Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 54966: 2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
54966
Contract Title:
2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES
Contract Continuation:
Previous: Next:
23380 REL 6: 2007-398-00 CAP MANASTASH CONSTRUCTION SERVICES - FISHPRO
Contract Status:
Closed
Contract Description:
The following scope of services is to be performed by HDR Engineering, Inc. (HDR) to support the ongoing multi-disciplinary implementation process associated with the Manastash Creek Restoration program. This task order is specifically oriented towards: removal of the abandoned dam; the design and integration of a new water control structure at the Barnes Road Diversion Structure.
Account Type(s):
Capital
Contract Start Date:
09/30/2011
Contract End Date:
09/30/2013
Current Contract Value:
$253,985
Expenditures:
$253,985

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Sarah Bettmann HDR Constructors, Inc. Yes Contract Manager sarah.bettmann@hdrinc.com (816) 412-1285
Rossana Callejas Bonneville Power Administration No Interested Party rxcallejas@bpa.gov (503) 230-7558
Ed Donahue Fishpro, Inc. Yes Supervisor ed.donahue@hdrinc.com (253) 858-5262
Michael Garello Fishpro, Inc. Yes Contract Manager mike.garello@hdrinc.com (253) 858-5635
Sherry Jeffery HDR Engineering, Inc. Yes Technical Contact sherry.jeffery@hdrinc.com (253) 858-5262
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Sherry Swanson Kittitas County Conservation District No Interested Party sherry-swanson@conservewa.net (509) 925-3352x6
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Efficiently managed project B: 119. Manage and Administer Project 09/30/2013 09/30/2013
100% design and specs C: 175. Design for the Removal of Abandoned Dam 07/02/2012 01/04/2013
Submittal of Permit Applications D: 165. Produce Environmental Documentation Materials 09/30/2013 03/15/2013
Effectively managed construction project F: 100. Construction Management for Barnes Facilities 05/31/2013 06/28/2013
Completed O&M plan G: 174. Produce O&M Plan/Manual for Barnes Facilities 02/28/2013 03/28/2013
Technical Reviews J: 122. Technical Coordination with USFWS & WDFW for Pit Tag Reader Design & Installation 05/31/2013 03/29/2013
Install SCADA Telemetry and Flow Monitoring Devices K: 148. Install SCADA Telemetry and Flow Monitoring Devices 07/01/2013 07/01/2013
Easement Required L: 172. NEW CCR26859 Easement Valuation & Acquisition Services for Siemore Parcel 07/01/2013 07/01/2013
Existing Conditions Summary Report M: 175. NEW CCR26859 Evaluate Abandoned Dam Existing Conditions 01/04/2013 01/04/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 122 Provide Technical Review and Recommendation
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 148 Install Flow Measuring Device
  • 2 instances of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 11/01/2011
B 119 Manage and Administer Project 11/01/2011
C 175 Design for the Removal of Abandoned Dam 11/01/2011
D 165 Produce Environmental Documentation Materials 11/01/2011
E 100 Construction Management for Removal of Abandoned Dam 11/01/2011
F 100 Construction Management for Barnes Facilities 11/01/2011
G 174 Produce O&M Plan/Manual for Barnes Facilities 11/01/2011
H 172 Easement Valuation & Acquisition Services for Reed, Hatfield, Anderson and Abandoned Dam Projects 11/01/2011
I 132 No progress report required. 11/01/2011
J 122 Technical Coordination with USFWS & WDFW for Pit Tag Reader Design & Installation 11/01/2011
K 148 Install SCADA Telemetry and Flow Monitoring Devices
L 172 NEW CCR26859 Easement Valuation & Acquisition Services for Siemore Parcel 09/30/2011
M 175 NEW CCR26859 Evaluate Abandoned Dam Existing Conditions 09/30/2011