Contract 37261: 1984-025-00 JOSEPH CREEK, GRANDE RONDE
Project Number:
Title:
Grande Ronde and Umatilla Fish Habitat Improvement Program
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
37261
Contract Title:
1984-025-00 JOSEPH CREEK, GRANDE RONDE
Contract Continuation:
Previous: Next:
32053: 1984-025-00 EXP JOSEPH CREEK, GRANDE RONDE RIVER
  • 41677: 1984-025-00 EXP ODFW BLUE MOUNTAIN FISH HABITAT IMPROVEMENT
  • 41904: 1984-025-00 EXP ODFW BLUE MOUNTAIN FISH HABITAT IMPROVEMENT
Contract Status:
Closed
Contract Description:
ODFW Northeast Oregon Habitat Projects FY2008 Summary

This project continues Oregon Department of Fish and Wildlife's efforts to restore the habitat of salmon, steelhead and other fishes in the Blue Mountain Province as mitigation for losses resulting from development of the federal Columbia River Power System.  

This project has completed 58 projects restoring 3302 acres of riparian and 79.95 miles of stream habitat in the Blue Mountain Province since it began in 1985.  Restoration efforts have focused on the Joseph Creek, Wallowa River and Upper Grande Ronde River systems based on recommendations of agencies, tribes and the Grande Ronde Model Watershed Program (CTUIR 1983; Noll et al. 1988; ODFW et al. 1990; and, Anderson et al. 1992, Huntington 1993, GRMWP 1994, , and Mobrand and Lestelle 1997,  NPCC 2004a , NPCC 2004b).  Review of these restoration efforts has found improving conditions in project areas for salmon, steelhead and other native fishes (Beschta et al. 1991, Kauffman et al. 2002 and McGowan 2005).

Project activities planned for this contract period include project planning, design, permitting, and construction as well as maintenance and implementation monitoring of existing projects.  Staff of this project works closely with the Grande Ronde Model Watershed Program (GRMWP) who provides policy direction, project review and organizes project funding for specific projects.  They work with staff of CTUIR  to support the activities of other agencies (NRCS, ODOT, USFWS, NOAA, USFS, etc) implementing habitat restoration projects.

ODFW will work on channel restoration projects during this contract period.  These include:

• Wallowa River Phase 2: Complete channel reconstruction by installing the diversion structures and compacted plug, activating the new channel, and reclaiming the old channel beginning in summer FY 2008 thus restoring 0.4 miles of channelized river. Riparian planting that was started in FY2007 will continue.

• Ladd Creek Phase 1: West and Middle Forks (Catherine Creek) - Continue with conducting  field surveys, design, and permitting with construction beginning in summer FY 2007 and finishing in FY2009 to restore 3.3 miles of channelized stream;


In addition, ODFW staff are working to complete the Hidaway fence project started in FY2006.  At this time no other fences are slated for FY2008. As stated in the SOW, additional fence construction will occur if time and money allow.

ODFW staff will also inspect 53 habitat projects built earlier, conduct maintenance (i.e. fix fencing and watergaps,  etc) necessary to ensure habitat treated by these projects continue to improve and perform implementation monitoring to track this improvement.  Administration, reporting and outreach activities will be conducted as well.


Literature Cited

Anderson, J.W., and others.  1992.  Upper Grande Ronde River Anadromous Fish Habitat Protection, Restoration, and Monitoring Plan.  USFS, ODFW, CRITFC, CTUIR, NPT, OSU

Beschta, R. L., Platts, W.S., and  B. Kauffman.  1991.  Field review of fish habitat improvement projects in the Grande Ronde and John Day River basins of eastern Oregon

CTUIR.  1983.  Summary Report:  Salmon and steelhead habitat improvement initiatives--John Day, Umatilla, Grande Ronde and Imnaha drainages.

GRMWP.  1994.   Grande Ronde Model Watershed Operations - Action Plan.  Available from www.grmw.org/docs/reports_assessments/GRMWP_Plan_1994/GRMWP_Action_Plan_1994.pdf

Huntington, Charles W.  1993.  Stream and Riparian Conditions in the Grande Ronde Basin:  A report to the Grande Ronde Model Watershed Board, Clearwater Biostudies, Inc.

Kauffman, J. B., P. Bayley, H. Li, P. Mc Dowell and R.L Beschta.  2002.  Research/Evaluate Restoration of NE Oregon streams: Effects of livestock enclosures (corridor fencing) on riparian vegetation, stream geomorphic features and fish populations.  DOE/BP  00006210-1.  Available from BPA online at https://efw.bpa.gov/searchpublications/

Mobrand, L. and L. Lestelle.  1997.  Application of the ecosystem diagnosis and treatment method to the Grande Ronde model watershed project.  BPA Task Order Number 95AT61148, P.O. Box 3621, Portland, OR.

McGowan, V.R. 2005.  Grande Ronde Basin Fish Habitat Enhancement Project:  2004 Annual Report to BPA.  Oregon Department of Fish and Wildlife, La Grande, OR.  

Noll, W., Williams, S., and R. Boyce.  1988.  Grande Ronde river basin fish habitat improvement implementation plan.  Oregon Department of Fish and Wildlife.

NPCC.  2004a. Grande Ronde Subbasin Plan.  Prepared for Northwest Power and Conservation Council by Grande Ronde Model Watershed Program.  Pgs 491.  Available from www.nwcouncil.org/fw/subbasinplanning/granderonde/plan/

NPCC.  2004b. Imnaha Subbasin Plan.  Prepared for Northwest Power and Conservation Council by Wallowa County Natural Resources Advisory Committee.  Paged by section.  Available from www.nwcouncil.org/fw/subbasinplanning/imnaha/plan/

ODFW, CTUIR, NPT, WDF, WDW.  1990.  Grande Ronde River Subbasin Salmon and Steelhead Production Plan.  Northwest Power Planning Council.  Portland, OR.
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
02/28/2009
Current Contract Value:
$364,994
Expenditures:
$364,994

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Description: Mature transplanting along with trench willow installation

Contract(s):

37261

Dimensions: 1024 x 685

Description: In cooperation with Wallowa Resources, presented river restoration and redd surveying for outdoor school. Penny Arentsen of Wallowa resources took the photo.

Contract(s):

37261

Dimensions: 640 x 427


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Local, state and federal permits A: 165. Environmental compliance for construction activities 02/28/2009 02/28/2009
Ladd Creek Phase 1 Restoration B: 175. Ladd Creek Phase 1:West and Middle Forks 02/28/2009
Ladd Creek Phase 1 Restoration C: 30. Ladd Creek Phase 1:West and Middle Forks 02/28/2009
Ladd Creek Phase 1 Restoration D: 29. Ladd Creek Phase 1:West and Middle Forks 02/28/2009
Ladd Creek Phase 1 Restoration E: 181. Ladd Creek Phase 1:West and Middle Forks 02/28/2009
Ladd Creek Phase 1 Vegetation F: 47. Ladd Creek Phase 1:West and Middle Forks 02/28/2009
Wallowa River Phase 2 Restoration G: 30. Wallowa River Phase 2 02/28/2009 10/15/2008
Wallowa River Phase 2 Restoration H: 29. Wallowa River Phase 2 02/28/2009 10/15/2008
Wallowa River Phase 2 Restoration I: 181. Wallowa River Phase 2 02/28/2009 10/15/2008
Wallowa River Phase 2 Vegetation J: 47. Wallowa River Phase 2 02/28/2009 12/15/2008
Hidaway Fence K: 40. Hidaway Creek 09/30/2008 09/15/2008
Dark Canyon Fence L: 40. Other riparian fencing projects as time and money allows: Dark Canyon Creek 02/28/2009 12/31/2008
Monitoring results M: 157. Monitor restoration projects 02/28/2009 02/28/2009
Healthy riparian vegetation N: 22. Manage riparian projects 02/28/2009 02/28/2009
Functioning riparian enclosures O: 186. Manage riparian projects 02/28/2009 02/28/2009
Functioning channel restoration P: 186. Manage stream channel restorations 02/28/2009 02/28/2009
Outreach Q: 99. Community Outreach 02/28/2009 02/28/2009
Technical Review R: 122. Provide support for GRMW 02/28/2009 02/28/2009
Regional Coordination S: 189. Regional Coordination 02/28/2009 02/28/2009
List of potential new Blue Mountain Province projects for implementation in future contracts T: 114. Work with cooperators to identify new projects 02/28/2009 02/28/2009
Annual Report results and discussion. U: 162. Prepare field data for Annual Report 02/28/2009 02/28/2009
2007 Annual Report V: 132. Submit Progress Report for the period (Mar 1, 2007 to Feb 28, 2008) 01/15/2009 12/30/2008
Project Management W: 119. Manage and Administer Project 02/28/2009 02/28/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance for construction activities 02/09/2007
B 175 Ladd Creek Phase 1:West and Middle Forks 02/09/2007
C 30 Ladd Creek Phase 1:West and Middle Forks 02/01/2008
D 29 Ladd Creek Phase 1:West and Middle Forks 02/01/2008
E 181 Ladd Creek Phase 1:West and Middle Forks 02/01/2008
F 47 Ladd Creek Phase 1:West and Middle Forks 02/05/2008
G 30 Wallowa River Phase 2 02/01/2008
H 29 Wallowa River Phase 2 02/01/2008
I 181 Wallowa River Phase 2 02/01/2008
J 47 Wallowa River Phase 2 02/01/2008
K 40 Hidaway Creek 02/01/2008
L 40 Other riparian fencing projects as time and money allows: Dark Canyon Creek
M 157 Monitor restoration projects 05/23/2007
N 22 Manage riparian projects 02/01/2008
O 186 Manage riparian projects 02/09/2007
P 186 Manage stream channel restorations 02/09/2007
Q 99 Community Outreach 02/09/2007
R 122 Provide support for GRMW 02/09/2007
S 189 Regional Coordination 02/09/2007
T 114 Work with cooperators to identify new projects 02/09/2007
U 162 Prepare field data for Annual Report 02/09/2007
V 132 Submit Progress Report for the period (Mar 1, 2007 to Feb 28, 2008) 02/09/2007
W 119 Manage and Administer Project 02/09/2007
X 185 Periodic Status Reports for BPA 02/09/2007