Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Ensure EC requirements are met | A: 165. Complete and/or initiate Environmental Permitting for Project Activities | 11/30/2020 | 10/30/2020 | |
Remove old cobble dam, old hydro dam, and their associated infrastructure | B: 85. Remove 2 Small Dams | 11/30/2021 | 09/01/2021 | |
Remove old undersized culvert and roadbed | C: 85. Remove Old Culvert and Roadbed | 10/15/2021 | 09/05/2021 | |
Install 20 LWD Structures | D: 29. Install 20 Large Wood Structures | 10/31/2021 | 09/01/2021 | |
Riparian Revegetation, Plantings and Seeding | E: 47. Revegetation and Cleanup | 11/30/2021 | 12/01/2021 | |
Effective implementation management and timely contract administration | F: 119. Project/Contract Administration | 01/31/2022 | 12/31/2021 | |
Upload Completion | G: 132. Indian Creek Completion Report | 01/31/2022 | 01/31/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete and/or initiate Environmental Permitting for Project Activities | |||||||
B | 85 | Remove 2 Small Dams | 02/01/2021 | ||||||
C | 85 | Remove Old Culvert and Roadbed | 02/01/2021 | ||||||
D | 29 | Install 20 Large Wood Structures | 02/01/2021 | ||||||
E | 47 | Revegetation and Cleanup | 02/01/2021 | ||||||
F | 119 | Project/Contract Administration | |||||||
G | 132 | Indian Creek Completion Report | |||||||
H | 185 | Quarterly Status Reports |