water Developments | 02/01/2018 | ||||||
H | 198 | Noxious Weed Control | 02/01/2018 | ||||||
I | 29 | Desolation Creek Upper Reach 6 Implementation - Floodplain Enhancement | 02/28/2018 | ||||||
J | 30 | Desolation Creek Upper Reach 6 Implementation - Side Channel Reconnect | 02/28/2018 | ||||||
K | 33 | Desolation Creek Upper Reach 6 Implementation - Road Decommission | |||||||
L | 157 | Collect Water Temperature and Photopoint Data | 02/01/2018 | ||||||
M | 115 | Desolation Creek Meadow Storage Feasibility | 04/24/2018 | ||||||
N | 175 | Hideway Creek Design | |||||||
O | 185 | Periodic Status Reports for BPA | 02/01/2018 | ||||||
P | 132 | Submit Progress Report for the Period (February 1, 2016) to (January 31, 2017) | 02/01/2018 | ||||||
Q | 175 | CCR-40645 Bull Run Creek Design | |||||||
R | 175 | CCR-40645 Desolation Creek Reach 3 Design | 01/31/2019 |