Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 32732: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Project Number:
Title:
Restoration of Bull Trout Passage at Albeni Falls Dam
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
32732
Contract Title:
2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Continuation:
Previous: Next:
n/a
  • 37624: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Status:
Closed
Contract Description:
Bull trout in the Columbia River Basin were listed as Threatened by the US Fish and Wildlife Service (USFWS) in 1998 (USFWS 2000).  Bull trout populations are threatened by habitat degradation and fragmentation, past fisheries management practices, poor water quality, and blockage of migratory corridors.  Pend Oreille River and Lake is a core area within the Northeast Washington Recovery Unit of the Columbia Basin bull trout population (USFWS 2002a, 2002b).  Recovery of Pend Oreille bull trout is limited by the fact that dams on the mainstem Pend Oreille River (Albeni Falls and Box Canyon dams) have blocked migration of bull trout between Lake Pend Oreille and spawning/rearing areas (USFWS 2002a, 2002b). Albeni Falls Dam is a federal facility under the responsibility of the action agencies (US Army Corps of Engineers, Bonneville Power Administration, and Bureau of Reclamation).  Albeni Falls Dam created two types of problems for bull trout in the Pend Oreille Basin. First, bull trout from natal tributaries above the dam, that either became entrained or had elected to volitionally pass below the dam, were unable to return to spawn in their natal tributaries. (Source populations could include bull trout spawning in the Priest River, inlet tributaries of Pend Oreille Lake, or tributaries of the Clark Fork River below or above Cabinet Gorge Dam.) Second, adfluvial bull trout that formerly spawned in tributaries below the dam and migrated upstream to a cold water refuge in Lake Pend Oreille, Idaho were no longer able to do so.

The goal of this project is to provide temporary upstream passage for bull trout at Albeni Falls Dam on the Pend Oreille River. We propose to collect bull trout below the dam using boat electrofishing.  Any bull trout captured will be biopsied via hole punch and their DNA sent to the USFWS lab in Abernathy, Washington for rapid analysis within 48 hours. Each DNA sample will be compared to DNA from other bull trout populations in the Priest River drainage, Pend Oreille Lake tributaries, and Clark Fork drainage and an assignment will be made as to its probable region of origin.  Prior to release each fish will be implanted with a combination radio-acoustic transmitter to ascertain if the spawning tributary it selected was the same as its assigned tributary. A system of stationary radio receiving stations and airplane/truck/boat surveys will be used to monitor the movement of the tagged fish. This project provides direct on-the-ground benefits for endangered bull trout in the Pend Oreille Basin because it will allow fish, whose migration corridor has been blocked by a dam without fish passage, to return to their natal streams and contribute their genes (which would otherwise have been lost) to the spawning population.
Account Type(s):
Expense
Contract Start Date:
05/01/2007
Contract End Date:
04/30/2008
Current Contract Value:
$203,460
Expenditures:
$174,326

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Todd Andersen Kalispel Tribe Yes Technical Contact tandersen@knrd.org (509) 447-7245
Mickey Carter Bonneville Power Administration Yes Env. Compliance Lead macarter@bpa.gov (503) 230-5885
Jason Connor Kalispel Tribe Yes Contract Manager jconnor@knrd.org (509) 447-7285
Terry Holtcamp Jr Bonneville Power Administration Yes Contracting Officer taholtcamp@bpa.gov (503) 230-3518
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Joe Maroney Kalispel Tribe Yes Supervisor jmaroney@knrd.org (509) 447-7272
Carlos Matthew Bonneville Power Administration Yes COR cjmatthew@bpa.gov (503) 230-3418
Holly (EWU) McLellan Eastern Washington University No Interested Party hmclellan@mail.ewu.edu (509) 359-7498
Jason Olson Kalispel Tribe Yes Technical Contact jolson@knrd.org (509) 447-7290
Allan (EWU) Scholz Eastern Washington University No Interested Party ascholz@mail.ewu.edu (509) 359-6397
Virgil Watts III Bonneville Power Administration Yes Interested Party vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Idaho scientific collection, transportation, and federal permits A: 165. Obtain necessary permits and set up contract for genetic analysis 01/31/2008 12/20/2007
Install fish monitoring equipment B: 70. Procure, install and test stationary radio receiver stations 06/20/2007 06/20/2007
Weekly electrofishing collection of bull trout below Albeni Falls Dam C: 157. Weekly electrofishing collecting a representative sample of bull trout below Albeni Falls Dam 11/15/2007 04/30/2008
Implanting of radio tags D: 158. Implant combination radio acoustic transmitter into bull trout 11/30/2007
Annual maintenance of monitoring equipment E: 70. Annual overhaul and recalibration of ground receiver stations 03/28/2008 03/28/2008
Genetic Analysis F: 157. Rapid response genetic analysis of bull trout biopsy samples 04/30/2008 04/30/2008
Bull trout transported above Albeni Falls Dam G: 28. Transport bull trout above Albeni Falls Dam 04/30/2008
Electrofishing data entry H: 157. Compile electronic spread sheet data base of electrofishing data 04/30/2008 04/30/2008
Downloading stationary ground radio receiver I: 157. Download stationary ground radio receiving station 04/30/2008
Tracking of radio tagged fish with aircraft, vehicle, and boat. J: 157. Mobile tracking surveys by fixed wing aircraft, vehicle, and boat 04/30/2008
Data analysis of tracking data K: 162. Data reduction and analysis 04/30/2008
Project coordination among stakeholders L: 189. Project coordination among all stakeholders 04/30/2008 04/30/2008
Funding Package - Submit draft to COTR M: 119. Manage Project 02/01/2008 02/01/2008
Final report uploaded to the BPA website N: 132. Submit Annual Report for the period (5/1/2007) to (4/30/2008) 04/30/2008 05/13/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain necessary permits and set up contract for genetic analysis 02/09/2007
B 70 Procure, install and test stationary radio receiver stations 04/17/2007
C 157 Weekly electrofishing collecting a representative sample of bull trout below Albeni Falls Dam 02/09/2007
D 158 Implant combination radio acoustic transmitter into bull trout 02/09/2007
E 70 Annual overhaul and recalibration of ground receiver stations 02/09/2007
F 157 Rapid response genetic analysis of bull trout biopsy samples 02/09/2007
G 28 Transport bull trout above Albeni Falls Dam 02/09/2007
H 157 Compile electronic spread sheet data base of electrofishing data 02/09/2007
I 157 Download stationary ground radio receiving station 02/09/2007
J 157 Mobile tracking surveys by fixed wing aircraft, vehicle, and boat 02/09/2007
K 162 Data reduction and analysis 02/09/2007
L 189 Project coordination among all stakeholders 02/09/2007
M 119 Manage Project 02/09/2007
N 132 Submit Annual Report for the period (5/1/2007) to (4/30/2008) 02/09/2007
O 185 Periodic Status Reports for BPA 02/09/2007