Contract 47867: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Project Number:
Title:
Idaho Fish Screening Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
47867
Contract Title:
1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Contract Continuation:
Previous: Next:
43653: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
  • 53579: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Contract Status:
Closed
Contract Description:
Goal:   To provide management and operational support for a capital construction program dedicated to the protection of anadromous fish from loss in water diversions, improve fish passage at diversions for juvenile and adult anadromous fish, and improve stream flow conditions where possible.  Staff will process environmental regulatory documents, provide oversight to archaeologists and consulting engineers, engage in scoping activities, and negotiate with private landowners for habitat projects.  All projects require compliance with State of Idaho and Federal regulations including, but not limited to, IDAPA Title 42, IDAPA Title 36, National Environmental Policy Act, Clean Water Act, Endangered Species Act, Federal Land Management Policy Act, National Historical Preservation Act, and Magnuson-Stevens Fishery Conservation and Management Act.  

Project Coordination:  The Idaho Department of Fish & Game (IDFG) coordinates other funding sources with this Bonneville Power Administration (BPA) contract in order to maximize the potential for anadromous fish recovery efforts in the Salmon River basin.  

Background:   Since the 1800's, anadromous fish runs in the Columbia River have declined drastically.  Historically,  IDFG estimates that the Salmon River basin produced 39% of the spring Chinook salmon and 45% of the summer Chinook salmon in the Columbia River Basin (Idaho Department of Fish & Game, 1985).  Steelhead estimates for the Salmon River basin are not available but production was substantial.  Due to the low return of spring Chinook salmon to Idaho in 1974, all but treaty harvest was curtailed.  Since then,  harvest has been limited to a tribal fishery and occasional harvest of surplus hatchery stocks.  

Irrigation diversions date back to the 1860's in the Salmon River basin of the Snake River drainage and have impacted anadromous fish in a number of ways.  These impacts included loss of habitat, entrainment of smolts on their migration to the ocean,  and returning adults have been blocked by irrigation diversion wing dams.  Riparian corridors have been degraded by various management actions.

In 1938 the U.S. Congress passed the Mitchell Act in an attempt to partially mitigate for losses resulting from hydroelectric projects, logging, mining, and agricultural developments.  The Act provided a mechanism for conserving fishery resources of the Columbia River basin and created the Columbia River Fisheries Development Program (CRFDP).  The CRFDP program was extended to include the upper basin (above McNary) in 1956.  Between 1958 and 1966, IDFG constructed more than 200 screens on the main stem Salmon River and tributaries.  Today about 235 screens are in operation in Idaho.  

Funding was first provided to the IDFG  by BPA in 1994 for anadromous fisheries projects falling outside the scope of the Mitchell Act.  These funds were used in non-traditional ways to eliminate or consolidate irrigation diversions, improve fish passage, conserve water and provide proper screening of water withdrawals.  These projects have been undertaken by IDFG on a tributary wide basis to maximize the potential for success.

Location of Project:  All portions of the project are located in the Salmon River drainage.  This contract provides funding to support the capitalization project 1994-015-00.   Legal descriptions for each capital improvement project are located in the companion project 1994-015-00.

Results Expected:  Preliminary capital projects will be identified.  Landowner agreements will be ratified.  Topographic surveys will be conducted.  Cultural resource surveys will be conducted.  Biological evaluations will be conducted in areas of interest,  monitoring and evaluations of past projects will be completed, and all scoping will be completed for NEPA compliance.  Funding will provide office operation support.  

BPA Furnished Property:   Following submittal by IDFG of NEPA checklists, biological assessments, and cultural resource documentations BPA will provide NEPA determinations as applicable by Federal regulation.  It is anticipated that many determinations will be in accordance with BPA's Fish & Wildlife Program Environmental Impact Statement.
Account Type(s):
Expense
Contract Start Date:
07/01/2010
Contract End Date:
06/30/2011
Current Contract Value:
$200,031
Expenditures:
$200,031

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR A: 119. Routine Administration of Contract 05/02/2011 05/25/2011
Conduct public and private meetings with stakeholders. B: 114. Conduct meetings 05/30/2011 03/15/2011
Produce environmental compliance documents and permits. C: 165. Complete Environmental Compliance 05/30/2011 05/30/2011
Coordination Meetings D: 191. Agency Project Coordination 06/30/2011 03/17/2011
Stream Investigation Reports E: 157. Stream Investigations 05/31/2011 03/15/2011
Topographic Electronic Files F: 175. Topographic Surveys 06/30/2011 06/23/2011
Attach Progress Report in Pisces H: 132. Submit Progress Report for the period July 2010 thru June 2011 06/01/2011 06/23/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine Administration of Contract 07/01/2010
B 114 Conduct meetings 07/01/2010
C 165 Complete Environmental Compliance 07/01/2010
D 191 Agency Project Coordination 07/01/2010
E 157 Stream Investigations 07/01/2010
F 175 Topographic Surveys 07/01/2010
G 185 Periodic Status Reports for BPA 07/01/2010
H 132 Submit Progress Report for the period July 2010 thru June 2011 07/01/2010