Contract 53638: 1998-019-00 EXP WIND RIVER WATERSHED UCD
Project Number:
Title:
Wind River Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
53638
Contract Title:
1998-019-00 EXP WIND RIVER WATERSHED UCD
Contract Continuation:
Previous: Next:
49229: 1998-019-00 EXP WIND RIVER WATERSHED UCD
  • 57840: 1998-019-00 EXP WIND RIVER WATERSHED UCD
Contract Status:
Closed
Contract Description:
This contract supports and is part of the Wind River Watershed Project, initiated in 1998.  The project's focus is on restoration of Wind River steelhead.  In 1998, the National Marine Fisheries Service listed the steelhead of the lower Columbia river as "threatened" under the Endangered Species Act.  In 1997, the Washington Department of Fish and Wildlife rated the status of the Wind River summer run steelhead as critical.  Due to the status of this stock, the Wind River summer steelhead have the highest priority for recovery/restoration in the state of Washington's Lower Columbia Steelhead Conservation Initiative.  Project participants are the Underwood Conservation District, US Geological Survey, US Forest Service, and Washington Department of Fish and Wildlife.  

This contract continues UCD support and participation in the project.  Underwood Conservation District will provide habitat restoration work in 2011-12.  Included in this contract will be removal of noxious weeds (primarily scotch broom), planting of native vegetation along riparian areas, providing the appropriate environmental compliance documentation for this work, and developing new projects with landowners that support the recovery of Wind River steelhead.  Additionally, UCD will utilize BPA dollars to match other grant funds for the preparation of the Little Wind River Community Habitat Restoration Project.  This project will likely be constructed in the summer of 2012, but this contract will include finalizing of permits, engineering, and design work, as well as conducting the bid process and contracting with a subcontractor for the construction work to occur in FY12.  Other work under this FY11 contract will include producing periodic (quarterly) status reports, annual reports, as well as managing and administering the project.
Account Type(s):
Expense
Contract Start Date:
07/01/2011
Contract End Date:
06/30/2012
Current Contract Value:
$98,108
Expenditures:
$98,108

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jamie Gomez Underwood Conservation District (UCD) Yes Contract Manager jamiegomez@gorge.net (509) 493-1936
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Ann Gross Underwood Conservation District (UCD) No Administrative Contact ann@ucdwa.org (509) 493-1936
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Tova Tillinghast Underwood Conservation District (UCD) Yes Supervisor tova@ucdwa.org (509) 493-1936
Adrianne Zuckerman Underwood Conservation District (UCD) No Contract Manager adriannezuckerman@gorge.net (509) 493-1936


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit Final to COTR B: 119. Manage and Administer Projects 05/01/2012 05/08/2012
Environmental Compliance Support C: 165. Produce Environmental Compliance Documentation 06/30/2012
Final report uploaded to the BPA website D: 132. Submit Annual Report for the period of July 2010 to June 2011 03/15/2012 04/17/2012
25 Acres of noxious weeds controlled E: 53. Remove Noxious Weeds 10/31/2011 10/01/2011
16 Acres planted F: 47. Plant Native Vegetation 04/05/2012 04/16/2012
Complete Engineer/Design and Subcontracting Work for Little Wind River Habitat Project G: 175. Little Wind River Engineer and Design 06/30/2012
Summarize pre-project site monitoring data H: 157. Little Wind River Pre-Project Site Monitoring 06/29/2012
Up-to-date Watershed Enhancement Project List I: 114. Identify and Develop Future Projects 06/05/2012 06/29/2012
Temperature Data Stored in Water Quality Database J: 157. Stream Temperature Monitoring 06/29/2012 06/29/2012
Watershed map of areas needing vegetation enhancement K: 157. Vegetation Monitoring 06/29/2012 06/29/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2011
B 119 Manage and Administer Projects 07/01/2011
C 165 Produce Environmental Compliance Documentation 07/01/2011
D 132 Submit Annual Report for the period of July 2010 to June 2011 07/01/2011
E 53 Remove Noxious Weeds 09/26/2011
F 47 Plant Native Vegetation 09/26/2011
G 175 Little Wind River Engineer and Design 07/01/2011
H 157 Little Wind River Pre-Project Site Monitoring 07/01/2011
I 114 Identify and Develop Future Projects 07/01/2011
J 157 Stream Temperature Monitoring 07/01/2011
K 157 Vegetation Monitoring 07/01/2011