Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 38293: 2007-396-00 CAP NURSERY BRIDGE COST-SHARE
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
38293
Contract Title:
2007-396-00 CAP NURSERY BRIDGE COST-SHARE
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
WALLA WALLA 1135   - Nursery Street Bridge
(based on current fed funds thru FY08)

                FED 75%         $4,290,569
                Spon 25%        $1,430,190
                Est TPC           $5,720,758
                      
Sponsor has funded to date (prior to this contract grant award):        $1,353,257
                      
Sponsor funds owing to match cost percentage:   $76,933

Amount of this contract $80,010 (includes admin fee for MFWCD) should bring the sponsor funds in line with Federal funds (thru FY2008).
=================================================================================
FED & Sponsor funds expended (see notes)
WI           Funding#     CEFMS Amt              x8862 (sponsor)
0027XW  G426747      -                                -
002J12    G426706      3,086,819.43           1,053,583.52           SEC. 1135 - CONST. -  WALLA WALLA RIVER, OR
002MJJ    G429238      171,861.92             204,076.63              SEC. 1135 - S&A - WALLA WALLA RIVER, OR
002MQ2   G426786       -
04B114    G450340      35,385.74
09J9HB    G444489      56,866.62                18,688.78               SEC. 1135 - WW RIV - PHASE II - POST CONSTRUCTION
19KHBB   G443808       -  
A00646    G426746       -  
CJGDL2   G443806       -  
FC252L    G443087       -  
GBBC3F   G450341      271,653.69               29,740.78               A3270-Prepare CAP Plans & Specifications (R) [105888] (downstream stabilization)
HB963B    G432471      -  
Plus Non-Tied WI          670,456.38

Total FED Work Allowance 4,293,043.78 *              1,306,089.71 **

Notes:
**Sponsor amount does not match above because some of the funds are obligated on a contract (but not expended yet)
*  Amount does not match above because some of the funds are obligated but not expended yet. Also deduct  2,474.78 for pre-Feas amount.
Account Type(s):
Capital
Contract Start Date:
06/16/2008
Contract End Date:
06/30/2009
Current Contract Value:
$80,010
Expenditures:
$80,010

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Firm Fixed Price
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Sarah Branum Bonneville Power Administration Yes COR stbranum@bpa.gov (503) 230-5115
George Gillette Milton Freewater Water Control District No Supervisor gilletg@wwics.com (541) 938-7284
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Stan Heller US Army Corps of Engineers (COE) Yes Contract Manager stanley.g.heller@usace.army.mil (509) 527-7258
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Administrative work complete A: 119. Project Management 09/30/2008 09/30/2008
100% design for Nursery Bridge downstream stabilization B: 175. 100% Design Review for Downstream Stabilization at Nursery Bridge 06/01/2009 06/15/2009
Comments submitted in DR Checks C: 122. Review Gravel Management Plan 04/20/2009 06/15/2009
Gravel Management Plan completed D: 174. Produce Gravel Management Plan 06/30/2009 06/15/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project Management 02/09/2007
B 175 100% Design Review for Downstream Stabilization at Nursery Bridge 02/09/2007
C 122 Review Gravel Management Plan 02/09/2007
D 174 Produce Gravel Management Plan 02/09/2007
E 185 Periodic Status Reports for BPA 02/09/2007
F 132 Gravel Mgmt Plan & 100% Designs will substitute for annual report 02/09/2007