Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 39456: 2007-396-00 CAP SPRING CREEK PASSAGE - WWCCD
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
39456
Contract Title:
2007-396-00 CAP SPRING CREEK PASSAGE - WWCCD
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Spring Creek is a high quality tributary of Dry Creek which dumps into the Walla Walla River and supports a remnant run of Mid-Columbia steelhead.  This project will address what appear to be two complete passage barriers a short distance from the mouth of Spring Creek.  This project will make an additional 3.2 miles of tributary habitat available to steelhead for spawning and rearing.  Our early plans are to use series of rock weirs to step the surface elevation up 6-12 inches per weir, a design we have used successfully on other tributary streams.  Project design will be done by the WWCCD staff engineer who will coordinate with WDFW and CTUIR passage specialists.  Construction will be done during the in-water work window of 2009.

With delays in obtaining cultural resources clearance, WWCCD will seek an extension/variance in the in-water work window to complete construction later in the fall/winter of 2009/2010.  Cultural resource clearance is now expected by about December 7.
Account Type(s):
Capital
Contract Start Date:
09/22/2008
Contract End Date:
05/31/2010
Current Contract Value:
$127,607
Expenditures:
$127,607

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Audrey Ahmann Walla Walla County Conservation District (SWCD) Yes Contract Manager audrey.ahmann@wwccd.net (509) 522-6340x107
Sarah Branum Bonneville Power Administration Yes COR stbranum@bpa.gov (503) 230-5115
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Rick Jones Walla Walla County Conservation District (SWCD) Yes Supervisor rick.jones@wwccd.net (509) 522-6340x110
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Lisa Marko MacLellan Bonneville Power Administration No Env. Compliance Lead lmmarko@bpa.gov (503) 230-4047
Jennifer Stolz Bonneville Power Administration No Interested Party jpstolz@bpa.gov (503) 230-3233


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
BPA contract requirements complete B: 119. Manage Spring Creek passage project 05/31/2010 05/31/2010
PE stamped plans and specifications C: 174. Develop engineered design and construction cost estimate 06/30/2009 06/30/2009
Documentation and assistance to support BPA's Environmental Compliance Group D: 165. Produce environmental documents and construction easements 12/31/2009 12/31/2009
Project completed according to PE stamped design E: 184. Construct Spring Creek fish passage structures 05/31/2010 05/31/2010
Attach Progress Report in Pisces F: 132. Submit a progress report for the period 9/20/08 to 4/30/10 05/31/2010 05/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 119 Manage Spring Creek passage project 02/09/2007
C 174 Develop engineered design and construction cost estimate 02/09/2007
D 165 Produce environmental documents and construction easements 02/09/2007
E 184 Construct Spring Creek fish passage structures 12/07/2009
F 132 Submit a progress report for the period 9/20/08 to 4/30/10 02/09/2007