Contract 86154: 2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
Project Number:
Title:
Snake River Sockeye Captive Propagation
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
86154
Contract Title:
2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
Contract Continuation:
Previous: Next:
83291: 2007-402-00 EXP IDFG SPRINGFIELD HATCHERY SOCKEYE PRODUCTION
  • 88775: 2007-402-00 EXP IDFG SPRINGFIED HATCHERY SOCKEYE PRODUCTION
Contract Status:
Closed
Contract Description:
This contract period will be the second year at full production levels at Springfield Fish Hatchery. Approximately one million BY19 fingerlings will be in outdoor raceways at Springfield Fish Hatchery at the beginning of the contract period. A representative group of these fish will be PIT tagged during fall of 2020. The smolts will be released during early May 2021 at a size of approximately 10-12 fish per pound (fpp). Baseline data including growth, survival, feed conversion rates, etc. will be collected, reported monthly, and used to set-up future brood year's projections and standard fish culture procedures. Springfield Fish Hatchery anticipates a full production scenario of 1.2 million BY20 Sockeye Salmon eyed eggs to be received in November 2020. The resulting fry are to be incubated to the swim-up stage, then transferred to early rearing tanks in January/February 2021. When these fish reach a size of approximately 100-120 fpp, they will be adipose clipped and transferred from early rearing tanks to the outdoor raceways. This usually occurs in early July of each year. Baseline data described above will continue to be collected.

Refinement of operational procedures relating to the water delivery systems for fish production activities and fish transport will continue into this contract period. This includes fixed speed and variable speed pumps, head-boxes with aeration equipment, and chiller.

Hatchery staff will update inventory as equipment is received. Annual preventative scheduled maintenance activities will be ongoing throughout this and all future contract periods.

Hatchery personnel will attend and participate in Stanley Basin Sockeye Technical Oversight Committee (SBSTOC) and program specific meetings as program needs necessitate and time allows.
Account Type(s):
Expense
Contract Start Date:
10/01/2020
Contract End Date:
09/30/2021
Current Contract Value:
$1,512,016
Expenditures:
$1,512,016

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration Yes Contracting Officer dxaffonso@bpa.gov (503) 230-5918
Dan Baker Idaho Department of Fish and Game (IDFG) Yes Technical Contact dan.baker@idfg.idaho.gov (208) 939-4114
Travis Brown Idaho Department of Fish and Game (IDFG) No Technical Contact travis.brown@idfg.idaho.gov (208) 939-4114
Gary Byrne Idaho Department of Fish and Game (IDFG) Yes Interested Party gary.byrne@idfg.idaho.gov (208) 287-2778
Matthew Campbell Idaho Department of Fish and Game (IDFG) Yes Interested Party matthew.campbell@idfg.idaho.gov (208) 939-6713
Brandon Filloon Idaho Department of Fish and Game (IDFG) Yes Contract Manager brandon.filloon@idfg.idaho.gov (208) 328-9945
Bryan Grant Idaho Department of Fish and Game (IDFG) Yes Supervisor bryan.grant@idfg.idaho.gov (208) 236-1256
Kristen Jule Bonneville Power Administration Yes F&W Approver krjule@bpa.gov (503) 230-3588
Paul Kline Idaho Department of Fish and Game (IDFG) Yes Interested Party paul.kline@idfg.idaho.gov (208) 287-2788
Christine Kozfkay Idaho Department of Fish and Game (IDFG) Yes Interested Party christine.kozfkay@idfg.idaho.gov (208) 287-2789
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
John Powell Idaho Department of Fish and Game (IDFG) No Supervisor john.powell@idfg.idaho.gov (208) 287-2789
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Craig Steele Pacific States Marine Fisheries Commission No Interested Party craig.steele@idfg.idaho.gov (208) 939-6713


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Permits/Authorizations Acquired A: 165. Obtain Permits and submit copies to BPA NEPA group 09/30/2021 09/30/2021
Maintain Springfield Fish Hatchery B: 61. Maintenance of grounds, buildings, vehicles and related fish rearing equipment at Springfield Fish Hatchery 09/30/2021 09/30/2021
Attendance at program essential and SBSTOC meetings. C: 189. Quarterly SBSTOC coordination meeting and program essential meetings 09/30/2021 09/30/2021
Rear BY19 juvenile Snake River Sockeye Salmon at Springfield Fish Hatchery D: 176. Rear BY19 Snake River Sockeye Salmon production group 05/15/2021 04/30/2021
Mark BY19 Snake River Sockeye Salmon production group E: 158. Tag BY19 Snake River Sockeye Salmon production group 11/30/2020 10/22/2020
Rear BY20 Snake River Sockeye Salmon Production Group at Springfield Hatchery F: 176. Rear BY20 Snake River Sockeye Salmon production group 09/30/2021 09/30/2021
Mark BY20 Snake River Sockeye Salmon production group at Springfield Fish Hatchery G: 158. Mark BY20 Snake River Sockeye Salmon production group 07/31/2021 06/30/2021
2021 Salmon River AOP H: 174. Salmon River Annual Operating Plan 06/30/2021 03/22/2021
Completed Annual Report I: 132. Submit Progress Report for the period (OCT 2019) to (SEP 2020) 04/30/2021 02/05/2021
Effective implementation management and timely contract administration J: 119. Submit FY22 funding package to BPA 09/30/2021 09/30/2021
Final invoice received and approved L: 171. Hatchery effluent pipe replacement and pollution abatement pond expansion 09/30/2021 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Permits and submit copies to BPA NEPA group
B 61 Maintenance of grounds, buildings, vehicles and related fish rearing equipment at Springfield Fish Hatchery 04/28/2021
C 189 Quarterly SBSTOC coordination meeting and program essential meetings
D 176 Rear BY19 Snake River Sockeye Salmon production group 04/28/2021
E 158 Tag BY19 Snake River Sockeye Salmon production group 04/28/2021
F 176 Rear BY20 Snake River Sockeye Salmon production group 04/28/2021
G 158 Mark BY20 Snake River Sockeye Salmon production group 04/28/2021
H 174 Salmon River Annual Operating Plan 07/13/2020
I 132 Submit Progress Report for the period (OCT 2019) to (SEP 2020)
J 119 Submit FY22 funding package to BPA
K 185 Periodic Status Reports for BPA
L 171 Hatchery effluent pipe replacement and pollution abatement pond expansion 04/28/2021