Produce environmental compliance documentation |
A: 165. Environmental Compliance |
|
04/01/2009 |
02/25/2009 |
Develop three alternative water sources for livestock on Little Catherine Creek |
B: 34. Water Source Development - Project 1,2,3: Little Catherine Creek |
|
09/30/2011 |
10/08/2010 |
Riparian exclosure fence on unnamed tributary to Little Catherine Creek |
C: 40. Fence Installation - Project 4: Little Catherine Creek Unnamed Tributary |
|
09/30/2009 |
09/30/2009 |
Riparian exclosure fence construction on Lick Creek |
D: 40. Fence Installation - Project 5: Lick Creek |
|
09/30/2009 |
09/30/2009 |
Construct exclusion fence & place Large Wood barriers on tributary to Lick Creek |
E: 40. Fence Installation - Project 6: Lick Creek Tributary |
|
11/30/2009 |
11/30/2009 |
Place Large Wood Material Livestock Barriers On Lick Creek |
F: 40. Large Wood barrier Placement - Project 7: Lick Creek |
|
11/30/2009 |
11/30/2009 |
Develop two alternative water sources for livestock near Collins Creek |
G: 34. Water Source Development - Project 8A and 8B |
|
09/30/2009 |
09/30/2009 |
Riparian exclosure fence construction on Corral Creek |
H: 40. Fence Installation - Project 9: Corral Creek |
|
11/30/2009 |
09/30/2009 |
Develop two alternative water sources for livestock on Prong Creek |
I: 34. Water Source Development - Project 10: Prong Creek |
|
11/30/2010 |
10/08/2010 |
Drift fence construction on South Fork Catherine Creek |
J: 40. Fence Installation - Project 12: South Fork Catherine Creek |
|
09/30/2011 |
11/01/2011 |
Develop three alternative water sources for livestock near Scout Creek |
K: 34. Water Source Development - Project 13, 14, 15: Scout Creek |
|
09/30/2009 |
09/30/2009 |
Construct 1.5 miles of riparian exclosure/drift fence near Camp Creek. |
L: 40. Fence Insatllation - Project 16: Camp Creek |
|
11/30/2010 |
11/01/2010 |
Develop alternative water sources for livestock on Indian Creek |
M: 34. Water Source Development - Project 17: Indian Creek |
|
09/30/2009 |
09/30/2009 |
Develop two alternative water sources for livestock near Fly Creek |
N: 34. Water Source Development - Project 18 and 19: Fly Creek |
|
09/30/2011 |
09/30/2011 |
Construct a solar powdered water source for livestock |
O: 34. Water Source Development - Project 20: Warm Springs Creek |
|
11/30/2011 |
11/30/2011 |
Construct 150’ of buck and pole fencing, place 500 feet of LWM barriers. |
P: 40. Fence Installation - Project 21: Last Chance Creek |
|
09/30/2009 |
09/30/2009 |
Develop an alternative water source for livestock on Last Chance Creek |
Q: 34. Water Source Development - Project 21: Last Chance Creek |
|
09/30/2009 |
09/30/2009 |
Construct four 40’-60’ diameter ponds. |
R: 34. Water Source Development - Project 22A-D: Burnt Corral Creek |
|
09/30/2011 |
09/30/2011 |
Install one spring development and construct one 40 foot diameter pond. |
S: 34. Water Source Development - Project 23: Burnt Corral Creek |
|
09/30/2011 |
09/30/2011 |
Develop alternative water sources for livestock on Bear & Little Bear Creek |
T: 34. Water Source Development - Project 24: Bear & Little Bear Creek |
|
09/30/2009 |
09/30/2009 |
Develop alternative water sources for livestock on Smith Creek |
U: 34. Water Source Development - Project 25 A-C: Smith Creek |
|
09/30/2009 |
09/30/2009 |
Successful project administration |
V: 119. Project Management and Administration |
|
09/30/2011 |
09/30/2011 |
Attach Final Annual report in PISCES |
W: 132. Submit Final Report for the 12/1/08 - 11/30/11 |
|
11/30/2011 |
11/30/2011 |