Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 46889: 2008-900-00 EXP ACCORD SBT ACCORD PLANNING & DVLPMNT
Project Number:
Title:
Accord Planning and Development-Shoshone-Bannock Tribe
Stage:
Closed
Area:
Province Subbasin %
Upper Snake Snake Upper 100.00%
Contract Number:
46889
Contract Title:
2008-900-00 EXP ACCORD SBT ACCORD PLANNING & DVLPMNT
Contract Continuation:
Previous: Next:
41350: 200890000 EXP SHBA-ACCORD PLANNING & DVLPMNT
Contract Status:
History
Contract Description:
Goal:  To complete a 10 Year Strategic Implementation Plan for all Shoshone-Bannock Tribes' Fish Accord projects.  The Columbia Basin Accords provide a unique opportunity to implement a variety of new and existing projects designed to improve fisheries resources in the Columbia River Basin and enhance habitat for both fish and wildlife.  

This is a one-time project/contract under the 10-year MOA to provide support for planning and implementation of MOA work.  The Strategic Plan will identify applicable basin-wide recovery goals, quantifiable project objectives and strategies to meet those goals and objectives within the framework of the Fish Accord.  Budgets may include subcontractors.  This project will provide strategic guidance for Tribal program managers to insure that the projects are planned strategically, scoped adequately, and well coordinated.  The Accord includes 5 new, 6 existing, and 1 expanded Shoshone-Bannock Tribes projects.
Account Type(s):
Expense
Contract Start Date:
04/01/2010
Contract End Date:
02/15/2011
Current Contract Value:
$123,460
Expenditures:
$123,460

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Submit accrual package to COTR B: 119. Routine Administration of Contract 09/10/2010 09/10/2010
Programmatic Cultural Resource Plan (may be under a separate contract) C: 165. Work with BPA on a programmatic cultural resource plan 02/15/2011 02/15/2011
Accord project plans reflect recovery planning D: 122. Participate in recovery planning 01/31/2011 01/31/2011
BPA accepts Implementation Plan E: 174. Accord Strategic Implementation Plan 02/15/2011 02/15/2011
BPA accepts all documents: 1) Proposal and 2) Responses, as final 3) Initial contract is signe F: 174. 2008-903-00 ESA Habitat Restoration 01/31/2011 01/31/2011
BPA accepts all documents: 1) Proposal and 2) Responses, as final 3) Initial contract is signed G: 174. 2008-905-00 Supplementation Projects 02/15/2011 02/15/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 174 Produce Plan
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 3 instances of WE 174 Produce Plan
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 3 instances of WE 174 Produce Plan
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/16/2010
B 119 Routine Administration of Contract 02/16/2010
C 165 Work with BPA on a programmatic cultural resource plan 02/16/2010
D 122 Participate in recovery planning 02/16/2010
E 174 Accord Strategic Implementation Plan 02/16/2010
F 174 2008-903-00 ESA Habitat Restoration 02/16/2010
G 174 2008-905-00 Supplementation Projects 02/16/2010
H 132 Progress Report not required 02/16/2010