Contract 76828 REL 1: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Project Number:
Title:
Coeur D'Alene Reservation Fisheries Habitat
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
76828 REL 1
Contract Title:
1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Continuation:
Previous: Next:
76243: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
  • 76828 REL 4: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
The scope of work and budget presented in this document describe the activities associated with the Coeur d'Alene Tribe's resident fish enhancement project for the Coeur d'Alene Subbasin corresponding to the contract period June 1, 2018 to May 31, 2019. The work elements for this project have been grouped under the general objective headings: Planning and Coordination; Construction and Implementation; Research and Monitoring; and Project Administration.

Objective - Planning and Coordination
WE A: NEPA analysis and documentation
WE B: Coordinate restoration efforts with stakeholders
WE C: Identify and select new restoration projects
WE D: Produce fish passage design for Lake Creek
WE E: Produce fish passage design for Upper Lake Creek
WE F: Produce fish passage designs for Bull Creek

Objective - Construction and Implementation
WE G: Lake Creek fish passage improvement
WE H: Upper Lake Creek fish passage improvement
WE I: Alder Creek fish passage improvement
WE J: Benewah road improvement
WE K: Lake Creek sediment basin construction
WE L: Construct beaver dam analogs - Lake Creek
WE M: Construct beaver dam analogs - Benewah Creek
WE N: Lake Creek riparian planting
WE O: Upper Lake Creek LWD additions
WE P: Benewah Creek riparian planting
WE Q: Maintain BDAs - Benewah Creek
WE R: Remove brook trout from Benewah Creek and Evans Creek
WE S: Remove pike from Coeur d'Alene Lake
WE T: Mark northern pike in southern end of Lake Coeur d'Alene

Objective - Research and Monitoring
WE U: Trap adfluvial adult cutthroat trout - Lake and Benewah creeks
WE V: Trap adfluvial juvenile cutthroat trout - Lake and Benewah creeks
WE W: Mark adfluvial adult cutthroat trout - Lake and Benewah creeks
WE X: Mark adfluvial juvenile cutthroat trout - Lake and Benewah creeks
WE Y: Sample salmonids in rearing habitats of target watersheds
WE Z: Collect data at stationary PIT antenna arrays
WE AA: Analyze data generated from trapping of adfluvial adult westslope cutthroat trout
WE AB: Analyze data generated from trapping of adfluvial juvenile westslope cutthroat trout
WE AC: Analyze data generated from sampling salmonids in rearing habitats of target watersheds
WE AD: Analyze data logged at stationary PIT antenna arrays
WE AE: Data management for RME and management actions that sample or manipulate fish populations
WE AF: Measure physical habitat in reaches proposed for treatments
WE AG: Measure water and air temperatures
WE AH: Measure ground water at wells
WE AI: Analyze data from physical habitat sampling
WE J: Analyze data from water and temperature monitoring
WE K: Analyze data from groundwater wells
WE L: Data management for physical and chemical habitat attributes
WE M: Provide education and outreach opportunities
WE N: Periodic Status Reports for BPA
WE O: Compile information for bi-annual report for the periods Jan 2018 to Dec 2019
WE P: Manage and administer project
Account Type(s):
Expense
Contract Start Date:
06/01/2018
Contract End Date:
05/31/2019
Current Contract Value:
$1,535,025
Expenditures:
$1,535,025

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jon Firehammer Coeur D'Alene Tribe Yes Technical Contact jfirehammer@cdatribe-nsn.gov (208) 686-7037
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
Phyllis Johnson Coeur D'Alene Tribe No Administrative Contact pjohnson@cdatribe-nsn.gov (208) 686-6803
Cajeton Matheson Coeur D'Alene Tribe No Supervisor camatheson@cdatribe-nsn.gov (208) 686-1009
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Jennifer Snyder Bonneville Power Administration Yes Interested Party jasnyder@bpa.gov (503) 230-4187
Angelo Vitale Coeur D'Alene Tribe Yes Contract Manager ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NEPA Checklist A: 165. Complete NEPA analysis and documentation 05/31/2019 05/31/2019
Summary of Activities B: 189. Coordinate restoration efforts with stakeholders 05/31/2019 05/31/2019
Project Descriptions/Agreements C: 114. Identify and select new restoration projects 05/31/2019 05/31/2019
Completed designs D: 175. Produce fish passage designs for Upper Lake Creek 07/31/2018 06/15/2018
Completed designs E: 175. Produce fish passage designs for Upper Lake Creek 05/31/2019
Completed design F: 175. Produce fish passage designs for Bull Creek 07/31/2018 07/20/2018
Upper Lake Creek fish passage improvement G: 184. Upper Lake Creek fish passage improvement 10/31/2018 10/26/2018
Upper Lake Creek fish passage improvement H: 184. Upper Lake Creek fish passage improvement 05/31/2019
Alder Creek Fish Passage Improvement I: 184. Alder Creek fish passage improvement 10/15/2018 09/28/2018
Benewah road improvement J: 38. Reduce sediment delivery to Benewah Creek 10/26/2018 08/17/2018
Beaver Dam Analog Construction L: 29. Construct beaver dam analogs_Lake Creek 08/15/2018 07/06/2018
Beaver Dam Analog Construction M: 29. Construct beaver dam analogs_Benewah Creek 08/15/2018 08/31/2018
Lake Creek riparian planting N: 47. Lake Creek Riparian Planting 05/31/2019 05/31/2019
Place instream LWD O: 29. Place instream LWD in upper Lake Creek 05/31/2019
Benewah Creek riparian planting P: 47. Benewah Creek ripariran planting 05/31/2019 05/03/2019
Inspected and repaired PLWW structures Q: 186. Maintain beaver dam analogs_Benewah creek 06/30/2018 06/29/2018
Removal of non-native brook trout from Benewah Creek and Evans Creek watersheds. R: 190. Remove brook trout from Benewah Creek and Evans Creek 10/31/2018 09/28/2018
Removal of non-native northern pike from Lake Coeur d'Alene S: 190. Remove northern pike from Lake Coeur d'Alene 05/31/2019 09/30/2018
Distribution of marked northern pike in the southern end of Lake Coeur d'Alene T: 158. Mark northern pike in southern end of Lake Coeur d'Alene 04/30/2019 05/31/2019
Demographic data collected for adult adfluvial WCT at migrant traps U: 157. Trap adfluvial adult westslope cutthroat trout 05/31/2019 05/31/2019
Demographic data collected for outmigrating juvenile WCT at migrant traps V: 157. Trap adfluvial juvenile westslope cutthroat trout 05/31/2019 05/31/2019
Marked adfluvial adult westslope cutthroat trout W: 158. Mark adfluvial adult westslope cutthroat trout 05/31/2019 05/31/2019
Marked juvenile adfluvial cutthroat trout X: 158. Mark adfluvial juvenile westslope cutthroat trout 05/31/2019 05/31/2019
Salmonids captured during stream surveys in subbasins of target watersheds Y: 157. Sample salmonids in rearing habitats of target watersheds 05/31/2019 05/31/2019
Interrogation data collected from stationary PIT-tag antenna arrays Z: 157. Collect data at stationary PIT antenna arrays 05/31/2019 05/31/2019
Demographic metrics generated for adult adfluvial WCT sampled in migrant traps AA: 162. Analyze data generated from trapping of adfluvial adult westslope cutthroat trout 02/28/2019 02/22/2019
Demographic metrics generated for adfluvial juvenile WCT sampled in migrant traps AB: 162. Analyze data generated from trapping of adfluvial juvenile westslope cutthroat trout 02/28/2019 02/22/2019
Examination of spatial distribution patterns of salmonid abundance at the subbasin and watershed scale AC: 162. Analyze data generated from sampling salmonids in rearing habitats of target watersheds 02/28/2019 02/22/2019
Metrics generated from interrogation data logged at stationary PIT antenna arrays AD: 162. Analyze data logged at stationary PIT antenna arrays 02/28/2019 02/22/2019
Updated database for fish manipulation and RME fish sampling activities AE: 160. Data management for RME and management actions that sample or manipulate fish populations 05/31/2019 05/31/2019
Physical habitat data in stream reaches of the upper fork of Lake Creek AF: 157. Measure physical habitat in reaches proposed for treatments 05/31/2019 05/31/2019
Continuous records of water and air temperatures AG: 157. Measure water and air temperatures 05/31/2019 05/31/2019
Collected data from groundwater wells in a restored reach of upper Benewah watershed AH: 157. Measure groundwater at wells 05/31/2019 05/31/2019
Generation of physical habitat metrics in stream reaches of the upper fork of Lake Creek AI: 162. Analyze data from physical habitat sampling 02/28/2019 02/22/2019
Metrics and indicators of water temperature in Benewah and Lake creeks AJ: 162. Analyze data from temperature monitoring 02/28/2019 02/22/2019
Analyzed groundwater data from the upper Benewah watershed AK: 162. Analyze data from groundwater wells 02/28/2019 02/22/2019
Updated database of physical habitat attributes, temperatures, and groundwater data AL: 160. Data management for physical and chemical habitat attributes 05/31/2019 05/31/2019
Summary of Education/Outreach Activities AM: 99. Provide education and outreach opportunities 05/31/2019 05/31/2019
Compiled information for bi-annual report AO: 132. Compile information for bi-annual report for the periods Jan 2018 to Dec 2019 05/31/2019 05/31/2019
Accrual Estimates/FY2018 SOW/Metrics Reports AP: 119. Manage and administer project 05/31/2019 05/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 2 instances of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 3 instances of WE 175 Produce Design
  • 7 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 158 Mark/Tag Animals
  • 7 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete NEPA analysis and documentation 06/01/2018
B 189 Coordinate restoration efforts with stakeholders 06/01/2018
C 114 Identify and select new restoration projects 06/01/2018
D 175 Produce fish passage designs for Upper Lake Creek 05/07/2018
E 175 Produce fish passage designs for Upper Lake Creek 05/07/2018
F 175 Produce fish passage designs for Bull Creek 05/07/2018
G 184 Upper Lake Creek fish passage improvement 06/13/2018
H 184 Upper Lake Creek fish passage improvement
I 184 Alder Creek fish passage improvement 06/13/2018
J 38 Reduce sediment delivery to Benewah Creek 05/07/2018
K 55 Lake Creek sediment basin construction
L 29 Construct beaver dam analogs_Lake Creek 05/10/2018
M 29 Construct beaver dam analogs_Benewah Creek 05/10/2018
N 47 Lake Creek Riparian Planting
O 29 Place instream LWD in upper Lake Creek
P 47 Benewah Creek ripariran planting 12/31/2018
Q 186 Maintain beaver dam analogs_Benewah creek 05/07/2018
R 190 Remove brook trout from Benewah Creek and Evans Creek 05/09/2018
S 190 Remove northern pike from Lake Coeur d'Alene 05/09/2018
T 158 Mark northern pike in southern end of Lake Coeur d'Alene 05/09/2018
U 157 Trap adfluvial adult westslope cutthroat trout 05/07/2018
V 157 Trap adfluvial juvenile westslope cutthroat trout 05/07/2018
W 158 Mark adfluvial adult westslope cutthroat trout 05/07/2018
X 158 Mark adfluvial juvenile westslope cutthroat trout 05/07/2018
Y 157 Sample salmonids in rearing habitats of target watersheds 05/07/2018
Z 157 Collect data at stationary PIT antenna arrays 05/07/2018
AA 162 Analyze data generated from trapping of adfluvial adult westslope cutthroat trout 06/01/2018
AB 162 Analyze data generated from trapping of adfluvial juvenile westslope cutthroat trout 06/01/2018
AC 162 Analyze data generated from sampling salmonids in rearing habitats of target watersheds 06/01/2018
AD 162 Analyze data logged at stationary PIT antenna arrays 06/01/2018
AE 160 Data management for RME and management actions that sample or manipulate fish populations 06/01/2018
AF 157 Measure physical habitat in reaches proposed for treatments 05/07/2018
AG 157 Measure water and air temperatures 05/07/2018
AH 157 Measure groundwater at wells 05/07/2018
AI 162 Analyze data from physical habitat sampling 06/01/2018
AJ 162 Analyze data from temperature monitoring 06/01/2018
AK 162 Analyze data from groundwater wells 06/01/2018
AL 160 Data management for physical and chemical habitat attributes 06/01/2018
AM 99 Provide education and outreach opportunities 06/01/2018
AN 185 Periodic Status Reports for BPA 06/01/2018
AO 132 Compile information for bi-annual report for the periods Jan 2018 to Dec 2019 06/01/2018
AP 119 Manage and administer project 06/01/2018