Environmental Compliance Documentation |
B: 165. Environmental Compliance Documentation |
|
06/01/2011 |
06/01/2011 |
Funding Package - Submit draft to COTR |
C: 119. Project Management |
|
09/01/2011 |
11/15/2011 |
Produce Draft Progress Report |
D: 132. Complete Draft Progress Report for the period (Dec 2010) to (Nov 2011) |
|
11/30/2011 |
11/30/2011 |
Task 1A: Juvenile sampling and marking data. |
E: 157. Task 1A: Conduct juvenile seining and PIT tagging activities in the South Fork Salmon River. |
|
11/30/2011 |
11/30/2011 |
Task 1A: Juvenile tagging data. |
F: 158. Task 1A: Mark/Tag juvenile anadromous salmonids captured in seining surveys. |
|
11/30/2011 |
11/30/2011 |
Task 1C: Juvenile sampling and marking data. |
G: 157. Task 1B: Conduct juvenile seining and PIT tagging activities in the Lemhi River. |
|
11/30/2011 |
11/23/2011 |
Task 1C: Juvenile tagging data. |
H: 158. Task 1B: Mark/Tag juvenile anadromous salmonids captured in seining surveys. |
|
11/30/2011 |
11/30/2011 |
South Fork Salmon River habitat survey data. |
I: 157. Task 2: South Fork Salmon River habitat sampling and LiDAR validation. |
|
11/30/2011 |
11/30/2011 |
Task 3A: Report on South Fork Salmon River PIT tag array performance and PIT tag detections. |
J: 157. Task 3A: Operate PIT tag Arrays in South Fork Salmon River. |
|
11/30/2011 |
11/30/2011 |
Task 3B: Report on Lemhi River PIT tag array performance and PIT tag detections. |
K: 157. Task 3B: Operate PIT tag Arrays in the Lemhi River. |
|
11/30/2011 |
11/30/2011 |
Task 4A: Install/remove rotary screw traps. |
L: 70. Task 4A: Install/remove South Fork Salmon River rotary screw traps. |
|
11/30/2011 |
11/30/2011 |
Task 4A: Report juvenile capture data, biological information, and PIT tagging data for SFSR t |
M: 157. Task 4A: Operate ISEMP screw traps in South Fork Salmon River. |
|
11/30/2011 |
11/30/2011 |
Task 4B: Install/remove rotary screw traps. |
N: 70. Task 4B: Assist in installation/removal of Lemhi River rotary screw traps. |
|
11/15/2011 |
11/15/2011 |
Task 4B: Report juvenile capture data, biological information, and PIT tagging data for Lemhi |
O: 157. Task 4B: Assist in operation of screw traps in Lemhi River. |
|
11/30/2011 |
11/30/2011 |
Task 5: Lower Granite Dam adult PIT tagging and biological sample data. |
P: 157. Task 5: Lower Granite Dam adult PIT tagging and data synthesis. |
|
11/30/2011 |
11/30/2011 |
Task 5: Conduct adult PIT tagging. |
Q: 158. Task 5: Lower Granite Dam adult PIT tagging. |
|
11/30/2011 |
11/30/2011 |
Develop and Refine ISEMP Survey Protocols |
R: 156. Develop and Refine ISEMP Survey Protocols |
|
11/30/2011 |
11/30/2011 |
Enter data using Automated Template Module in ISEMP Database |
S: 159. Enter data using Automated Template Module in ISEMP Database (IDFG) |
|
11/30/2011 |
11/30/2011 |
Enter data using Automated Template Module in ISEMP Database |
T: 159. Enter data using Automated Template Module in ISEMP Database (Nez Perce Tribe) |
|
11/30/2011 |
11/30/2011 |
Salmon and John Day subbasin Database support and data QA/QC |
U: 160. Manage databases for Salmon and John Day sub-basins |
|
11/30/2011 |
11/30/2011 |
Database trainings and data migration assistance to John Day and Salmon basins |
V: 161. Database training and support for Salmon and John Day basins |
|
11/30/2011 |
11/30/2011 |
Salmon Subbasin Data Analysis |
W: 162. ISEMP Salmon subbasin data analysis |
|
11/30/2011 |
11/30/2011 |
ISEMP Regional Data Analysis |
X: 162. ISEMP Regional Data Analysis |
|
11/30/2011 |
11/30/2011 |
Produce ISEMP funded activities annual report (IDFG) |
Y: 141. Produce Annual Report on ISEMP Activities (IDFG) |
|
11/15/2011 |
11/15/2011 |
Produce ISEMP funded activities annual report (IDFG) |
Z: 141. Produce Annual Report on ISEMP Activities (Nez Perce) |
|
11/15/2011 |
11/15/2011 |
ISEMP Salmon Subbasin Annual Report Review |
AA: 122. ISEMP Salmon Subbasin Annual Report Review |
|
11/30/2011 |
11/30/2011 |
ISEMP Coordination (QCI) |
AB: 189. ISEMP Project Coordination (QCI) |
|
11/30/2011 |
11/30/2011 |
ISEMP Project Coordination (IDFG) |
AC: 189. ISEMP Project Coordination (IDFG) |
|
11/30/2011 |
11/30/2011 |
ISEMP Project Coordination (NPT) |
AD: 189. ISEMP Project Coordination (Nez Perce) |
|
11/30/2011 |
11/30/2011 |
ISEMP Salmon Subbasin Coordination (QCI) |
AE: 191. ISEMP Salmon Subbasin Coordination (QCI) |
|
11/30/2011 |
11/30/2011 |
ISEMP Salmon Subbasin Coordination (IDFG) |
AF: 191. ISEMP Salmon Subbasin Coordination (IDFG) |
|
11/30/2011 |
11/30/2011 |
ISEMP Salmon Subbasin Coordination (NPT) |
AG: 191. ISEMP Salmon Subbasin Coordination (Nez Perce) |
|
11/30/2011 |
11/30/2011 |
ISEMP Annual Review |
AH: 141. ISEMP Annual Draft Report Review |
|
11/30/2011 |
11/30/2011 |
Obtain permits for installation of PIT tag arrays proposed under the fast-track proposal process |
AI: 165. Obtain permits for installation of PIT tag arrays proposed under the fast-track proposal process |
|
07/10/2011 |
11/30/2011 |
Manage PIT tag array installation for PIT tag arrays proposed under the fast-track review proc |
AJ: 119. Manage PIT tag array installation for PIT tag arrays proposed under the fast-track review proc |
|
11/30/2011 |
11/30/2011 |
Annual report describing implementation of PIT tag arrays proposed in the fast-track process. |
AK: 132. Submit Progress Report for the period (12/2010) to (11/2011) |
|
11/30/2011 |
11/30/2011 |
Conduct site surveys to identify primary and backup location for PIT tag arrays. |
AL: 175. Conduct site surveys to identify primary and backup location for PIT tag arrays. |
|
08/01/2011 |
06/30/2011 |
Assist in installation of PIT tag arrays. |
AM: 70. Assist in installation of PIT tag arrays. |
|
11/30/2011 |
11/30/2011 |
Operate ISEMP PIT tag arrays funded under the fast-track process. |
AN: 157. Operate ISEMP PIT tag arrays funded under the fast-track process. |
|
11/30/2011 |
11/30/2011 |
Operate ISEMP PIT tag arrays (Biomark Yearly O&M) |
AO: 157. Operate ISEMP PIT tag arrays (Biomark Yearly O&M) |
|
11/30/2011 |
11/30/2011 |
Transfer PIT tag array data to QCInc server, STEM databank, and PTAGIS. |
AP: 159. Transfer PIT tag array data to QCInc server, STEM databank, and PTAGIS. |
|
11/30/2011 |
11/30/2011 |
Program and maintain PIT tag array data storage system. |
AQ: 160. Program and maintain PIT tag array data storage system. |
|
11/30/2011 |
11/30/2011 |
Transfer PIT tag array data to regional databases, comanagers, and serve summary data |
AR: 161. Transfer PIT tag array data to regional databases, comanagers, and serve summary data |
|
11/30/2011 |
11/30/2011 |
Develop and test methods to calculate instantaneous and periodic PIT tag array efficiency. |
AS: 162. Develop and test methods to calculate instantaneous and periodic PIT tag array efficiency. |
|
11/30/2011 |
11/30/2011 |
LiDAR Data Analysis and Habitat Metric Development |
AT: 162. LiDAR Data Analysis and Habitat Metric Development |
|
11/30/2011 |
11/30/2011 |
Cumulative Analysis Report |
AU: 132. Cumulative Analysis Report |
|
07/31/2011 |
09/02/2011 |