Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 52041: 2008-458-00 EXP STEELHEAD KELT RECONDITIONING
Project Number:
Title:
Steelhead Kelt Reconditioning
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Columbia Upper Middle 100.00%
Contract Number:
52041
Contract Title:
2008-458-00 EXP STEELHEAD KELT RECONDITIONING
Contract Continuation:
Previous: Next:
46618: 2008-458-00 EXP ACCORD STEELHEAD KELT RECONDITIONING
  • 55957: 2008-458-00 EXP STEELHEAD KELT RECONDITIONING
Contract Status:
Closed
Contract Description:
The goal of this project is to increase the abundance of naturally produced Upper Columbia River steelhead on their natural spawning grounds.  Project objectives include: (1) Implementing steelhead kelt reconditioning program in Upper Columbia River to increase natural origin steelhead spawner abundance relative to current conditions, (2) Evaluating kelt survival and program effectiveness, and (3) Collaborating with on going M&E studies to document the reproductive success of reconditioned kelts after release.  The scope of this contract covers steps critical to development and implementation of a kelt reconditioning program in the Upper Columbia River.  Activities expected to be completed within the contract period include the development of a site plan for the kelt reconditioning facility and construction of the facility.  Coordination with on-site visits at capture and reconditioning locations with affected stakeholders (USFWS, WDFW, Chelan PUD and Douglas PUD) will take place.  Two studies will be conducted during this contract period, a live spawning/fucundity study and a trapping study, will determine potential sources for natural origin steelhead kelts that to be included in the program.  The work elements to be performed under this contract will ensure that the infrastructure and methodologies are in place so that kelt collection and reconditioning activities may begin in the spring of 2012.
Account Type(s):
Expense
Contract Start Date:
03/01/2011
Contract End Date:
04/30/2012
Current Contract Value:
$771,416
Expenditures:
$771,416

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matthew Abrahamse Yakama Confederated Tribes Yes Technical Contact abrm@yakamafish-nsn.gov (509) 996-3122
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Roy Beaty Bonneville Power Administration Yes COR rebeaty@bpa.gov (503) 230-5213
Monica Clark Yakama Confederated Tribes Yes Administrative Contact monica@yakama.com (509) 865-5121x6338
Cory Kamphaus Yakama Confederated Tribes Yes Technical Contact kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Keely Murdoch Yakama Confederated Tribes Yes Technical Contact murk@yakamafish-nsn.gov (509) 548-2206
Steve Parker Yakama Confederated Tribes No Interested Party pars@yakamafish-nsn.gov (509) 865-6262x6342
Thomas Scribner Yakama Confederated Tribes Yes Contract Manager scrt@yakamafish-nsn.gov (503) 331-9850
Paul Ward Yakama Confederated Tribes Yes Supervisor warp@yakamafish-nsn.gov (509) 949-4129
Nancy Weintraub Bonneville Power Administration Yes Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. # Manage and administer 2011 upper Columbia kelt reconditioning project 12/01/2011 12/01/2011
Dryden Property Purchase C: 172. Acquisition activities for Dryden Property 01/31/2012 01/31/2012
Environmental Compliance Documentation D: 165. ESA compliance for project implementation 01/31/2012 01/31/2012
Operational Kelt Reconditioning Facility E: 171. # Construct kelt reconditioning facility 04/30/2012 01/31/2012
2011 Progress Report F: 132. Submit progress report for the period (1/2011) to (12/2011) 01/31/2012 01/31/2012
Reconditioning facility plans G: 175. Produce kelt reconditioning facility design 04/15/2011 04/15/2011
Live spawning study final report H: 157. Steelhead live spawning study 01/31/2012 01/31/2012
Methow Kelt Capture test I: 66. Test prototype trap designs 01/31/2012 01/31/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2011
B 119 # Manage and administer 2011 upper Columbia kelt reconditioning project 03/01/2011
C 172 Acquisition activities for Dryden Property 03/01/2011
D 165 ESA compliance for project implementation 03/01/2011
E 171 # Construct kelt reconditioning facility 11/11/2011
F 132 Submit progress report for the period (1/2011) to (12/2011) 03/01/2011
G 175 Produce kelt reconditioning facility design 03/01/2011
H 157 Steelhead live spawning study 03/01/2011
I 66 Test prototype trap designs 03/21/2011