Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 45233: 2007-398-00 CAP MANASTASH FLOW ENHANCEMENT
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
45233
Contract Title:
2007-398-00 CAP MANASTASH FLOW ENHANCEMENT
Contract Continuation:
Previous: Next:
35408: 200739800 CAP MANASTASH FLOW ENHANCEMENT
  • 58058: 2007-398-00 CAP MANASTASH FLOW ENHANCEMENT
Contract Status:
Closed
Contract Description:
This contract covers the capital portion of the Manastash Creek Instream Flow Enhancement Project, which is part of the larger Manastash Creek Restoration Project.  The expense portion is covered by contracted number 54238.
In Manastash Creek, several man-made structures (dams and unscreened diversions) reduce or eliminate fish passage, create the potential for fish entrainment into ditches, and contribute to diminished flow creating a low-flow or no-flow fish passage barrier. These diversions date to the 1870’s and have been actively diverting water for irrigation and stock water since then. Water rights in this watershed have been adjudicated and the Court’s conditional final order is in place.

The overall Manastash Creek Restoration Project includes providing fish screens to protect fish from entrainment in irrigation systems, removing barriers to fish passage and improving instream flow.  Funding is in place through BPA and the Washington Department of Ecology to complete the screening and passage portion of the project.
The Manastash Creek Instream Flow Enhancement Project's purpose is to accomplish the final goal, improving instream flow in lower Manastash Creek, by identifying and implementing projects. This project is guided by the Manastash Creek Restoration Project Instream Flow Enhancement Plan
completed by the Manastash Steering Committee.   The KCCD will work with all water right owners to identify water conservation projects in water delivery systems and water application systems (on-farm), potential options to convert to groundwater, and to match water right owners with groups who purchase or lease water rights. This contract not only identifies projects and implements projects, it will also serve to identify and secure additional funding sources to complete projects.  The Manastash Steering Committee will play a key role in prioritizing projects for implementation.

This contract will also include remaining funds from the BPA fish screening and passage portion of the project.  The remaining screening and passage funds will be used on project tasks not yet completed.  This includes, modifying the Barnes Road check structure, Abandoned Dam restoration and removal, installing and programming water metering telemetry for each diversion, removal and restoration of Reed, Hatfield, and Anderson, and coordinating installation of WDFW Pit Tag detectors at Barnes and MWDA diversion. The remaining funds and tasks will be competed by KCCD and HDR Engineering.  

2012 will be the final year of this contract; if FY2013 funds are approved for this project, it cannot be guaranteed that unspent contract funds remaining at the end of this contract will be approved for rescheduling to a new contract in 2013.
Account Type(s):
Capital
Contract Start Date:
11/15/2009
Contract End Date:
11/14/2012
Current Contract Value:
$814,718
Expenditures:
$814,718

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Anna Lael Kittitas County Conservation District Yes Supervisor anna.lael@kccd.net (509) 925-3352x7
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Sherry Swanson Kittitas County Conservation District Yes Contract Manager sherry-swanson@conservewa.net (509) 925-3352x6
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation and assistance to support BPA's Environmental Compliance Group B: 165. Environmental Compliance Documentation 11/14/2012 11/14/2012
Project Engineering and Design C: 175. Engineering and Designs 11/01/2012 11/01/2012
Gregerich Sprinkler Conversion D: 150. Gregerich Sprinkler Conversion 10/31/2010 10/21/2010
Anderville Sprinkler Conversion E: 150. Anderville Sprinkler Conversion 11/14/2011 12/08/2011
Dyk Sprinkler Conversion F: 150. Dyk Sprinkler Conversion 11/14/2011 10/13/2011
MWDA Ditch Flow Measuring Devices G: 148. MWDA Ditch Flow Measuring Devices 04/30/2010 04/30/2010
MWDA Pipeline - MWDA diversion to Hanson Road H: 149. MWDA pipeline - MWDA Diversion to Hanson Road 11/14/2012
Water Right Transactions I: 154. Develop Water Rights Transactions and Negotiate donations of water rights 11/14/2012 11/14/2012
Acquire 2nd Class MWDA water in perpetuity. J: 164. Acquire Water Instream at Manastash Diversion via donations 11/14/2012 10/24/2012
Trust 2nd class Anderson Diversion water rights in perpetuity. K: 164. Acquire Water Instream at Anderson Diversion via donation 11/14/2011 09/30/2011
Fish screening, passage and instream flow project management. L: 119. Manage Projects 09/30/2012 09/09/2011
Attach Progress Report in Pisces M: 132. Submit Draft Progress Report for the period Nov 2009 through Oct 2010 11/14/2011 12/06/2011
Attach Progress Report in Pisces N: 132. Submit Progress Report for the period Nov 2007 to Oct 2009 11/14/2011 12/06/2011
Mellergaard Sprinkler Conversion P: 150. Mellergaard Sprinkler Conversion 11/14/2012 11/14/2012
Trust 3rd and 4th class KJ Diversion water rights in perpetuity. Q: 164. Acquire Water Instream at Keach Jensen Diversion via donation 11/14/2012 11/14/2012
Attach Progress Report in Pisces R: 132. 3rd CCR 24921 - Submit Final Progress Report for the period Nov 2011 through Oct 2012 11/14/2012 11/14/2012
Dyk Sprinkler Conversion #2 S: 150. 3rd CCR 24921 -Dyk Sprinkler Conversion #2 11/14/2012
Harrell Sprinkler Conversion #1 T: 150. 3rd CCR 24921 -Harrell Sprinkler Conversion #1 11/14/2012 11/14/2012
Harrell Sprinkler Conversion #2 U: 150. 3rd CCR 24921 -Harrell Sprinkler Conversion #2 11/14/2012
Harrell Sprinkler Conversion #3 V: 150. 3rd CCR 24921 -Harrell Sprinkler Conversion #3 11/14/2012
Trust Reed Diversion water rights in perpetuity. W: 164. 3rd CCR 24921 -Acquire Water Instream at Reed Diversion via donation 11/14/2012 11/14/2012
Construction Management Complete X: 100. 3rd CCR 24921 -Remaining Fish Screen/Passage Projects 11/14/2012 11/14/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 149 Install Pipeline
  • 7 instances of WE 150 Install Sprinkler
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 3 instances of WE 164 Acquire Water Instream
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 150 Install Sprinkler
  • 1 instance of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 Environmental Compliance Documentation 02/09/2007
C 175 Engineering and Designs 02/09/2007
D 150 Gregerich Sprinkler Conversion 09/30/2009
E 150 Anderville Sprinkler Conversion 10/02/2010
F 150 Dyk Sprinkler Conversion 10/02/2012
G 148 MWDA Ditch Flow Measuring Devices 09/30/2009
H 149 MWDA pipeline - MWDA Diversion to Hanson Road 12/03/2012
I 154 Develop Water Rights Transactions and Negotiate donations of water rights 02/09/2007
J 164 Acquire Water Instream at Manastash Diversion via donations 09/30/2009
K 164 Acquire Water Instream at Anderson Diversion via donation 11/01/2009
L 119 Manage Projects 02/09/2007
M 132 Submit Draft Progress Report for the period Nov 2009 through Oct 2010 02/09/2007
N 132 Submit Progress Report for the period Nov 2007 to Oct 2009 11/01/2009
O 148 Reed Ditch Flow Measuring Devices 07/28/2010
P 150 Mellergaard Sprinkler Conversion 07/26/2012
Q 164 Acquire Water Instream at Keach Jensen Diversion via donation 11/18/2010
R 132 3rd CCR 24921 - Submit Final Progress Report for the period Nov 2011 through Oct 2012 11/15/2009
S 150 3rd CCR 24921 -Dyk Sprinkler Conversion #2 11/15/2009
T 150 3rd CCR 24921 -Harrell Sprinkler Conversion #1 02/02/2012
U 150 3rd CCR 24921 -Harrell Sprinkler Conversion #2 10/09/2012
V 150 3rd CCR 24921 -Harrell Sprinkler Conversion #3
W 164 3rd CCR 24921 -Acquire Water Instream at Reed Diversion via donation 02/03/2012
X 100 3rd CCR 24921 -Remaining Fish Screen/Passage Projects 11/15/2009