Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 50547: 2000-027-00 EXP MALHEUR RIVER WILDLIFE MITIGATION
Project Number:
Title:
Malheur River Wildlife Mitigation
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Middle Snake Malheur 100.00%
Contract Number:
50547
Contract Title:
2000-027-00 EXP MALHEUR RIVER WILDLIFE MITIGATION
Contract Continuation:
Previous: Next:
45458: 200002700 EXP MALHUER RIVER WILDLIFE MITIGATION
  • 55222: 2000-027-00 EXP MALHEUR RIVER WILDLIFE MITIGATION
Contract Status:
Closed
Contract Description:
The Malheur River Wildlife Mitigation Project was purchased in November 2000 to compensate, in part, for the loss of fish and wildlife resources in the Columbia and Snake River Basins.  The 31,781-acre Project is located eleven miles east of Juntura, Oregon and is adjacent to the Malheur River.  The Project includes 6,385 deeded acres owned by the Burns Paiute Tribe, 4,154 acres leased from the Department of State Lands, and 21,242 acres leased from the BLM.  The Project is comprised of meadow, wetland, and shrub-steppe habitats and stretches for seven miles along the Malheur River.

In 2011, this contract will allow the Burns Paiute Tribe in the following management activities: complying with cultural resource and ESA requirements, improving and maintaining multiple vegetation communities through seeding projects, identifying and controlling noxious weeds, re-establishing a riparian corridor, work with BLM to permanently protect the BLM allotments, providing access, and education/coordination with tribal, government and general public parties.
Account Type(s):
Expense
Contract Start Date:
01/01/2011
Contract End Date:
12/31/2011
Current Contract Value:
$355,807
Expenditures:
$355,807

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Rebecca Fritz Burns-Paiute Tribe No Contract Manager Rebecca.Fritz@burnspaiute-nsn.gov (541) 573-8081
Kyle Heinrick Burns-Paiute Tribe Yes Technical Contact kyle.heinrick@burnspaiute-nsn.gov (541) 573-1375
Jason Kesling Burns-Paiute Tribe Yes Supervisor jason.kesling@burnspaiute-nsn.gov (541) 573-1375x2
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jenna Peterson Bonneville Power Administration Yes Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
Nicole Rutherford Bonneville Power Administration No Interested Party narutherford@bpa.gov (503) 230-4320
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Cultural Resource clearance complete A: 165. Cultural Resources/Tribal Monitor 12/31/2011 12/31/2011
Weed control B: 22. Weed Control 12/31/2011 12/31/2011
Maintained irrigation system C: 22. Maintain wet meadow irrigation system 12/31/2011 12/31/2011
WILL NOT BE COMPLETED D: 47. Plant dry-land grasses 09/30/2011 09/30/2011
Completed hay harvest. E: 22. Haying Operation 12/31/2011 07/31/2011
Planted Field into Triticale F: 47. Convert Old Alfalfa Field into Triticale Planting 12/31/2011 12/31/2011
Grazing Completed G: 53. Grazing Operation 12/31/2011
Data Collected and entered H: 157. Conduct Project Surveys 12/31/2011 12/31/2011
Access controlled I: 188. Control Access 12/31/2011 12/31/2011
Completed Planting in Hunter Creek J: 122. Hunter Creek Planting Plan 12/31/2011 12/31/2011
Community education and information K: 99. Public Education and Information 12/31/2011 12/31/2011
Tribal education complete L: 99. Tribal Community Education 12/31/2011 12/31/2011
Staff education and communication M: 99. Seminars/Training for Staff 12/31/2011 12/31/2011
Meeting and Plan Developed N: 114. Work with BLM to Permanently Protect BLM Allotments 12/31/2011
Verification of BPA posting 2011 annual report. O: 132. Submit Progress Report for the period (1/1/2011) to (12/31/2011) 12/31/2011 12/31/2011
Project administration P: 119. Project Administration 12/31/2011 12/31/2011
Irrigation dam and fish ladder in place and working R: 84. Construct Irrigation Dam and Fish Ladder 12/31/2011
Full Size Diesel Truck S: 98. Purchase Vehicle for Project 12/31/2011 12/31/2011
New heating and cooling system T: 98. Heating and Cooling System 12/31/2011 12/31/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 84 Remove/Install Diversion
Wildlife
  • 3 instances of WE 22 Maintain Vegetation
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 98 Other
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Cultural Resources/Tribal Monitor 01/01/2011
B 22 Weed Control 04/18/2011
C 22 Maintain wet meadow irrigation system 06/01/2011
D 47 Plant dry-land grasses 06/01/2011
E 22 Haying Operation 06/01/2011
F 47 Convert Old Alfalfa Field into Triticale Planting 05/12/2011
G 53 Grazing Operation 06/01/2011
H 157 Conduct Project Surveys 01/01/2011
I 188 Control Access 01/01/2011
J 122 Hunter Creek Planting Plan 01/01/2011
K 99 Public Education and Information 01/01/2011
L 99 Tribal Community Education 01/01/2011
M 99 Seminars/Training for Staff 01/01/2011
N 114 Work with BLM to Permanently Protect BLM Allotments 01/01/2011
O 132 Submit Progress Report for the period (1/1/2011) to (12/31/2011) 01/01/2011
P 119 Project Administration 01/01/2011
Q 185 Periodic Status Reports for BPA 01/01/2011
R 84 Construct Irrigation Dam and Fish Ladder 06/01/2011
S 98 Purchase Vehicle for Project 01/01/2011
T 98 Heating and Cooling System 01/01/2011