Funding Package - Submit draft to COTR |
A: 119. Routine admin of contract |
|
05/31/2009 |
05/31/2009 |
environmental compliance documents |
B: 165. produce proof of environmental compliance to BPA |
|
07/07/2008 |
07/07/2008 |
Projects grouped into categories with a 10-year research plan and development of individual project |
C: 114. Identify and Select Projects |
|
03/31/2010 |
03/31/2010 |
Progress and Benefits Tracking System |
D: 98. Develop a progress and benefit tracking system |
|
09/30/2009 |
03/31/2010 |
Science review of Accord projects. |
E: 122. Develop Technical Review Process |
|
03/31/2010 |
03/31/2010 |
Columbia Basin Accords Information Systems |
F: 99. Information and Outreach |
|
07/31/2009 |
07/31/2009 |
Submit and update proposal list quarterly |
G: 174. Quarterly mutual reprioritization |
|
08/31/2009 |
08/31/2009 |
Produce Finalized list of projects |
H: 174. Produce a finalized list of projects |
|
07/31/2009 |
07/31/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
I: 174. 2008-501-00 GSI to Evaluate Catch |
|
07/31/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
J: 174. 2008-502-00 Expanded Tribal Catch Sampling |
|
03/31/2010 |
|
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
K: 174. 2008-503-00 Sockeye Studies |
|
07/31/2009 |
07/20/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
L: 174. 2008-504-00 Sturgeon Genetics |
|
01/30/2010 |
11/01/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
M: 174. 2008-505-00 Streamnet Library |
|
07/31/2009 |
09/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
N: 174. 2008-506-00 Smolt Monitoring Video Feasibility Project |
|
07/31/2009 |
03/01/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
O: 174. 2008-507-00 Tribal Monitoring Data |
|
08/15/2009 |
08/15/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
P: 174. 2008-508-00 Power Anlys Catch Samplg Rates |
|
03/31/2010 |
|
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
Q: 174. 2008-509-00 Sea Lion Hazing |
|
04/30/2009 |
01/01/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
R: 174. 2008-510-00 SNP Discovery |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
S: 174. 2008-511-00 Bonneville GSI |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
T: 174. 2008-512-00 Water Quality Monitoring |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
U: 174. 2008-513-00 Improved Escapement Estimation |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
V: 174. 2008-514-00 Mgmt Scenarios Climate Change |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
W: 174. 2008-515-00 Modeling Survival Sp Chinook |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
X: 174. 2008-516-00 Climate Change Database |
|
07/31/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
Y: 174. 2008-517-00 Monitoring Trends-Habitat |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
Z: 174. 2008-518-00 Upstream Migration Timing |
|
04/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AA: 174. 2008-519-00 Traits Related to Recovery |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AB: 174. 2008-520-00 Genetic Baseline Expansion |
|
07/31/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AC: 174. 2008-521-00 Landscape Genetics (Ch & Sthd) |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AD: 174. 2008-522-00 Supplementation Benefits/Risks |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AE: 174. 2008-523-00 Supplementation Monitoring |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AF: 174. 2008-524-00 Lamprey Passage Design |
|
03/31/2010 |
03/31/2010 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AG: 174. 2008-525-00 Recondition W. Steelhead Kelt |
|
07/31/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AH: 174. 2008-526-00 Snake River Kelts-Capital |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AI: 174. 2008-527-00 John Day Reprogramming & Const |
|
03/31/2010 |
03/31/2010 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AJ: 174. 2008-528-00 Regional RM&E Coordination |
|
07/31/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AM: 174. 2008-907-00 Genetic Assessment of Columbia River Stocks |
|
06/30/2009 |
03/09/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AN: 174. 2009-004-00 Monitoring Recovery Trends in Key Sp. Chinook Habitat Variables & Validation of Indicato |
|
05/30/2009 |
05/11/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AO: 174. 2009-005-00 Influence of Environment and Landscape on Salmonid Genetics |
|
06/30/2009 |
06/30/2009 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AP: 174. 2009-008-00 Climate Change Impacts |
|
03/31/2010 |
03/31/2010 |
BPA accepts all documents: 1) Proposal and 2) responses, as final 3) Initial contract is signed |
AQ: 174. 2009-009-00 Basinwide Supplementation Monitoring |
|
05/30/2009 |
04/01/2009 |