21787 REL 1: 200500200 - LOWER GRANITE DAM ADULT TRAP IMPROVEMENTS |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Jan Brady | Bonneville Power Administration | Yes | COR | jebrady@bpa.gov | (503) 230-4514 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
Jan Poolman | US Army Corps of Engineers (COE) | No | Administrative Contact | janice.d.poolman@usace.army.mil | (509) 527-7351 |
Karen Robison | US Army Corps of Engineers (COE) | Yes | Technical Contact | karen.k.robison@usace.army.mil | (509) 527-7614 |
Nancy Weintraub | Bonneville Power Administration | No | Env. Compliance Lead | nhweintraub@bpa.gov | (503) 230-5373 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Routine mgmt of contract | 07/02/2007 | 07/03/2007 | |
Supervise and Administer Construction Contract for LGR Dam Adult Fish Trap Modifications | B: 70. Supervision and Administration | 09/30/2007 | 08/15/2008 | |
Engineering During Construction of Lower Granite Adult Fish Trap Modifications | C: 70. Engineering During Construction | 09/30/2007 | 09/30/2007 | |
Construction and Construction Administration of Trap Modifications (Design/Build Contract) | D: 70. Construction | 09/30/2007 | 12/31/2007 | |
FY06 Annual Report | E: 132. Annual Report | 08/31/2007 | 08/27/2007 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Routine mgmt of contract | 02/09/2007 | ||||||
B | 70 | Supervision and Administration | 08/26/2005 | ||||||
C | 70 | Engineering During Construction | 08/26/2005 | ||||||
D | 70 | Construction | 12/20/2005 | ||||||
E | 132 | Annual Report | 02/09/2007 | ||||||
F | 185 | Periodic Status Reports for BPA | 02/09/2007 |