Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 44048: 200820200 EXP PROTECT & RESTORE TUCANNON WATERSHED
Project Number:
Title:
Protect and Restore Tucannon Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Tucannon 100.00%
Contract Number:
44048
Contract Title:
200820200 EXP PROTECT & RESTORE TUCANNON WATERSHED
Contract Continuation:
Previous: Next:
n/a
  • 45826: 200820200 EXP PROTECT & RESTORE TUCANNON WATERSHED
Contract Status:
Closed
Contract Description:
Project funds furnished by BPA and issued to CTUIR for the purpose of restoring and protecting fisheries habitat in the Tucannon Watershed.  This is the first contract under this new Fish Accord project.  The scope of the work to be performed under this project has been previously reviewed by the ISRP for Columbia Conservation District's project 1994-018-06.
Account Type(s):
Expense
Contract Start Date:
08/04/2009
Contract End Date:
12/31/2009
Current Contract Value:
$116,740
Expenditures:
$116,740

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Sarah Branum Bonneville Power Administration Yes COR stbranum@bpa.gov (503) 230-5115
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Eric Hoverson Umatilla Confederated Tribes (CTUIR) Yes Contract Manager erichoverson@ctuir.org (541) 429-7555
Gary James Umatilla Confederated Tribes (CTUIR) Yes Supervisor garyjames@ctuir.org (541) 429-7285
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jim Webster Umatilla Confederated Tribes (CTUIR) Yes Technical Contact jameswebster@ctuir.org (541) 429-7240
Nancy Weintraub Bonneville Power Administration Yes Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR A: 119. Manage Tucannon Watershed Habitat Improvement Projects 10/01/2009 12/15/2009
Establish beneficial relationships and agreements with federal and state entities B: 191. Coordination of habitat restoration with other entities 12/31/2009 12/10/2009
Survey data results produced C: 115. Survey habitat conditions for the Tucannon River and tributaries 12/31/2009 12/01/2009
Analysis and results of pre-implementation survey data D: 162. Compile survey data for Spring Creek and upper Tucannon River Watershed 12/31/2009 12/01/2009
Prioritized Project List for FY 2010 uploaded to Pisces E: 114. Identify, prioritize and select projects for habitat improvement 12/31/2009 12/29/2009
Management Plans F: 174. Prepare restoration plans for Spring Creek & the upper Tucannon Watershed 10/31/2009 10/15/2009
All environmental compliance clearances obtained G: 165. Obtain environmental clearance when necessary for applicable enhancement projects 11/01/2009 10/29/2009
Abandoned cars and appliances removed from riparian area H: 27. Removal of car bodies, discarded machinery and appliances 12/31/2009 11/20/2009
LWD placed in the stream channel I: 29. Install woody debris in Spring Creek 12/31/2009 11/20/2009
LWD placed in Cummings Creek J: 29. Install woody debris in the upper Tucannon Watershed 12/31/2009 12/10/2009
Vegetative plantings completed K: 47. Plant native vegetation at project locations in Spring Creek and the upper Tucannon watershed 12/31/2009 11/30/2009
Culvert unplugged L: 85. Re-connect Spring Creek channel dissected by culvert at RM 0.1 12/31/2009 12/17/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage Tucannon Watershed Habitat Improvement Projects 02/09/2007
B 191 Coordination of habitat restoration with other entities 02/09/2007
C 115 Survey habitat conditions for the Tucannon River and tributaries 09/01/2009
D 162 Compile survey data for Spring Creek and upper Tucannon River Watershed 02/09/2007
E 114 Identify, prioritize and select projects for habitat improvement 02/09/2007
F 174 Prepare restoration plans for Spring Creek & the upper Tucannon Watershed 02/09/2007
G 165 Obtain environmental clearance when necessary for applicable enhancement projects 02/09/2007
H 27 Removal of car bodies, discarded machinery and appliances 10/01/2009
I 29 Install woody debris in Spring Creek 10/01/2009
J 29 Install woody debris in the upper Tucannon Watershed 10/05/2009
K 47 Plant native vegetation at project locations in Spring Creek and the upper Tucannon watershed 11/10/2009
L 85 Re-connect Spring Creek channel dissected by culvert at RM 0.1 10/01/2009
M 185 Periodic Status Reports for BPA 02/09/2007
N 132 Progress Report will be due under next contract 02/09/2007