Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 51399: 2010-001-00 EXP LOWER WENATCHEE INSTREAM FLOW ENHANCEMENT
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
51399
Contract Title:
2010-001-00 EXP LOWER WENATCHEE INSTREAM FLOW ENHANCEMENT
Contract Continuation:
Previous: Next:
n/a
  • 56585: 2010-001-00 EXP LOWER WENATCHEE INSTREAM FLOW ENHANCEMENT
Contract Status:
Closed
Contract Description:
This is one of three projects funded, in part, by BPA (matching funds from SRFB, Ecology, Tributary Committees, USFWS, BOR and others) through the Upper Columbia Habitat Project (project #2010-001-00) for FFY 2011 (project # 2010-001-00).  The costs associated with administering this contract are covered under the programmatic project (contract # 50379).  This project is also funded under the Columbia Basin Water Transaction Program as the Pioneer Piping Project, which funded staff time in the beginning to develop the project.

The objective of this project is to improve habitat by increasing flows in the Lower Wenatchee by up to 15 cubic-feet per second (cfs), as described in the water right, with up to an additional 2.5 cfs of return flow by delivering water upstream to users from the new point of diversion on the Columbia River.  This project will create infrastructure improvements for the Pioneer Water Users Association (PWUA) who operate and maintain the Gunn Ditch, which supplies water for agricultural and residential irrigation to shareholders.  The project has several components that will address limiting factors in the Wenatchee and is part of the Upper Columbia Salmon Recovery Plan implementation schedule.  By initiating this project, other biologically productive restoration activities can also be implemented, including habitat improvements, diversion removal and possible side channel reconnection.

There is over 29,000 linear feet of pipeline that will be installed.  There will be one pump station on the Columbia River with two pumps for redundancy, which will be metered.  The turnouts on farm will be sized with the appropriate orifice to restrict flows to the appropriate quantity, but will not be metered.  The irrigators will be responsible for long term maintenance of the system.

The entire water right will be transferred to instream flow in the Wenatchee River and then a portion of it will then (approximately 30%) be pumped back up out of the Columbia River to the shareholders.  Trout Unlimited will be submitting the Trust Water Rights Application and will shepherd it through Ecology, but the point of diversion change will be completed by the PWUA Attorney.
Account Type(s):
Expense
Contract Start Date:
02/01/2011
Contract End Date:
01/31/2012
Current Contract Value:
$51,061
Expenditures:
$51,061

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Douglas Corkran Bonneville Power Administration Yes Env. Compliance Lead dfcorkran@bpa.gov (503) 230-7646
Kathleen Deason Upper Columbia Salmon Recovery Board Yes Administrative Contact kathleen.deason@ucsrb.org (509) 888-5347
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Julie Morgan Upper Columbia Salmon Recovery Board Yes Supervisor julie.morgan@ucsrb.org (509) 662-4710
Aaron Penvose Trout Unlimited (TU) Yes Technical Contact apenvose@tu.org (509) 888-0970
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Derek Van Marter Upper Columbia Salmon Recovery Board Yes Contract Manager derek.vanmarter@ucsrb.org (509) 670-1462


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Contract Administration. A: 119. Manage BPA contracting requirements 01/31/2012 01/26/2012
Complete EC permitting processes B: 165. Complete EC permitting processes 12/30/2011 12/30/2011
Pipeline Installed C: 149. Implement pipeline installation 01/31/2012 01/26/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 149 Install Pipeline
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 149 Install Pipeline

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage BPA contracting requirements 02/01/2011
B 165 Complete EC permitting processes 02/01/2011
C 149 Implement pipeline installation
D 185 Periodic Status Reports for BPA 02/01/2011
E 132 Project Completion Report (funded through separate contract) 02/01/2011