SOW Report
Contract 55969: 2003-017-00 EXP ISEMP - SO FORK RESEARCH
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
55969
Contract Title:
2003-017-00 EXP ISEMP - SO FORK RESEARCH
Contract Continuation:
Previous: Next:
50900: 2003-017-00 EXP ISEMP
  • 59513: 2003-017-00 EXP ISEMP - SO FORK RESEARCH
Contract Status:
Closed
Contract Description:
PURPOSE AND NEED FOR  MAY 2012 AMENDMENT:
This CCR provides additional funding to support answering questions about GRTS study designs for fish sampling for the 2012 and 2013 field seasons and development of production-ready analysis models. Results of 2010-2011 fish data analysis occurring in early 2012 suggested specific questions regarding fish sampling design be addressed prior to the 2012 and 2013 field seasons.  Similarly, supplemental funding allocated to production-ready analysis models is needed to finalize models for use post 2012 field season, as model updates will require more time than previously allocated. These models will be tested and validated using 2012 field data. These needs surfaced after the original contract date of Dec 1, 2011.  THE NEW WORK IS IDENTIFIED IN NEW WE's W-156 AND X-162.


Note: This contract has no inventory, nothing carried over, and no equipment purchases planned.
Note2: All EC issues are covered by NMFS Section 7,  on the overall Bridge Creek Restoration and Monitoring Project, Wheeler County, OR.

Contract Description: The Integrated Status and Effectiveness Monitoring Program (ISEMP, 2003-017-00) is an ongoing collaborative effort to design, test, implement and evaluate Status and Trends Monitoring for salmon and steelhead populations and their habitat, and watershed-scale Effectiveness Monitoring for management actions impacting salmon and steelhead populations and habitat in the Interior Columbia River Basin.

ISEMP explicitly addresses work requirements of many 2008 FCRPS Biological Opinion RPAs (56.1, 56.2, 56.3, 57.1, 57.2, 57.3, 57.4, 57.5) and is directly related to additional 2008 FCRPS Biological Opinion implementation strategy requirements and recommendations. ISEMP takes a pilot-project approach to the research and development of monitoring by implementing experimental programs in several major subbasins of the Interior Columbia: the Wenatchee, Entiat, Methow, John Day, South Fork Salmon and Lemhi River basins. The overall goal of the project is to provide regional salmon management agencies with the data, information and tools necessary to design efficient and effective monitoring programs.

Specifically, ISEMP generates quantitative guidance on and examples of: the robustness and limitations of population and habitat monitoring protocols, indicators and metrics; sampling design approaches for the distribution of monitoring effort in time and space; analytical approaches to the evaluation of monitoring data, information and programs; effective data management and communication designs that support the use, standardization and compilation of implementation, compliance, status, trends and effectiveness monitoring data by regional data generators and decision makers; and finally the design and implementation of watershed-scale restoration actions to maximize both the biological impact and associated learning opportunities resulting from the design and implementation strategy.

Through its work to date, ISEMP has developed expertise in the coordination and implementation of large-scale monitoring data collection programs. Applying this experience, ISEMP coordinates the installation, maintenance and calibration of in-stream PIT tag arrays across the Snake River basin and is designing and coordinating the implementation of a Columbia River basin-wide stream habitat status and trends monitoring. These programmatic implementation facets of ISEMP leverage previous experience with logistics and social factors to effectively implement comprehensive, standardized monitoring research and development at an unprecedented scale.  

This contract is one of several contracts that will implement this project.  Each contract is responsible for an end of contract progress report.  Additionally, a project level "synthesis report" will also be produced under this project and data and analysis from this contract will be utilized in the production of that project level report.  The synthesis report is a deliverable under the TerraQua contract (not this contract) under this project.

Volk Consulting facilitates data flow, work flow and management (protocol development, data entry, data qa/qc, data delivery, GIS data management and database output) for the ISEMP pilot projects. Volk Consulting also participates as a project coordinator and data analyst within ISEMP.
Account Type(s):
Expense
Contract Start Date:
12/01/2011
Contract End Date:
11/30/2012
Current Contract Value:
$598,955
Expenditures:
$598,955

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Christopher Beasley Quantitative Consultants Inc Yes Interested Party chris@qcinc.org (360) 620-2883
Nick Bouwes Eco Logical Research Yes Interested Party nbouwes@gmail.com (435) 760-0771
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Chris Jordan National Oceanic and Atmospheric Administration Yes Supervisor chris.jordan@noaa.gov (541) 754-4629
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Pamela Nelle Terraqua, Inc. Yes Interested Party pamela@terraqua.biz (509) 885-8143
Steve Rentmeester Environmental Data Services Yes Interested Party environmentaldataservices@gmail.com (503) 247-8431
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Carol Volk South Fork Research, Inc. Yes Contract Manager carol@southforkresearch.org (206) 240-0301
Jody White Quantitative Consultants Inc Yes Interested Party jody@qcinc.org (208) 860-5269


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation of Environmental Compliance A: 165. Provide Environmental Compliance Documentation for Work Element U. 11/30/2012 11/30/2012
Review documents produced by ISEMP personnel and meeting participation D: 174. Participate in RME planning process for pilot basins 11/30/2012 11/30/2012
Web accessible spatial datasets for pilot basins E: 161. Organization and updates of spatial datasets for pilot basins 11/30/2012 11/30/2012
Data summary and QAQC support F: 161. QA and summary of Bridge Creek data 11/30/2012 11/30/2012
Tabular data delivery to ISEMP analysts G: 162. Tabular data support for data analysis in pilot basins 11/30/2012 11/30/2012
Manuscript of Wenatchee Status and Trend Monitoring H: 183. Wenatchee Status and Trend monitoring project journal article 11/30/2012
Submit peer-reviewed manuscript about Bridge Creek IMW I: 183. Manuscript for Bridge Creek project (riparian planting or monitoring dataset) 11/30/2012 11/30/2012
Field data in electronic format J: 157. Collect field data for monitoring BDS structures and vegetation in Bridge Creek 11/30/2012 11/30/2012
Summary of Bridge Creek 2011 data K: 162. Bridge Creek analysis of climate, groundwater, and riparian planting data 08/31/2012 08/31/2012
Data in Access databases and annual report of riparian planting activities L: 47. Plant and fence riparian stakes along Bridge Creek 11/30/2012 11/30/2012
Funding Package - Submit draft to COTR M: 119. Bridge Creek IMW Project Management 10/01/2012 10/01/2012
Meeting notes N: 189. Data management coordination for pilot basins 11/30/2012 11/30/2012
ISEMP Data management guidance documentation O: 141. Develop Data Management Guidance Documents 11/30/2012 11/30/2012
Log of maintenance and bug repair for STEM P: 160. Maintenance of STEM Databank 11/30/2012 11/30/2012
Documentation of metric and protocol metadata Q: 156. Metadata development for ISEMP projects 11/30/2012 11/30/2012
Website updates and STEM website summary queries R: 161. ISEMP and STEM website development and updates 11/30/2012 11/30/2012
Manuscript of data QAQC in ISEMP S: 183. Data handling strategies for multi-agency monitoring programs 08/31/2012 08/31/2012
Feasibility plan and/or implementation of web services for ISEMP databases T: 160. Enhance interoperability of ISEMP databases 10/01/2012 10/31/2012
QA report for each dataset reviewed U: 161. QA and Summary of ISEMP data 11/30/2012 11/30/2012
Attach Progress Report in Pisces V: 132. Submit Final Progress Report for contract 50900 (12/1/2010) to 11/30/2011) 11/30/2012 11/30/2012
Updated documentation of study designs for fish sampling assumptions and uncertainty estimates W: 156. Assess and develop statistical designs and uncertainty estimation procedures for ISEMP 11/30/2012 11/30/2012
Completion of 2 modeling projects X: 162. Modeling and analysis of ISEMP fish data 11/30/2012 11/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 4 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 183 Produce Journal Article
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 183 Produce Journal Article
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 4 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 183 Produce Journal Article
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 183 Produce Journal Article
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide Environmental Compliance Documentation for Work Element U. 12/01/2011
B 132 Produce annual report for SFR 12/01/2011
C 185 Periodic Status Reports for BPA 12/01/2011
D 174 Participate in RME planning process for pilot basins 12/01/2011
E 161 Organization and updates of spatial datasets for pilot basins 12/01/2011
F 161 QA and summary of Bridge Creek data 12/01/2011
G 162 Tabular data support for data analysis in pilot basins 12/01/2011
H 183 Wenatchee Status and Trend monitoring project journal article 12/01/2011
I 183 Manuscript for Bridge Creek project (riparian planting or monitoring dataset) 12/01/2011
J 157 Collect field data for monitoring BDS structures and vegetation in Bridge Creek 12/13/2011
K 162 Bridge Creek analysis of climate, groundwater, and riparian planting data 12/01/2011
L 47 Plant and fence riparian stakes along Bridge Creek 12/13/2011
M 119 Bridge Creek IMW Project Management 12/01/2011
N 189 Data management coordination for pilot basins 12/01/2011
O 141 Develop Data Management Guidance Documents 12/01/2011
P 160 Maintenance of STEM Databank 12/01/2011
Q 156 Metadata development for ISEMP projects 12/01/2011
R 161 ISEMP and STEM website development and updates 12/01/2011
S 183 Data handling strategies for multi-agency monitoring programs 12/01/2011
T 160 Enhance interoperability of ISEMP databases 12/01/2011
U 161 QA and Summary of ISEMP data 12/01/2011
V 132 Submit Final Progress Report for contract 50900 (12/1/2010) to 11/30/2011) 12/01/2011
W 156 Assess and develop statistical designs and uncertainty estimation procedures for ISEMP 12/01/2011
X 162 Modeling and analysis of ISEMP fish data 12/01/2011