NEPA Checklist |
A: 165. Complete NEPA Analysis and Documentation |
|
10/14/2006 |
09/21/2006 |
Summary of Activites |
B: 118. EXPIRED: Coordinate Restoration Efforts with Stakeholders |
|
05/30/2007 |
05/30/2007 |
Project Descriptions/Agreements |
C: 114. Identify and Select New Restoration Projects |
|
05/31/2007 |
05/31/2007 |
Complete Preliminary Dataset |
D: 175. Collect Preliminary Design Data For New Projects |
|
05/31/2007 |
05/31/2007 |
Install New Culvert |
E: 184. Install Culvert on N. Fork Alder Creek |
|
09/30/2006 |
09/21/2006 |
Complete Channel Construction |
F: 30. Benewah Creek Channel construction |
|
10/30/2006 |
10/31/2006 |
Vegetate Disturbed Areas |
G: 47. Plant Disturbed Areas in Benewah Creek |
|
05/30/2007 |
05/25/2007 |
Plant 10,000 Conifers |
H: 47. Enhance Floodplain Plant Communities |
|
05/30/2007 |
05/18/2007 |
Modify/Replace LWD Structures |
I: 186. Maintain Instream Structures at Treatment Sites |
|
10/31/2006 |
10/11/2006 |
Complete Herbicide Treatments and Replant |
J: 22. Conduct O&M Activities at WF Lake Creek |
|
05/31/2007 |
05/31/2007 |
Remove Brook Trout from Benewah Creek |
K: 166. EXPIRED: Remove Brook Trout from Benewah Creek |
|
09/06/2006 |
09/21/2006 |
Analyze Data from Brook Trout Removal |
L: 162. Analyze Data from Brook Trout Removal from Benewah Creek |
|
01/01/2007 |
02/28/2007 |
Install Migration Traps in Lake and Benewah Creeks |
M: 70. Install and Maintain Migration Traps Lake and Benewah Creeks |
|
05/31/2007 |
05/31/2007 |
Monitor Movements of Adfluvial WCT in Lake and Benewah Creeks |
N: 157. Trap Juvenile and Adult Adfluvial Westslope Cutthroat Trout in Lake and Benewah Creeks |
|
05/31/2007 |
05/31/2007 |
Operational PIT Tag System |
O: 70. Install PIT tag antenna system in Benewah Creek |
|
05/31/2007 |
05/18/2007 |
PIT Tag Juvenile Cutthroat in Lake and Benewah Creeks |
P: 158. PIT Tag Juvenile Adfluvial Westslope CutthroatTrout in Lake Creek and Benewah Creek |
|
05/31/2007 |
05/31/2007 |
Population Estimates of Salmonids in Target Watersheds |
Q: 157. Sample Salmonids in Target Watersheds for Population Estimation |
|
10/31/2006 |
11/10/2006 |
Complete Database of Biological Parameters for Target Watersheds |
R: 160. Biological Data Management |
|
05/31/2007 |
05/31/2007 |
Completed Analysis from Trapping and PIT Tagging in Lake and Benewah Creeks. |
S: 162. Analyze Data Generated from Salmonid Trapping and PIT Tagging in Lake and Benewah Creeks |
|
02/01/2007 |
03/23/2007 |
Population and Production Estimates for Target Watersheds |
T: 162. Analyze Data Generated from Salmonid Sampling in Target Watersheds |
|
12/01/2006 |
12/22/2006 |
Completed Inventories |
U: 157. Measure Physical Habitat in Reference and Treatment Reaches in Target Watersheds |
|
10/31/2006 |
10/20/2006 |
Measured Water and Air Temperature |
V: 157. Measure Water and Air Temperature in Lake, Benewah, and Evans Creek Watersheds |
|
05/31/2007 |
05/31/2007 |
Measurement of Thermal Heterogeneity in Benewah Creek |
W: 156. Measure Summer and Winter Thermal Heterogeneity in Benewah Creek |
|
02/28/2007 |
03/15/2007 |
Complete Database of Physical Habitat and Temperature Attributes |
X: 160. Physical Data Management |
|
05/31/2007 |
05/31/2007 |
Analyses of Physical Habitat and Temperature Data |
Y: 162. Analyze Data from Physical Habitat Sampling and Temperature Monitoring in Target Watersheds |
|
02/01/2007 |
03/23/2007 |
Complete Record of Education/Outreach Activities |
Z: 99. Provide Education and Outreach Opportunities |
|
05/31/2007 |
05/31/2007 |
Accrual Estimates/FY07 SOW/Metrics Reports |
AA: 119. Manage and Administer Project |
|
05/31/2007 |
05/31/2007 |
Completed FY05 and Draft FY06 Annual Reports |
AC: 132. Produce Annual Report |
|
05/31/2007 |
|
Stock and maintain pond sites |
AD: 187. Conduct O&M for Put and Take Fisheries |
|
11/30/2006 |
11/30/2006 |
Monitor site conditions |
AE: 157. Implement M&E for Put and Take Fisheries |
|
11/30/2006 |
11/30/2006 |