Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Michele Andersen | Kalispel Tribe | No | Contract Manager | mandersen@knrd.org | (509) 447-7283 |
Todd Andersen | Kalispel Tribe | Yes | Technical Contact | tandersen@knrd.org | (509) 447-7245 |
Hannah Dondy-Kaplan | Bonneville Power Administration | Yes | Env. Compliance Lead | hadondy-kaplan@bpa.gov | (503) 230-4071 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Joe Maroney | Kalispel Tribe | Yes | Supervisor | jmaroney@knrd.org | (509) 447-7272 |
Carmel Melton | Kalispel Tribe | No | Administrative Contact | cmelton@kalispeltribe.com | (509) 447-7239 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
Nancy Weintraub | Bonneville Power Administration | No | Interested Party | nhweintraub@bpa.gov | (503) 230-5373 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Completed Environmental Clearance | B: 165. Obtain Required Permits | 07/22/2011 | 07/11/2011 | |
Signed Agreements | C: 114. Interagency Coordination/planning for Stream Restoration and Native Fish Recovery Actions | 02/29/2012 | 02/29/2012 | |
Updated Fisheries Database | D: 160. Maintain Databases | 02/29/2012 | 02/29/2012 | |
Maintained Riparian Fencing | E: 186. Maintain Previously Installed Fence. | 07/15/2011 | 07/14/2011 | |
Instream Structure Integrity Maintained | F: 186. Maintain Instream Structures | 02/29/2012 | 02/29/2012 | |
Largemouth bass habitat enhancement maintenance | G: 186. Maintain Largemouth Bass Habitat Structures | 11/30/2011 | 11/30/2011 | |
750 potted plants. | H: 47. Nursery Development | 07/29/2011 | 07/14/2011 | |
Goose Creek Phase I Final Design | I: 174. Goose Creek Phase I Final Design | 07/22/2011 | 06/01/2011 | |
Nonnative Fish Barrier | J: 190. Goose Creek Non Native Fish Barrier | 09/30/2011 | 09/30/2011 | |
Completed 2010 Progress Report | K: 132. FY'10 Progress Report | 08/11/2011 | 09/30/2011 | |
Project Management | L: 119. Project Management | 02/29/2012 | 02/29/2012 |
Primary Focal Species | Work Statement Elements |
---|---|
Bass, Largemouth (Micropterus salmoides) |
|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 03/01/2011 | ||||||
B | 165 | Obtain Required Permits | 03/01/2011 | ||||||
C | 114 | Interagency Coordination/planning for Stream Restoration and Native Fish Recovery Actions | 03/01/2011 | ||||||
D | 160 | Maintain Databases | 03/01/2011 | ||||||
E | 186 | Maintain Previously Installed Fence. | 03/01/2011 | ||||||
F | 186 | Maintain Instream Structures | 03/01/2011 | ||||||
G | 186 | Maintain Largemouth Bass Habitat Structures | 03/01/2011 | ||||||
H | 47 | Nursery Development | 03/01/2011 | ||||||
I | 174 | Goose Creek Phase I Final Design | 03/01/2011 | ||||||
J | 190 | Goose Creek Non Native Fish Barrier | 11/30/2011 | ||||||
K | 132 | FY'10 Progress Report | 03/01/2011 | ||||||
L | 119 | Project Management | 03/01/2011 |