% Produce Environmental Compliance Documentation |
A: 165. % Produce Environmental Compliance Documentation |
|
02/28/2010 |
12/31/2009 |
Manage and Administer Project |
B: 119. Manage and Administer Projects for CMZ N4, CMZ 6, CMZ 11, CMZ 17 and CMZ 20 |
|
09/26/2008 |
09/26/2008 |
Completed draft design report for CMZ N4 |
D: 175. Survey and Design for CMZ N4 |
|
09/15/2008 |
09/26/2008 |
Summary of coordination activities |
E: 189. Coordinate restoration efforts with stakeholders |
|
09/26/2008 |
09/26/2008 |
Complete Final CMZ 11 Construction Documents |
F: 175. Survey and Design for CMZ 11 |
|
04/30/2008 |
04/30/2008 |
Feasibility Analysis and Alternatives Analysis for CMZ 6, CMZ 17 and CMZ 20 |
G: 175. Feasibility Analysis and Alternatives Analysis for CMZ 6, CMZ 17 and CMZ 20 |
|
12/31/2008 |
09/26/2008 |
Completed survey data for CMZ 6, CMZ 17 or CMZ 20 |
H: 175. Survey and Design for CMZ 6, CMZ 17 or CMZ 20 |
|
02/20/2009 |
02/20/2009 |
Develop a monitoring plan for CMZ 11 |
I: 174. Develop a monitoring plan for CMZ 11 |
|
04/30/2008 |
04/30/2008 |
Pre-construction monitoring report |
J: 157. Collect pre-construction monitoring data for CMZ 11 |
|
09/26/2008 |
09/26/2008 |
Complete activities prior to in-water work at CMZ 11 |
K: 30. Complete activities prior to in-water work at CMZ 11 |
|
08/08/2008 |
08/08/2008 |
Complete in-water work to construct the channel for CMZ 11 |
L: 30. Complete in-water work to construct the channel for CMZ 11 |
|
08/08/2008 |
08/08/2008 |
Add large woody debris and rock elements to constructed channel for CMZ 11 |
M: 29. Add large woody debris and rock elements to constructed channel for CMZ 11 |
|
08/22/2008 |
08/22/2008 |
Complete activities after in-water work at CMZ 11 |
N: 30. Complete activities after in-water work at CMZ 11 |
|
07/31/2009 |
07/31/2009 |
Develop solicitation for revegetation of disturbed area |
O: 47. Vegetate disturbed areas at CMZ 11 |
|
09/26/2008 |
09/26/2008 |
Attach Progress Report in Pisces |
P: 132. Submit Progress Report for the period (09 27 2007) to (09 26 2008) |
|
09/26/2008 |
09/26/2008 |
% Produce Environmental Compliance Documentation |
Q: 165. % A2: Produce Environmental Compliance Documentation |
|
02/28/2010 |
06/01/2010 |
% Completed draft design report |
R: 175. % A2: Survey and Design for one of CMZ 6, CMZ 17 or CMZ 20 |
|
02/28/2010 |
02/28/2010 |
% Develop a monitoring plan for one of CMZ 6, CMZ 17 or CMZ 20 |
S: 174. % A2: Develop a monitoring plan for one of CMZ 6, CMZ 17 or CMZ 20 |
|
02/28/2010 |
12/11/2009 |
% Manage and Administer Project |
T: 119. % A2: Manage and Administer Projects for CMZ N4, CMZ 6, CMZ 11, CMZ 17 and CMZ 20 |
|
02/28/2010 |
06/01/2010 |
% Summary of coordination activities |
U: 189. % A2: Coordinate restoration efforts with stakeholders |
|
02/28/2010 |
06/01/2010 |
Complete Final CMZ N4 Construction Documents |
V: 175. A2: Survey and Design for CMZ N4 |
|
07/31/2009 |
07/31/2009 |
% Completed draft design report |
W: 175. % A2: Survey and Design for 2nd one of CMZ 6, CMZ 17 or CMZ 20 |
|
12/31/2009 |
09/30/2009 |
Develop a monitoring plan for CMZ N4 |
X: 174. A2: Develop a monitoring plan for CMZ N4 |
|
06/26/2009 |
06/26/2009 |
Pre-construction monitoring report |
Y: 157. A2: Collect pre-construction monitoring data for CMZ N4 |
|
12/31/2009 |
12/31/2009 |
Post-construction monitoring report |
Z: 157. A2: Collect post-construction monitoring data for CMZ 11 and CMZ N4 |
|
12/31/2009 |
06/01/2010 |
Complete activities prior to in-water work |
AA: 184. A2: Complete activities prior to in-water work at CMZ N4 |
|
12/31/2009 |
07/17/2009 |
% Complete in-water work to install the culverts for CMZ N4 |
AB: 184. % A2: Complete in-water work to install the culverts for CMZ N4 |
|
02/28/2010 |
10/02/2009 |
Add large woody debris and rock elements to oxbow for CMZ N4 |
AC: 29. A2: Add large woody debris and rock elements to oxbow for CMZ N4 |
|
08/21/2009 |
08/21/2009 |
Complete activities after in-water work at CMZ N4 |
AD: 184. A2: Complete activities after in-water work at CMZ N4 |
|
12/31/2009 |
06/01/2010 |
Sign off on work. |
AE: 47. A2: Vegetate disturbed areas at CMZ 11 |
|
12/31/2008 |
12/31/2008 |
Attach Progress Report in Pisces |
AF: 132. #A2: Submit Progress Report for the period (09 27 2008) to (12 31 2009) |
|
06/01/2010 |
06/01/2010 |
Complete in-water work to install the culverts for CMZ N4 |
AG: 184. #A2: Complete in-water work to install the culverts for CMZ N4 |
|
06/01/2010 |
06/01/2010 |