Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
Previous: | Next: |
---|---|
73982 REL 8: 2008-207-00 EXP UMATILLA TRIBE ACQUISITION & PROTECTION |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | B: 119. Manage and Adminster Project | 01/31/2019 | 01/01/2019 | |
Identify, prioritize, select, and develop land and easement acquisition projects | C: 114. Identify, prioritization, select, and develop projects | 01/31/2019 | 01/01/2019 | |
Pre Acquisition Activities for Hamley Property | E: 172. Conduct Pre-Acquisition Activities: Hamley | 08/01/2019 | 08/01/2019 | |
Pre Acquisition Activities for Wujek Property | F: 172. Conduct Pre-Acquisition Activities:Wujek Umatilla River | 01/31/2019 | 08/01/2018 | |
Complete Pre-acquisition work | H: 172. Conduct Pre-Acquisition Activities: Touchet Orchard Easement 1 | 01/31/2020 | ||
Complete Pre-acquisition work | I: 172. Conduct Pre-Acquisition Activities:Touchet Orchard Easement 2 | 01/31/2020 | ||
Complete Pre-acquisition work | J: 172. Conduct Pre-Acquisition Activities: UmaBirch Easement | 01/31/2020 | ||
Complete Pre-acquisition work | K: 172. Conduct Pre-Acquisition Activities: Tucannon Ranch | 01/31/2020 | ||
Complete Pre-acquisition work | L: 172. Conduct Pre-Acquistion Activities Rainwater Additions | 01/31/2020 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Freshwater Mussels |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/01/2018 | ||||||
B | 119 | Manage and Adminster Project | 02/01/2018 | ||||||
C | 114 | Identify, prioritization, select, and develop projects | 02/01/2018 | ||||||
D | 172 | Conduct Pre-Acquisition Activities: Catherine Creek, Stephens Timber LLC Property | 02/01/2018 | ||||||
E | 172 | Conduct Pre-Acquisition Activities: Hamley | 02/01/2018 | ||||||
F | 172 | Conduct Pre-Acquisition Activities:Wujek Umatilla River | 02/01/2018 | ||||||
G | 132 | Submit Progress Report for the period 2/1/2018 through 1/31/2019 | 02/01/2018 | ||||||
H | 172 | Conduct Pre-Acquisition Activities: Touchet Orchard Easement 1 | 02/01/2018 | ||||||
I | 172 | Conduct Pre-Acquisition Activities:Touchet Orchard Easement 2 | 02/01/2018 | ||||||
J | 172 | Conduct Pre-Acquisition Activities: UmaBirch Easement | 02/01/2018 | ||||||
K | 172 | Conduct Pre-Acquisition Activities: Tucannon Ranch | 02/01/2018 | ||||||
L | 172 | Conduct Pre-Acquistion Activities Rainwater Additions | 02/01/2018 |