Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 30969: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Project Number:
Title:
Umatilla Fish Passage Operations
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
30969
Contract Title:
1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Continuation:
Previous: Next:
25827: 1988-022-00 EXP UMATILLA FISH PASSAGE OPS.
  • 36317: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Status:
Closed
Contract Description:
Umatilla Fish Passage Operations Project
Statement of Work and Budget FY 2007

BPA Project Number: 1983-435-00
Contract Number: 20591
Performance/Budget Period: January 1, 2007 - December 31, 2007
Technical Contacts:

Gary James, Fisheries Program Manager
Phone: (541) 276-4109
E-mail: garyjames@ctuir.com
Fax: (541) 276-2397

Brian Zimmerman, Fish Passage/Artificial Production Program Supervisor
Phone: (541) 966-2376
E-mail: brianzimmerman@ctuir.com
Fax: (541) 276-4348
James P. Bronson, Project Leader
Phone: (541) 966-2398
E-mail: prestonbronson@ctuir.com
Fax: (541) 276-4348

Administrative Contacts:

Michelle Thompson, Manager/Administrative Operations
Phone: (541) 966-2323
E-mail: michellethompson@ctuir.com
Fax: (541) 276-3317

E-mail: michellethompson@ctuir.com
Fax: (541) 276-3317

Julie Burke, Fish and Wildlife Administrative Manager
Phone: (541) 966-2372
E-mail: julieburke@ctuir.com
Fax: (541) 966-2397

Background

In the 1980's, CTUIR and ODFW began implementing the Umatilla Fisheries Restoration Plan.  An integral part of that effort was to address inadequate flow and migration conditions by constructing fish passage facilities, initiating a trap and haul program, and implementing the Umatilla Basin Project flow enhancement effort.  The Fish Passage Operations Project objective is to increase adult and juvenile migrant survival in the Umatilla Basin.  The project provides survival benefits for both hatchery and natural production by operating and maintaining ladders, bypasses, screen sites, trap facilities, and hauling equipment and coordinating these operations with flow enhancement measures and diversion activities.  The project also provides valuable support to other projects by refining fish passage criteria, collecting return and migration data, and collecting and transporting broodstock.    

Project Goal

Increase survival of migrating juvenile and adult salmon and steelhead in the Umatilla Basin by operating passage facilities, flow enhancement measures, trapping facilities, and transport equipment to provide adequate passage conditions.  

Location of Project

Threemile Dam Facility on the lower Umatilla River near the town of Umatilla

McKay Reservoir on McKay Creek just south of the town of Pendleton

The project works in the entire Umatilla River Basin, primarily in the mainstem between river mile 1 and 55 Umatilla River.
Account Type(s):
Expense
Contract Start Date:
01/01/2007
Contract End Date:
12/31/2007
Current Contract Value:
$315,556
Expenditures:
$261,731

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Preston Bronson Umatilla Confederated Tribes (CTUIR) Yes Technical Contact prestonbronson@ctuir.org (541) 429-7277
Julie Burke Umatilla Confederated Tribes (CTUIR) No Administrative Contact julieburke@ctuir.org (541) 429-7292
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Timmie Mandish Bonneville Power Administration Yes COR tamandish@bpa.gov (503) 230-3983
Rosemary Mazaika Bonneville Power Administration Yes F&W Approver rxmazaika@bpa.gov (503) 230-5869
Paul Rabb Umatilla Confederated Tribes (CTUIR) No Administrative Contact paulrabb@ctuir.org (541) 429-7165
Michelle Thompson Umatilla Confederated Tribes (CTUIR) No Administrative Contact michellethompson@ctuir.org (541) 429-7227
Nancy Weintraub Bonneville Power Administration No Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation A: 165. Environmental Compliance 01/01/2007 01/01/2007
Monitor Passage Conditions B: 186. Monitor Passage Conditions 12/31/2007 12/31/2007
Fish counts and transport information C: 157. Adult Return and Transport Data 12/31/2007 12/31/2007
Provide broodstock for artificial propagation program. D: 66. Provide broodstock for artificial production program 12/31/2007 12/31/2007
Safe transport of fish E: 28. Transport of Upstream And Downstream Migrants 12/31/2007 12/31/2007
Provide adult and juvenile transportation F: 61. Operate Hauling Equipment 12/31/2007 12/31/2007
Provide technical comments for fish passage improvement efforts G: 122. Provide Facility Design Technical Review 12/31/2007 12/31/2007
Provide Transportation Assistance H: 66. Provide Transportation Assistance 12/31/2007 12/31/2007
Coordination of passage facility operation and maintenance I: 189. Coordinate Passage Facility Operations 12/31/2007 12/31/2007
Ensure adequate migration conditions J: 189. Coordinate Umatilla Passage Program 12/31/2007 12/31/2007
Monthly Status Reports K: 141. Prepare Monthly Status Reports 12/31/2007 12/31/2007
2008 draft SOW and accrual reports L: 119. Manage and Administer Project 10/01/2007 10/01/2007
2006-2007 Annual Report. M: 132. 2006-2007 Annual Report 12/31/2007 12/31/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Fish
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 02/09/2007
B 186 Monitor Passage Conditions 02/18/2007
C 157 Adult Return and Transport Data 02/18/2007
D 66 Provide broodstock for artificial production program 02/18/2007
E 28 Transport of Upstream And Downstream Migrants 02/18/2007
F 61 Operate Hauling Equipment 02/18/2007
G 122 Provide Facility Design Technical Review 02/09/2007
H 66 Provide Transportation Assistance 02/18/2007
I 189 Coordinate Passage Facility Operations 02/09/2007
J 189 Coordinate Umatilla Passage Program 02/09/2007
K 141 Prepare Monthly Status Reports 02/09/2007
L 119 Manage and Administer Project 02/09/2007
M 132 2006-2007 Annual Report 02/09/2007
N 185 Periodic Status Reports for BPA 02/09/2007