Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 54762: 1995-057-00 EXP S I W M - IDF&G ADMINISTRATION
Project Number:
Title:
Southern Idaho Wildlife Mitigation
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Middle Snake Boise 10.00%
Upper Snake Snake Upper 90.00%
Contract Number:
54762
Contract Title:
1995-057-00 EXP S I W M - IDF&G ADMINISTRATION
Contract Continuation:
Previous: Next:
49724: 1995-057-00 EXP S I W M - IDF&G -- ADMINISTRATION
  • 59754: 1995-057-00 EXP S I W M - IDF&G ADMINISTRATION
Contract Status:
Closed
Contract Description:
This Administrative contract 1) provides opportunity to identify and pursue new mitigation opportunities, and 2)provides support for O + M activities on the Boise River properties. Operation, maintenance, monitoring, and evaluation activities are also funded under The Deer Parks and Centennial Marsh contracts.

The project is a continuation of activities associated with the Southern Idaho Wildlife Mitigation Program in the Middle Snake Province (225 acres Boise River property) and the Upper Snake Province (Deer Parks, Quarter Circle O, Centennial Marsh, 7 owned properties totaling 8,292 acres and a two conservation easements totaling 1,222 acres). Additional mitigation implementation activities would be associated with Palisades, Minidoka ,  Anderson Ranch and Black Canyon complex projects, including the Deadwood project, which while included in the Council's Fish and Wildlife Program, is not currently recognized by BPA as part of the FCRPS.

The purpose of managing these properties and administering the program is to protect BPA's investment in past mitigation implementation. The purpose of new mitigation implementation activities is to assist BPA and the Northwest Power and Conservation Council with meeting the mitigation debt identified in the Columbia Basin Fish and Wildlife Program.
Account Type(s):
Expense
Contract Start Date:
10/01/2011
Contract End Date:
09/30/2012
Current Contract Value:
$78,164
Expenditures:
$78,164

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Ensure completion of environmental compliance B: 165. Ensure completion of environmental compliance for O&M contracts 09/30/2012 09/26/2012
Complete the coordination of field activities C: 114. Manage field activities 09/30/2012 09/26/2012
Conduct pre-acquisition activities D: 172. Conduct pre-acquisition activities 09/30/2012 09/26/2012
Complete coordination activities E: 189. Liaison with other entities 09/30/2012 09/26/2012
Sustain I&E Program F: 99. Implement information and education (I&E) program 09/30/2012 09/26/2012
Attach Progress Report in Pisces G: 132. Submit Progress Report for the period 10/2010 to 09/2011 03/30/2012 03/30/2012
Complete project administration H: 119. Manage and administer the contract and tasks included in the contract 09/30/2012 09/26/2012
Maintain upland vegetation on the Boise River property I: 197. Maintain upland vegetation on the Boise River property 09/30/2012 09/26/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2011
B 165 Ensure completion of environmental compliance for O&M contracts 10/01/2011
C 114 Manage field activities 10/01/2011
D 172 Conduct pre-acquisition activities 10/01/2011
E 189 Liaison with other entities 10/01/2011
F 99 Implement information and education (I&E) program 10/01/2011
G 132 Submit Progress Report for the period 10/2010 to 09/2011 10/01/2011
H 119 Manage and administer the contract and tasks included in the contract 10/01/2011
I 197 Maintain upland vegetation on the Boise River property 10/01/2011