Contract 51700: 1993-066-00 CAP OREGON FISH SCREENS
Project Number:
Title:
Oregon Fish Screens Project
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
51700
Contract Title:
1993-066-00 CAP OREGON FISH SCREENS
Contract Continuation:
Previous: Next:
41267: 1993-066-00 CAP OREGON FISH SCREENS
  • 56395: 1993-066-00 CAP OREGON FISH SCREENS
Contract Status:
Closed
Contract Description:
The project provides immediate and long-term protection for anadromous and resident fish species in the John Day, Umatilla, and Walla Walla subbasins by the installation or replacement of outdated fish protection and passage devices on private irrigation diversions and dam structures. These facilities reduce or eliminate fish loss associated with irrigation withdrawals and passage barriers.   The program uses cost share from NOAA, OWEB Measure 66 (M66) funds, and BPA for implementation.  From 1993 to 1997, the program focused on an inventory of irrigation diversions in need of fish screens, or due to the change in NOAA criteria for Salmonids needed replaced, in the John Day, Umatilla and Walla Walla Basins.  During this time, there were also several pump irrigation screens installed.  In 1997, the program, directed the focus on replacement of non-criteria fish screens and related passage barriers, throughout the John Day, Umatilla and Walla Walla Subbasins.  The program wishes to expand into the Deschutes subbasin since we are in the same province.  Since the start of the cooperative efforts between BPA, NOAA, OWEB/M66, ODFW, private landowners, and a multitude of government entities, to present, the program has installed over 215 gravity irrigation diversion screens, over 175 pump screens and 13 fishways that meet the new criteria.  Annual Reports have been provided to BPA that detail results.  

The program will install 19 (+) new or replacement fish screens (see footnote 1), and implement a fish passage project (s) if identified.  The work elements will aid in the breakdown of the costs and describe the actions needed to continue these efforts.

Footnote 1:  Program obligations will be pending BPA's environmental compliance approval process.  If project environmental compliance process inhibits project installations beyond March 1, 2011, the Program's current commitment to 19 (+) new or replacement fish screen installations, and the implementation of a fish passage project (s) if identified, will decrease according to the amount of time needed for approval.  The Program will continue working on all other milestones except for field installations for maximum efficiency until the environmental compliance is approved.  There will be $30,000 withheld from the budget for contracting cultural resource studies only to be used in the event that BPA can not meet the timelines and/or their commitment to survey the potential 60 fish screen sites identified by the Program for the 2009 contract.  Otherwise, the money will be added back to the project, and will be used for project implementation.
Account Type(s):
Capital
Contract Start Date:
01/01/2011
Contract End Date:
02/29/2012
Current Contract Value:
$1,054,231
Expenditures:
$1,054,231

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete Environmental Clearance Documentation Or Prepare Biological Assessment A: 165. Complete Environmental Clearance Documentation Or Prepare Biological Assessment 12/31/2011 12/31/2011
Identify Projects B: 114. Project Pre-Work 12/31/2011 12/31/2011
Prepare Design & Layout C: 175. Prepare Design & Layout 12/31/2011 12/31/2011
Technical Review: Outside (FS&P) Projects In The John Day Basin D: 122. Technical Review Of Screens & Passage Projects 12/31/2011 12/31/2011
Remove Or Install Diversion Structure To Provide NOAA & ODFW Approved Fish Passage E: 84. Existing Passage Improvement 12/31/2011
Improve Fish Passage Structure F: 184. Passage Improvement 12/31/2011
Improve Fish Passage Structure G: 184. Passage Improvement (Placeholder) 12/31/2011
Install Fish Screen - #1 H: 69. Install Fish Screen - #1 12/31/2011 07/22/2011
Install Fish Screen - #2 I: 69. Install Fish Screen - #2 12/31/2011 09/09/2011
Install Fish Screen - #3 J: 69. Install Fish Screen - #3 12/31/2011
Install Fish Screen - #4 K: 69. Install Fish Screen - #4 12/31/2011 12/31/2011
Install Fish Screen - #5 L: 69. Install Fish Screen - #5 12/31/2011
Install Fish Screen - #6 M: 69. Install Fish Screen - #6 12/31/2011
Install Fish Screen - #7 N: 69. Install Fish Screen - #7 12/31/2011 12/31/2011
Install Fish Screen - #8 O: 69. Install Fish Screen - #8 12/31/2011
Install Fish Screen - #9 P: 69. Install Fish Screen - #9 12/31/2011
Install Fish Screen - #10 Q: 69. Install Fish Screen - #10 12/31/2011
Install Fish Screen - #11 R: 69. Install Fish Screen - #11 12/31/2011 08/15/2011
Install Fish Screen - #12 S: 69. Install Fish Screen - #12 12/31/2011 12/31/2011
Install Fish Screen - #13 T: 69. Install Fish Screen - #13 12/31/2011
Install Fish Screen - #14 U: 69. Install Fish Screen - #14 12/31/2011
Install Fish Screen - #15 V: 69. Install Fish Screen - #15 12/31/2011
Install Fish Screen - #16 W: 69. Install Fish Screen - #16 12/31/2011
Install Fish Screen - #17 X: 69. Install Fish Screen - #17 12/31/2011 12/31/2011
Install Fish Screen - #18 Y: 69. Install Fish Screen - #18 12/31/2011 09/30/2011
Install Fish Screen - #19 Z: 69. Install Fish Screen - #19 12/31/2011
Install Fish Screen - #20 AA: 69. Install Fish Screen - #20 12/31/2011 12/31/2011
Install Fish Screen - #21 AB: 69. Install Fish Screen - #21 12/31/2011 09/30/2011
Install Fish Screen - #22 AC: 69. Install Fish Screen - #22 12/31/2011 09/30/2011
Install Fish Screen - #23 AD: 69. Install Fish Screen - #23 12/31/2011
Install Fish Screen - #24 AE: 69. Install Fish Screen - #24 12/30/2011 12/31/2011
Install Fish Screen - #25 AF: 69. Install Fish Screen - #25 12/31/2011
Install Fish Screen - #26 AG: 69. Install Fish Screen - #26 12/31/2011
Install Fish Screen - #27 AH: 69. Install Fish Screen - #27 12/31/2011
Install Fish Screen - #28 AI: 69. Install Fish Screen - #28 12/31/2011
Install Fish Screen - #29 AJ: 69. Install Fish Screen - #29 12/31/2011 12/31/2011
Install Fish Screen - #30 AK: 69. Install Fish Screen - #30 12/31/2011 12/31/2011
Install Fish Screen - #31 AL: 69. Install Fish Screen - #31 12/31/2011
Install Fish Screen - #32 AM: 69. Install Fish Screen - #32 12/31/2011
Install Fish Screen - #33 AN: 69. Install Fish Screen - #33 12/31/2011
Install Fish Screen - #34 AO: 69. Install Fish Screen - #34 12/31/2011 12/31/2011
Install Fish Screen - #35 AP: 69. Install Fish Screen - #35 12/31/2011
Install Fish Screen - #36 AQ: 69. Install Fish Screen - #36 12/31/2011
Install Fish Screen - #37 AR: 69. Install Fish Screen - #37 12/31/2011
Install Fish Screen - #38 AS: 69. Install Fish Screen - #38 12/31/2011
Install Fish Screen - #39 AT: 69. Install Fish Screen - #39 12/31/2011
Install Fish Screen - #40 AU: 69. Install Fish Screen - #40 12/31/2011
Install Fish Screen - #41 AV: 69. Install Fish Screen - #41 12/31/2011
Install Fish Screen - #42 AW: 69. Install Fish Screen - #42 12/31/2011 12/31/2011
Install Fish Screen - #43 AX: 69. Install Fish Screen - #43 12/31/2011
Install Fish Screen - #44 AY: 69. Install Fish Screen - #44 12/31/2011 08/31/2011
Install Fish Screen - #45 AZ: 69. Install Fish Screen - #45 12/31/2011
Annual Report Submitted - Uploaded To BPA Website BB: 132. Produce Annual Report 02/28/2011 02/28/2011
Manage & Administer Projects BC: 119. Manage & Administer Projects 12/31/2011 12/31/2011
Install Fish Screen - #46 BD: 69. Install Fish Screen - #46 12/31/2011 12/31/2011
Install Fish Screen - #47 BE: 69. Install Fish Screen - #47 12/31/2011 12/31/2011
Install Fish Screen - #48 BF: 69. Install Fish Screen - #48 12/31/2011 12/31/2011
Install Fish Screen - #49 BG: 69. Install Fish Screen - #49 12/31/2011 12/31/2011
Install Fish Screen - #50 BH: 69. Install Fish Screen - #50 12/31/2011 12/31/2011
Install Fish Screen - #51 BI: 69. Install Fish Screen - #51 12/31/2011 12/31/2011
Install Fish Screen - #52 BJ: 69. Install Fish Screen - #52 12/31/2011 12/31/2011
Install Fish Screen - #53 BK: 69. Install Fish Screen - #53 12/31/2011 12/31/2011
Install Fish Screen - #54 BL: 69. Install Fish Screen - #54 12/31/2011 12/31/2011
Install Fish Screen - #55 BM: 69. Install Fish Screen - #55 12/31/2011 12/31/2011
Install Fish Screen - #56 BN: 69. Install Fish Screen - #56 (Placeholder) 12/31/2011
Install Fish Screen - #57 BO: 69. Install Fish Screen - #57 (Placeholder) 12/31/2011
Install Fish Screen - #58 BP: 69. Install Fish Screen - #58 (Placeholder) 12/31/2011
Install Fish Screen - #59 BQ: 69. Install Fish Screen - #59 (Placeholder) 12/31/2011
Install Fish Screen - #60 BR: 69. Install Fish Screen - #60 (Placeholder) 12/31/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 60 instances of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 60 instances of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
Cutthroat Trout, Westslope (O. c. lewisi)
  • 60 instances of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 60 instances of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
Trout, Interior Redband (O. mykiss gairdnerii)
  • 60 instances of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete Environmental Clearance Documentation Or Prepare Biological Assessment 01/01/2011
B 114 Project Pre-Work 01/01/2011
C 175 Prepare Design & Layout 01/01/2011
D 122 Technical Review Of Screens & Passage Projects 01/01/2011
E 84 Existing Passage Improvement
F 184 Passage Improvement
G 184 Passage Improvement (Placeholder)
H 69 Install Fish Screen - #1 01/01/2011
I 69 Install Fish Screen - #2 01/01/2011
J 69 Install Fish Screen - #3 01/01/2011
K 69 Install Fish Screen - #4 01/01/2011
L 69 Install Fish Screen - #5 01/01/2011
M 69 Install Fish Screen - #6 01/01/2011
N 69 Install Fish Screen - #7 01/01/2011
O 69 Install Fish Screen - #8 01/01/2011
P 69 Install Fish Screen - #9
Q 69 Install Fish Screen - #10 08/26/2011
R 69 Install Fish Screen - #11 01/01/2011
S 69 Install Fish Screen - #12 01/01/2011
T 69 Install Fish Screen - #13 01/01/2011
U 69 Install Fish Screen - #14 01/01/2011
V 69 Install Fish Screen - #15 01/01/2011
W 69 Install Fish Screen - #16 01/01/2011
X 69 Install Fish Screen - #17 01/01/2011
Y 69 Install Fish Screen - #18 01/01/2011
Z 69 Install Fish Screen - #19 01/01/2011
AA 69 Install Fish Screen - #20 01/01/2011
AB 69 Install Fish Screen - #21 01/01/2011
AC 69 Install Fish Screen - #22 01/01/2011
AD 69 Install Fish Screen - #23 01/01/2011
AE 69 Install Fish Screen - #24 01/01/2011
AF 69 Install Fish Screen - #25
AG 69 Install Fish Screen - #26 08/26/2011
AH 69 Install Fish Screen - #27 08/26/2011
AI 69 Install Fish Screen - #28 03/10/2011
AJ 69 Install Fish Screen - #29 03/10/2011
AK 69 Install Fish Screen - #30 01/01/2011
AL 69 Install Fish Screen - #31 03/10/2011
AM 69 Install Fish Screen - #32 08/26/2011
AN 69 Install Fish Screen - #33 08/26/2011
AO 69 Install Fish Screen - #34 03/10/2011
AP 69 Install Fish Screen - #35 03/10/2011
AQ 69 Install Fish Screen - #36 03/10/2011
AR 69 Install Fish Screen - #37
AS 69 Install Fish Screen - #38 08/26/2011
AT 69 Install Fish Screen - #39 08/26/2011
AU 69 Install Fish Screen - #40 03/10/2011
AV 69 Install Fish Screen - #41 01/01/2011
AW 69 Install Fish Screen - #42 03/10/2011
AX 69 Install Fish Screen - #43 03/10/2011
AY 69 Install Fish Screen - #44 03/10/2011
AZ 69 Install Fish Screen - #45 01/01/2011
BA 185 Periodic Status Reports for BPA 01/01/2011
BB 132 Produce Annual Report 01/01/2011
BC 119 Manage & Administer Projects 01/01/2011
BD 69 Install Fish Screen - #46 01/01/2011
BE 69 Install Fish Screen - #47 01/01/2011
BF 69 Install Fish Screen - #48 01/01/2011
BG 69 Install Fish Screen - #49 01/01/2011
BH 69 Install Fish Screen - #50 01/01/2011
BI 69 Install Fish Screen - #51 01/01/2011
BJ 69 Install Fish Screen - #52 01/01/2011
BK 69 Install Fish Screen - #53 01/01/2011
BL 69 Install Fish Screen - #54 01/01/2011
BM 69 Install Fish Screen - #55 01/01/2011
BN 69 Install Fish Screen - #56 (Placeholder)
BO 69 Install Fish Screen - #57 (Placeholder)
BP 69 Install Fish Screen - #58 (Placeholder)
BQ 69 Install Fish Screen - #59 (Placeholder)
BR 69 Install Fish Screen - #60 (Placeholder)