Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 20591: PI 198343500 UMATILLA HATCHERY SATELLITE FACILITIES O & M
Project Number:
Title:
Umatilla Hatchery Satellite Facilities Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
20591
Contract Title:
PI 198343500 UMATILLA HATCHERY SATELLITE FACILITIES O & M
Contract Continuation:
Previous: Next:
4013: 1983-435-00 UMATILLA HATCHERY SATELLITE FACILITIES O&M
  • 25824: 1983-435-00 EXP UMATILLA HATCHERY SATELLITE FACIL O&M
Contract Status:
History
Contract Description:
Draft April 1, 2005

Umatilla Hatchery Satellite Facilities Operation and Maintenance
Statement of Work and Budget FY 2005

BPA Project Number: 1983-435-00
Contract Number: 20591
Performance/Budget Period: January 1, 2005 - December 31, 2005

Technical Contacts:

Gary James, Fisheries Program Manager
Phone: (541) 276-4109
E-mail: garyjames@ctuir.com
Fax: (541) 276-2397

Brian Zimmerman, Fish Passage/Artificial Production Program Supervisor
Phone: (541) 966-2376
E-mail: brianzimmerman@ctuir.com
Fax: (541) 276-4348

Gerald Rowan, Project Leader
Phone: (541) 966-2375
E-mail: gerryrowan@ctuir.com
Fax: (541) 276-4348

Administrative Contacts:

Michelle Thompson, Manager/Administrative Operations
Phone: (541) 966-2323
E-mail: michellethompson@ctuir.com
Fax: (541) 276-3317

Julie Burke, Fish and Wildlife Administrative Manager
Phone: (541) 966-2372
E-mail: julieburke@ctuir.com
Fax: (541) 966-2397

FY2005 STATEMENT OF WORK

Background

The Umatilla Fisheries Restoration Program is a comprehensive plan to re-establish salmon runs and enhance summer steelhead runs in the Umatilla River basin. Projects associated with this plan include artificial production, new ladders and screens, fish trap and haul, and stream habitat and flow enhancement. The Umatilla Basin artificial production program consists of Umatilla Hatchery for fish production and satellite facilities for adult holding and spawning and juvenile acclimation/release. As fisheries co-managers, ODFW currently operates the Umatilla Hatchery and CTUIR, under this project, operates the satellite facilities.  

Bonifer, Minthorn, Imeques C-mem-ini-kem, Thornhollow, and Pendleton were completed in 1983, 1985, 1994, 1995, and 1999, respectively, and are used for temporary holding (acclimation) and release of juvenile salmon and steelhead. Minthorn is also used to hold and spawn adult summer steelhead collected from Three Mile Dam on the Umatilla River. Three Mile Dam Adult Holding and Spawning Facility was completed in 1996 and is currently used to hold and spawn fall Chinook adults. The South Fork Walla Walla Adult Holding and Spawning Facility was completed in 1997 and is used to hold and spawn spring Chinook adults. The operation of these facilities is closely coordinated with ODFW and is detailed in the Umatilla Hatchery and Basin Annual Operation Plan.

Project Goal

This project provides for the operation and maintenance of both juvenile and adult satellite facilities. The goal of the project is to assist in achievement of Umatilla Basin adult salmon and steelhead return goals by increasing smolt-to-adult survival/returns through acclimation of juvenile salmon and steelhead in natural production areas in the Umatilla River basin and operating adult holding and spawning facilities to provide salmon and steelhead eggs for the Umatilla production.

Location of Project

The project includes seven satellite facilities located in the Umatilla and Walla Walla River basins in Umatilla County, Oregon. Bonifer is located adjacent to Meacham Creek at rivermile (RM) 2. The pond spills into Boston Canyon Creek, which flows approximately 20 yards before entering Meacham Creek. Meacham Creek flows into the Umatilla River at RM 79. Minthorn is located approximately four miles east of Mission, Oregon. The facility is located near the mouth of Minthorn Springs Creek, which enters the Umatilla River at RM 63.8. The Pendleton, Thornhollow, and Imeques facilities are located on the Upper Umatilla River at RM 56, 73.5, and 79.5, respectively. The Three Mile Dam facility is located on the lower Umatilla River at approximately RM 3. The South Fork Walla Walla facility is located east of Milton-Freewater, Oregon. The facility is located on the South Fork Walla River at approximately RM 7.

BPA-Furnished Property

· Bonifer - The facility is located on privately owned property leased by BPA. The facility consists of a 1.75 acre earthen pond and concrete water outlet control structure which also functions as a fish trap and fish release channel.

· Minthorn - The facility is located on tribally owned property. The facility includes two concrete raceways, pump station with two 10 h.p. vertical mixed flow pumps, 30 KW standby generator, water outlet control structure which also functions as a summer steelhead broodstock holding area, and two storage buildings.

· Imeques - The facility is located on BPA owned property. The facility includes a water intake structure with automatic screen cleaner, water headbox/distribution system, two storage buildings, four acclimation ponds, and water outlet and fish release structure.

· Thornhollow - The facility is located on BPA owned property. The facility includes a water intake structure with automatic screen cleaner, pump station with three 15 h.p. vertical mixed flow pumps, 60 KW standby generator, water headbox/distribution system, two storage buildings, two acclimation ponds, and water outlet and fish release structure.

· Pendleton - The facility is located on state (ODFW) owned property. The facility includes a water intake structure with automatic screen cleaner, pump station with three 30 h.p. vertical mixed flow pumps, 80 KW standby generator, water headbox/distribution system, storage building, four acclimation ponds, settling pond for pond cleaning, and water outlet and fish release structure.

· Three Mile Dam - The facility is located on Bureau of Reclamation owned property. The facility includes a water intake system with automatic screen cleaning, pump station with four vertical mixed flow pumps (1-10 h.p., 1-20 h.p., 2-25 h.p), six adult holding ponds, mechanical fish crowder, visitor facilities including restrooms, 125 KW standby generator, and chemical storage, bunkhouse and spawning buildings. The bunkhouse includes two bunkrooms, kitchen area, office space, conference room, shop and restrooms. The spawning building includes a fish lift, electroshock anesthesia system, sorting and spawning facilities, wet and dry storage/work rooms, walk-in cooler and restroom.

· South Fork Walla Walla - The facility is located on BPA owned property. The facility includes a water intake system with automatic screen cleaning, pump station with three vertical mixed flow pumps (1 - 30 h.p, 2 - 200 h.p), ozone water treatment system, settling pond, five adult holding ponds, mechanical fish crowder, 350 KW standby generator, chemical storage and spawning buildings and two homes for nite watch personnel. The spawning building includes a fish lift, electroshock anesthesia system, sorting and spawning facilities, wet and dry storage/work rooms, walk-in cooler and restroom.

BPA holds the water right permits for South Fork Walla Walla, Thornhollow and Imeques facilities.
Account Type(s):
Expense
Contract Start Date:
01/01/2005
Contract End Date:
12/31/2005
Current Contract Value:
$747,020
Expenditures:
$747,020

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Acclimate juvenile summer steelhead at Minthorn A: 56. Acclimate juvenile summer steelhead at Minthorn 04/30/2005
Deliverable complete B: 56. Acclimate juvenile summer steelhead at Pendleton 04/30/2005 09/28/2005
Deliverable complete C: 56. Acclimate juvenile coho salmon at Pendleton 04/15/2005
Deliverable complete D: 56. Acclimate juvenile coho salmon at Pendleton 03/10/2005
Deliverable complete E: 56. Acclimate juvenile spring Chinook salmon at Imeques 12/31/2005 12/31/2005
Deliverable complete F: 56. Acclimate juvenile spring Chinook salmon at Imeques 03/10/2005 09/28/2005
Deliverable complete G: 56. Acclimate juvenile spring Chinook salmon at Imeques 04/15/2005
Deliverable complete H: 56. Acclimate juvenile fall Chinook salmon at Thornhollow 04/15/2005
Deliverable complete I: 56. Acclimate juvenile fall Chinook salmon at Thornhollow 05/31/2005
Deliverable complete J: 66. Hold adult summer steelhead at Minthorn for spawning 05/31/2005 09/29/2005
Deliverable complete K: 66. Hold adult spring Chinook salmon at South Fork Walla Walla for spawning 09/15/2005 09/29/2005
Deliverable complete L: 66. Hold adult fall Chinook salmon at Three Mile Dam for spawning 12/10/2005 12/10/2005
Deliverable complete M: 66. Potentially hold adult coho salmon at Three Mile Dam for spawning 12/10/2005
Deliverable complete N: 66. Provide temporary holding at South Fork Walla Walla for spring Chinook out planting programs 08/15/2005
Deliverable complete O: 66. Potentially provide temporary holding at Three Mile Dam for fall Chinook out planting programs 11/15/2005
Deliverable complete P: 64. Spawn summer steelhead at Minthorn 05/31/2005 09/29/2005
Deliverable complete Q: 64. Spawn spring Chinook salmon at South Fork Walla Walla 09/20/2005 09/29/2005
Deliverable complete R: 64. Spawn fall Chinook salmon at Three Mile Dam 12/10/2005 12/10/2005
Deliverable complete S: 64. Potentially spawn Coho salmon at Three Mile Dam 12/10/2005
Deliverable complete T: 60. Assist in collection of samples from adult fish for disease analysis 12/31/2005 12/31/2005
Deliverable complete U: 61. Maintain Minthorn 12/31/2005 12/31/2005
Deliverable complete V: 61. Maintain Pendleton 12/31/2005 12/31/2005
Deliverable complete W: 61. Maintain Thornhollow 12/31/2005 12/31/2005
Deliverable complete X: 61. Maintain Bonifer 12/31/2005 12/31/2005
Deliverable complete Y: 61. Maintain Imeques 12/31/2005 12/31/2005
Deliverable complete Z: 61. Maintain South Fork Walla Walla 12/31/2005 12/31/2005
Deliverable complete AA: 61. Maintain Three Mile Dam 12/31/2005 12/31/2005
Deliverable complete AB: 157. Collect biological data, snouts, and scales from adults 12/31/2005 12/31/2005
Deliverable complete AC: 157. Collect juvenile outmigration data at the Westland Canal juvenile facility 07/30/2005 09/28/2005
Deliverable complete AD: 119. Prepare FY 2006 Statement of Work and Budget Plan 09/30/2005 10/13/2005
Deliverable complete AE: 174. Participate in development of Umatilla Hatchery and Basin Annual Operation Plan 09/30/2005 09/29/2005
Participate in Umatilla Management and Monitoring and Evaluation Oversite Committee coordination meetings AF: 118. Participate in Umatilla Mgmt & M&E Oversite Committee coordination meetings 12/31/2005 12/31/2005
Deliverable complete AG: 122. Participate in development of Walla Walla Hatchery Master Plan 12/31/2005 12/31/2005
Deliverable complete AH: 141. Umatilla Hatchery Satellite Facilities Operation and Maintenance Status Reports 07/15/2005 09/29/2005
Deliverable complete AI: 132. Umatilla Hatchery Satellite Facilities Operation and Maintenance Annual Report 05/31/2005 09/28/2005
Deliverable complete AJ: 165. Produce Environmental Compliance Documentation 01/01/2005 09/28/2005
Deliverable complete AK: 119. Manage and Administer Project 09/28/2005

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Salmonids
  • 3 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 3 instances of WE 64 Spawn Fish
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 56 Acclimate Juvenile Fish
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 2 instances of WE 56 Acclimate Juvenile Fish
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 56 Acclimate Juvenile Fish
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 56 Acclimate Juvenile Fish

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 56 Acclimate juvenile summer steelhead at Minthorn
B 56 Acclimate juvenile summer steelhead at Pendleton
C 56 Acclimate juvenile coho salmon at Pendleton
D 56 Acclimate juvenile coho salmon at Pendleton
E 56 Acclimate juvenile spring Chinook salmon at Imeques
F 56 Acclimate juvenile spring Chinook salmon at Imeques
G 56 Acclimate juvenile spring Chinook salmon at Imeques
H 56 Acclimate juvenile fall Chinook salmon at Thornhollow
I 56 Acclimate juvenile fall Chinook salmon at Thornhollow
J 66 Hold adult summer steelhead at Minthorn for spawning
K 66 Hold adult spring Chinook salmon at South Fork Walla Walla for spawning
L 66 Hold adult fall Chinook salmon at Three Mile Dam for spawning
M 66 Potentially hold adult coho salmon at Three Mile Dam for spawning
N 66 Provide temporary holding at South Fork Walla Walla for spring Chinook out planting programs
O 66 Potentially provide temporary holding at Three Mile Dam for fall Chinook out planting programs
P 64 Spawn summer steelhead at Minthorn
Q 64 Spawn spring Chinook salmon at South Fork Walla Walla
R 64 Spawn fall Chinook salmon at Three Mile Dam
S 64 Potentially spawn Coho salmon at Three Mile Dam
T 60 Assist in collection of samples from adult fish for disease analysis
U 61 Maintain Minthorn
V 61 Maintain Pendleton
W 61 Maintain Thornhollow
X 61 Maintain Bonifer
Y 61 Maintain Imeques
Z 61 Maintain South Fork Walla Walla
AA 61 Maintain Three Mile Dam
AB 157 Collect biological data, snouts, and scales from adults
AC 157 Collect juvenile outmigration data at the Westland Canal juvenile facility
AD 119 Prepare FY 2006 Statement of Work and Budget Plan
AE 174 Participate in development of Umatilla Hatchery and Basin Annual Operation Plan
AF 118 Participate in Umatilla Mgmt & M&E Oversite Committee coordination meetings
AG 122 Participate in development of Walla Walla Hatchery Master Plan
AH 141 Umatilla Hatchery Satellite Facilities Operation and Maintenance Status Reports
AI 132 Umatilla Hatchery Satellite Facilities Operation and Maintenance Annual Report
AJ 165 Produce Environmental Compliance Documentation
AK 119 Manage and Administer Project
AL 185 Periodic Status Reports for BPA